A series of traffic projects worth hundreds of billions of VND in Phu Tho in the first half of 2025

Tô Công |

Phu Tho - In the first 6 months of 2025, the province has implemented major transport projects with a total investment of hundreds of billions of VND in districts and towns.

396 billion VND to build a road connecting Thuy Van Industrial Park

The project of the road from Thuy Van Industrial Park to the road connecting Nguyen Tat Thanh - Ton Duc Thang Street, Viet Tri City was approved from the end of 2024 according to Decision No. 4089 of the City People's Committee.

This project is invested by the Viet Tri City Infrastructure Construction Project Management Board. The total investment of the project is nearly 396 billion VND, of which the construction package alone has an estimated price of nearly 340 billion VND.

Duong Nguyen Tat Thanh, thanh pho Viet Tri. Anh: To Cong.
Nguyen Tat Thanh Street, Viet Tri City. Photo: To Cong

At the end of May 2025, the above construction package has completed the contractor selection, with the winning bid price of nearly 335 billion VND. Currently, the consortium of 3 construction units has begun implementing the package.

The project is a route with a total length of more than 4.5 km, passing through the communes of Thuy Van, Thanh Dinh and Chu Hoa of Viet Tri city.

Diem dau cua du an tai khu cong nghiep Thuy Van (gan Cong doan cac khu cong nghiep tinh). Anh: To Cong.
The starting point of the project is at Thuy Van Industrial Park (near the headquarters of the Provincial Industrial Parks Trade Union). Photo: To Cong

According to the project documents, the route starts at the intersection with Truong Chinh Street, Thuy Van Industrial Park and ends at the intersection with Nguyen Tat Thanh - Ton Duc Thang Street.

100 billion VND to build an extended inter-regional road

The Inter-regional Road project connecting Ho Chi Minh Road with National Highway 70B, National Highway 32C from Phu Tho province to Yen Bai province - with a total adjusted investment of VND 2,120 billion, the project investor is the Department of Construction of Phu Tho province (formerly the Department of Transport).

In mid-May 2025, Package No. 60: Construction of the project's extended road has completed the selection of contractors. This construction package has an estimated price of 100 billion VND, the winning bid price is nearly 97.6 billion VND, the implementation period is 240 days.

Binh do uoc chung tuyen duong lien vung keo dai. Anh: To Cong.
Chart of the approximately extended inter-regional road. Photo: To Cong

As for the project in Viet Tri city, after the results of contractor selection, the construction unit is starting to implement the package, the project is built as a road with a total length of more than 3.7 km, designed according to the scale of a grade III plain road, with a design speed of 80 km/h.

According to the design, the starting point of the route continues with the main inter-regional road, at Km0 intersecting with National Highway 32 (Km81+380), the end point intersecting with National Highway 32 (at Km76+150), near Tam Nong District Medical Center, only about 400 m from Phong Chau bridge.

Du an se nang cap duong tinh 315 len quy mo duong cap III dong bang. Anh: To Cong.
The project will upgrade provincial road 315 to the scale of a level III plain road. Photo: To Cong

692 billion VND to build a road connecting 2 key expressways

The Noi Bai - Lao Cai Expressway Connection Investment Project with Tuyen Quang - Phu Tho Expressway was approved by the Ministry of Transport (now the Ministry of Construction) in Decision No. 699/QD-BGTVT dated June 4, 2024.

The total investment of the project is more than 692 billion VND, the investor is the Department of Construction of Phu Tho province (formerly the Department of Transport). This project has a construction package value of nearly 468 billion VND, starting from mid-February 2025.

Du an trien khai giap tuyen duong Ho Chi Minh tai thi xa Phu Tho.
The project is deployed adjacent to the Ho Chi Minh road in Phu Tho town.

According to records, adjacent to the Ho Chi Minh road section passing through Ha Loc commune, Phu Ho commune of Phu Tho town, the construction contractor mobilized many equipment, vehicles, and raw materials to construct this project.

At the construction site, engineers and workers are focusing on tasks such as: excavation, packing bamboo stakes, underpasses, precast components...

According to the design, the project will build a main road connecting the two expressways with a total length of over 2.73 km, including 4 lanes, with the design of the A1 elevated road surface made of asphalt concrete.

Nhung ham chui voi khoi luong betong cot thep rat lon dang duoc xay dung. Anh: To Cong.
Underpasses with a large amount of reinforced concrete are under construction. Photo: To Cong

Along with that, the project will build a system of service roads and return roads to connect the local traffic system and bridges, underpasses on a number of level crossings, intersections at other intersection levels...

According to the report of the Phu Tho Provincial Construction Investment Project Management Board (project management unit), the construction work has so far reached a value of about VND 27,102/467.731 billion.

Regarding disbursement, the project has so far disbursed 137.376/692.565 billion VND (19.84%), of which: Consulting cost 11.33 billion VND; construction cost 126 billion VND; other costs; 0.046 billion VND.

Tô Công
TIN LIÊN QUAN

The billion-dollar road project in Dak Nong is unfinished, making it difficult for people to travel

|

Dak Nong - The Dao Nghia - Quang Khe road project has a road section of about 700m that has not been completed, causing many difficulties for people in traveling.

Hai Phong prioritizes investment in 32 key transport projects in the 2026-2030 period

|

Hai Phong - On June 10, the Standing Committee of the City Party Committee met to agree on a list of 32 key transport projects for the 2026-2030 period and investment policies for a number of projects.

Close-up of the urban area project of nearly 32,000m2 in Da Nang, which is open for sale with 530 apartments

|

Da Nang - The Department of Construction of Da Nang City has just approved the opening of 530 apartments for sale in the future at the Capital Square 2 Urban Area Project (Son Tra District).

Nearly 1,500 hectares of summer-autumn rice in Quang Binh were deeply flooded due to storm No. 1

|

Quang Binh - Heavy rain caused by storm No. 1 has caused nearly 1,500 hectares of summer-autumn rice in Bo Trach to be flooded, with the risk of having to be replanted, greatly affecting production.

Alternative traffic routes when vehicles are banned from traveling through the Saigon River tunnel

|

HCMC - Prohibit vehicles from circulating through the Saigon River tunnel from 11:00 p.m. on June 27 to 4:00 a.m. on June 28, 2025.

Forecast of heavy rain due to storm No. 1

|

According to the meteorological agency, heavy rain due to storm No. 1 will be concentrated from June 12 to 13.

The Israeli government narrowly escapes the risk of dispersation

|

On June 12, the Knesset ( Israeli parliament) rejected the results of a preliminary vote to dissolve itself, allowing the Israeli ruling coalition to temporarily avoid early elections.

The Secretary of the Ho Chi Minh City Party Committee highly appreciated the trial operation of 102 new wards and communes

|

HCMC - The pilot operation of the local government model at the commune level in 102 wards and communes has achieved positive results.

The billion-dollar road project in Dak Nong is unfinished, making it difficult for people to travel

DƯƠNG HẰNG |

Dak Nong - The Dao Nghia - Quang Khe road project has a road section of about 700m that has not been completed, causing many difficulties for people in traveling.

Hai Phong prioritizes investment in 32 key transport projects in the 2026-2030 period

Hoàng Khôi |

Hai Phong - On June 10, the Standing Committee of the City Party Committee met to agree on a list of 32 key transport projects for the 2026-2030 period and investment policies for a number of projects.

Close-up of the urban area project of nearly 32,000m2 in Da Nang, which is open for sale with 530 apartments

Thu Giang |

Da Nang - The Department of Construction of Da Nang City has just approved the opening of 530 apartments for sale in the future at the Capital Square 2 Urban Area Project (Son Tra District).