Proposal to build runway number 3 at Long Thanh airport

HÀ ANH CHIẾN |

The construction of Long Thanh airport is being accelerated, all packages are meeting and exceeding the schedule. The Airports Corporation of Vietnam (ACV) and Dong Nai province have proposed to continue implementing the third runway.

Many bidding packages at Long Thanh airport achieved and exceeded schedule

According to the Vietnam Airports Corporation (ACV), the construction package 4.6 of the Long Thanh airport runway phase 1 is expected to be 3 months ahead of schedule. The runway is expected to be completed and put into technical operation before April 30, 2025.

For the 5.10 package of the passenger terminal construction, the contractors are currently fabricating and assembling the steel roof structure according to the plan and schedule in the contract; construction is expected to be completed by April 2025. Then, in June 2025, a trial operation will be conducted to officially open Long Thanh airport phase 1 on September 2, 2026.

According to ACV, a large construction site has been established on the project site with the participation of hundreds of construction teams with more than 6,000 personnel and 2,700 construction equipment. The packages under construction at the site have been inspected, supervised and accepted according to the project's technical standards, ensuring the required quality and progress.

Mr. Nguyen Tien Viet - Deputy General Director in charge - Vietnam Airports Corporation (ACV) said: The investor is actively coordinating with contractors to deploy and maintain progress to put Long Thanh airport phase 1 into operation by September 2, 2026. Long Thanh airport is a driving force project for the whole Southern region and the whole country. ACV and Dong Nai province want to deploy runway number 3 soon.

Proposal to build runway number 3

ACV proposed to invest in the construction of an additional runway in phase 1 of the Long Thanh airport project (adjusting the construction phase of runway number 3 from phase 3 to phase 1, with an estimated total investment of VND 3,455 billion (not exceeding the total investment of component project 3 currently being implemented by ACV), implemented with ACV's legal capital.

Currently, ACV has arranged enough financial resources, human resources, and infrastructure to be ready to immediately deploy runway No. 3 after the National Assembly approves the investment policy. ACV plans to design and approve the project from the first quarter of 2025 to the third quarter of 2025, with a construction period of 12 months (expected from the fourth quarter of 2025 to the end of the third quarter of 2026), test run, and complete procedures for putting it into operation in the fourth quarter of 2026.

ACV also proposed adjusting the implementation time of Phase 1 of the Long Thanh airport project to 2026.

Mr. Vo Van Phi - Vice Chairman of Dong Nai Provincial People's Committee - said that according to the planning, there are already runways, instead of implementing in the later phase, if this phase has favorable factors, it should be implemented immediately. Currently, the land is available, the capital, according to ACV, can also be balanced. Therefore, adjusting to build more runways at this time is reasonable.

In addition to the proposal to adjust Resolution 94/2015/QH13 dated June 25, 2015 of the National Assembly, ACV also said that after putting into operation, 80% of international passengers will travel to and from Long Thanh airport, most of whom will want to go to Ho Chi Minh City. Therefore, the expansion of the Ho Chi Minh City - Long Thanh expressway is one of the important factors for Long Thanh airport to be put into operation and operate effectively.

ACV proposed that the Government pay attention to directing the acceleration of the project to expand the highway connecting Long Thanh airport with Ho Chi Minh City to ensure the project's effectiveness when put into operation.

On November 13, the adjustment of the investment policy for the Long Thanh International Airport Project in Resolution No. 94/2015/QH13 of the National Assembly was discussed at the 8th Session of the 15th National Assembly.

According to ACV, the 6.12 package for the construction of traffic routes No. 1 and No. 2 connecting Long Thanh airport has so far achieved an actual construction volume value of about VND 1,321 billion, equivalent to 55.3% of the contract value. Regarding the general progress, the construction of route No. 1 will be completed in November 2025; the construction of the intersection of route No. 1 and Bien Hoa - Vung Tau expressway will be completed in August 2025; the construction of the intersection of route No. 2 and Ho Chi Minh City - Long Thanh - Dau Giay expressway will be completed in October 2025; the project will be completed and handed over for use in December 2025.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Submit to the National Assembly to build runway number 3 of Long Thanh airport

|

The immediate construction of runway number 3 at Long Thanh airport will meet the needs of phase 1 exploitation.

Large contract worth 7,200 billion VND at Long Thanh airport ahead of schedule

|

Dong Nai - Package 4.6 for the construction of Long Thanh airport runway is 3 months ahead of schedule, according to the Airports Corporation of Vietnam (ACV).

Simultaneously starting construction of many large packages at Long Thanh airport

|

Dong Nai - Vietnam Airports Corporation (ACV) has just simultaneously started construction of many important packages worth thousands of billions of VND at the Long Thanh airport project.

Clarifying responsibility for issuing wrong red books on prison land

|

Lam Dong - Provincial inspectors determined that 4.29 hectares of land of Dai Binh Prison had been illegally granted red books by local authorities to 7 households.

Inadequate treatment of officials and workers

|

National Assembly delegates said that the treatment of officials and employees working at drug rehabilitation facilities is not commensurate with the requirements and tasks of the job.

Nam Dinh has a new Provincial Party Secretary

|

Nam Dinh - Mr. Dang Khanh Toan was mobilized and appointed by the Politburo to hold the position of Secretary of Nam Dinh Provincial Party Committee.

Go Cong sea dike "fluctuates" before monsoon season

|

Tien Giang - Some sections of the Go Cong sea dike are degraded, local authorities in Go Cong Dong district have proposed investing in wave-reducing dikes.

Sad news

|

Mr. Ignatius Do Van Luan, born in 1956, father of comrade Do Thi Yen Phuong, father-in-law of comrade Nguyen Van Quang - reporter of Lao Dong Newspaper working at the Representative Office in the Mekong Delta, passed away at 2:00 p.m. on November 13, 2024, October 13, Giap Thin year. He was 68 years old.

Submit to the National Assembly to build runway number 3 of Long Thanh airport

PHẠM ĐÔNG |

The immediate construction of runway number 3 at Long Thanh airport will meet the needs of phase 1 exploitation.

Large contract worth 7,200 billion VND at Long Thanh airport ahead of schedule

HÀ ANH CHIẾN |

Dong Nai - Package 4.6 for the construction of Long Thanh airport runway is 3 months ahead of schedule, according to the Airports Corporation of Vietnam (ACV).

Simultaneously starting construction of many large packages at Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - Vietnam Airports Corporation (ACV) has just simultaneously started construction of many important packages worth thousands of billions of VND at the Long Thanh airport project.