Series of overpasses on the 3,800 billion VND connecting route

Lam Thanh |

Thai Nguyen - 3 main overpasses on the route connecting Thai Nguyen - Bac Giang - Vinh Phuc are being accelerated in construction, their shapes gradually appearing.

The Thai Nguyen - Bac Giang - Vinh Phuc regional road project is over 42 km long, starting at Pho Yen city and ending at the intersection with provincial road 261 (Dai Tu district).

The project started construction in mid-May 2022 with a value of more than 3,800 billion VND, invested by the Management Board of Traffic Construction Investment Projects of Thai Nguyen province.

After more than 2 years of construction, the shape of the billion-dollar route has gradually appeared. Some locations have been paved with asphalt. In particular, the entire route has 3 large overpasses that are being accelerated, including: the railway overpass, the National Highway 3 overpass, and the Cong River overpass.

Cau vuot song Cong den nay da hoan thanh tren 50% khoi luong cong viec. Anh: Lam Thanh
The Cong River overpass has so far completed over 50% of its work. Photo: Lam Thanh

According to PV on November 27, all 3 overpasses are located in Pho Yen city, hundreds of workers and machinery were mobilized to implement the project.

At the railway overpass, the bridge piers are basically complete. Some bridge girders have been installed. Workers are continuing to construct the bridge deck.

The construction site of the Highway 3 overpass and the Cong River overpass is currently constructing piers, bridge foundations, and casting bridge girders. At the same time, underpasses for people are being built along the entire route. Hundreds of bridge girders have been completed and are awaiting installation.

Worker Nguyen Van Dong (Pho Yen City) said that at the construction site there are many construction teams, from casting beams to building bridge piers and underpasses. After completing all stages, the overpass beams will be installed.

"It takes 3 to 4 days to complete one overpass girder. My unit alone was assigned to cast more than 100 girders. During the construction process, the most difficult step was the girder installation, which required high technique, machinery and precision.

All workers are focused, trying to complete to speed up the project's progress, striving to complete it in the first quarter of next year," said Mr. Dong.

On November 27, informing reporters of Lao Dong Newspaper, a representative of the Management Board of the project to invest in the construction of traffic works in Thai Nguyen province said that up to now, the project has completed 99% of the site clearance work.

The construction progress of the three major bridges has reached 58.57% of the volume, of which the railway overpass has reached 69.28%, the National Highway 3 overpass has reached 58.39%, and the Cong River overpass has reached 50.8%. These main bridges are required to be completed by the end of March 2025. The total volume value of the project along the entire route has so far reached more than 62%.

Some images recorded at the project:

Cau vuot duong sat tren tuyen duong lien ket Thai Nguyen - Bac Giang - Vinh Phuc. Anh: Lam Thanh
Railway overpass on the route connecting Thai Nguyen - Bac Giang - Vinh Phuc. Photo: Lam Thanh
Cau vuot Quoc lo 3 tai du an. Anh: Lam Thanh
The National Highway 3 overpass at the project is constructing piers to install girders. Photo: Lam Thanh
Cac cong nhan trien khai duc dam cau vuot tren tuyen duong lien ket hon 3.800 ti dong. Anh: Lam Thanh
Workers are casting the overpass beams on the connecting road worth more than VND3,800 billion. Photo: Lam Thanh
Mot so dam cau vuot da hoan thien, chuan bi duoc lap dat. Anh: Lam Thanh
Some overpass girders have been completed and are ready to be installed. Photo: Lam Thanh
Cau vuot song Cong dang duoc trien khai thi cong. Anh: Lam Thanh
The Cong River overpass is under construction. Photo: Lam Thanh
Mot dam cau phai mat tu 3 den 4 ngay moi hoan thien. Anh: Lam Thanh
It takes 3 to 4 days to complete a bridge girder. Photo: Lam Thanh
Lam Thanh
TIN LIÊN QUAN

Construction of 1,000 billion VND expressway overpass over National Highway 51 is about to start

|

Dong Nai - Ben Luc - Long Thanh Expressway will be extended to Bien Hoa - Vung Tau Expressway, the section through National Highway 51 will have an overpass investment of 1,000 billion VND.

487 billion VND railway overpass in Vinh Phuc is about to be completed

|

Once completed, the overpass will ease traffic congestion and ensure traffic safety at the intersection of Nguyen Tat Thanh Street and the Hanoi - Lao Cai railway.

Large river bridges worth thousands of billions of dong in Nam Dinh

|

Nam Dinh - Large bridges over rivers, connecting Nam Dinh province with neighboring provinces and cities, are gradually being completed and put into operation.

Northwestern provinces are chasing momentum for a two-level local government model

|

Although not subject to provincial mergers, Dien Bien, Lai Chau, and Son La still have to strive to be ready to operate the 2-level local government model from July 1.

Overcoming pollution from waste treatment plants in Nam Dinh after Lao Dong's reflection

|

Nam Dinh - Handling and overcoming pollution from waste treatment plants in Nam Giang town (Nam Truc district) affecting people's lives after being reported by Lao Dong Newspaper.

Expected headquarters of administrative agencies of Hai Phong City after merging with Hai Duong

|

Hai Phong - The City People's Committee has just approved the Project on arranging, arranging, and handling assets of agencies, units at the city level, and administrative units at the commune level.

Mr. Trump declares to achieve a ceasefire between Israel and Iran

|

On the evening of June 23, US time, President Donald Trump suddenly announced that he had achieved a "comprehensive and complete" ceasefire between Israel and Iran.

Germany and Italy urged to repatriate $245 billion in gold from the US

|

Germany and Italy are facing calls to remove gold reserves from New York, USA.

Construction of 1,000 billion VND expressway overpass over National Highway 51 is about to start

HÀ ANH CHIẾN |

Dong Nai - Ben Luc - Long Thanh Expressway will be extended to Bien Hoa - Vung Tau Expressway, the section through National Highway 51 will have an overpass investment of 1,000 billion VND.

487 billion VND railway overpass in Vinh Phuc is about to be completed

An Vi |

Once completed, the overpass will ease traffic congestion and ensure traffic safety at the intersection of Nguyen Tat Thanh Street and the Hanoi - Lao Cai railway.

Large river bridges worth thousands of billions of dong in Nam Dinh

Lương Hà |

Nam Dinh - Large bridges over rivers, connecting Nam Dinh province with neighboring provinces and cities, are gradually being completed and put into operation.