On October 11, according to a reporter from Lao Dong Newspaper, the construction site of the rest stop on the Ham Nghi - Vung Ang expressway section in Cam Hung commune is being accelerated by Xuan Khiem Group Joint Stock Company.
Many machines and workers are focusing on paving the yard and parking lot. While the gas station and the toilet system on both sides (both North - South and South - North) of this rest stop have been basically completed.

The rest stop on the Ham Nghi - Vung Ang expressway section has an area of 10 hectares (5 hectares on each side), and will be implemented from April 2025.
Previously, on September 10, speaking with a reporter from Lao Dong Newspaper, Mr. Dinh Van Bay - Deputy General Director of Xuan Khiem Group - said that it is expected that in 10 days (ie around the end of September), the unit will put into operation the temporary rest stop on the Ham Nghi - Vung Ang expressway in both directions.
This temporary rest stop has a parking lot containing about 200 cars parked on a paved yard, with a fuel station, a restaurant, and a guaranteed restroom.


However, up to now, the plan to put the temporary rest stop into operation from the end of September that Xuan Khiem Group has proposed has not been implemented.
Regarding the above-mentioned deadline, on the afternoon of October 11, Mr. Dinh Van Bay - Deputy General Director of Xuan Khiem Group - said that due to the recent heavy rain and storms in Ha Tinh, the construction progress of the unit was affected, although the company had made great efforts and focused on speeding up construction.
According to Mr. Bay, if the weather is good and favorable, it is expected that the unit will temporarily put this rest stop into operation in about a week.
Currently, the rest stop on the expressway section Dien Chau - Bai Vot in Duc Quang commune (Ha Tinh province) with an area of 6 hectares (3 hectares on each side) won the bid by the consortium of Vietnam National Petroleum Group (Petrolimex) - Thua Thien Hue National Petroleum Company is also under construction.
The North-South expressway project in the East passing through Ha Tinh has a total length of more than 107 km with 4 component projects in 2 phases 2017 - 2020 (Dien Chau - Bai Vot expressway) and phase 2021 - 2025 ( Bai Vot - Ham Nghi, Ham Nghi - Vung Ang and Vung Ang - Bung expressways).
Currently, all 4 component projects of the expressway through Ha Tinh have been put into operation, of which the Vung Ang - Bung section will be put into operation no later than August 28.
On the expressway through Ha Tinh, there are 2 rest stops located in Duc Quang and Cam Hung communes.