Immediately after the Tet holiday, the departments and agencies of Lam Dong province urgently carried out key tasks. Among them, completing procedures to start the two expressway projects Tan Phu - Bao Loc and Bao Loc - Lien Khuong before April 30, under the direction of Chairman of the Provincial People's Committee Tran Hong Thai.
These are the last two expressway projects of the Dau Giay - Lien Khuong expressway. The completion of the expressway system through Lam Dong will expand strategic trade with the southern provinces.
The Tan Phu - Bao Loc Expressway project is about 66km long, with a total investment of 17,200 billion VND. The project proposal unit is a consortium of investors represented by Deo Ca Group Joint Stock Company.
The Bao Loc - Lien Khuong Expressway project is nearly 74km long, with a total investment of about 19,521 billion VND. The project proposal unit is a consortium of investors represented by Phuong Trang Group Investment Joint Stock Company.
To ensure progress, Lam Dong province proactively reports to the central government any problems and promptly finds solutions.
Relevant departments also coordinate with investors to complete documents to soon start construction and disburse allocated capital.
In 2025, Lam Dong province is also determined to disburse public investment capital from the beginning of the year, with the goal of achieving over 95% of the disbursement plan by December 31, 2025. Backlogged projects will be reviewed and completely resolved.