A series of high-voltage windshields at Cat Linh - Ha Dong metro station are broken, urgent repair

Tô Thế |

Hanoi - The stairs of the high-voltage glass at some Cat Linh - Ha Dong metro stations were broken and tilted.

According to Lao Dong newspaper reporters on May 31, the Cat Linh - Ha Dong metro line management unit is repairing many damaged items at stations, such as high-voltage glass railings, walkways, roofing panels at stations, etc.

It is known that the repair and replacement have been carried out for the past few days. According to a survey by PV, by the afternoon of May 31, only a few high-voltage glass railings at Ha Dong and Van Quan stations had not been replaced. Workers are replacing the roofing panels covering Yen Nghia station.

Lan can kinh cuong luc tai nha ga Van Quan, ga Ha Dong bi vo, hinh anh ghi nhan chieu 31.5. Anh: To The
The high-voltage glass railing at Van Quan station, Ha Dong station was broken, the image was recorded on the afternoon of May 31. Photo: To The
Tam lop mai nha ga Yen Nghia chua duoc thay the (khoanh do). Hinh anh ghi nhan chieu 31.5. Anh: To The
The roof of Yen Nghia station has not been replaced (closed). Image recorded on the afternoon of May 31. Photo: To The

Sharing with reporters, Ms. Nguyen Thi Nga (Ha Dong) - a regular passenger on the Cat Linh - Ha Dong metro train said that the above damages have appeared for a long time but have not been repaired by the management unit.

"I saw some broken glass panels with ropes as warning signs. I am just worried that if someone unfortunately falls there, it will have a strong impact, the glass falling onto the road below will be dangerous for road users," Ms. Nga shared.

Information from Hanoi Railway Company Limited (HMC) said that in this period, many items and equipment on the entire route will be inspected, repaired, and replaced, such as loudspeakers at stations, train display screens, glass railings, pedestrian roofs, etc.

Cac tru nuoc uong mien phi tai mot so nha ga tuyen metro Cat Linh - Ha Dong nhieu nam nay khong the su dung. Anh: To The
Free drinking water poles at some Cat Linh - Ha Dong metro stations have not been used for many years. Photo: To The
Ghe ngoi tai mot so nha ga cung da bi hu hong. Anh: To The
Seats at some stations have also been damaged. Photo: To The

Previously, the inspection team of the Hanoi Department of Construction had a report concluding that HMC Company was still late and had not actively coordinated with relevant units, reporting to competent authorities to take timely and effective remedial measures for equipment and infrastructure damage caused by Typhoon Yagi.

In order to ensure absolute safety and operation, ensure the quality of public passenger transport services, less affecting passengers, promptly handle the above situation, the Department of Construction proposed the Hanoi People's Committee to approve the policy of allowing HMC to repair emergency roofs on the roof of Yen Nghia station, the roofs of the escalator and the broken and cracked glass at some stations on the urban railway, Cat Linh, according to the urban railway.

The repair and replacement will be completed before June 6, 2025.

On May 30, 2025, during operation, the Cat Linh - Ha Dong metro train encountered another problem and had to stop the train.

According to the report from the operator, at 5:36 p.m. on May 30, 2025, on route 2A Cat Linh - Ha Dong, the system appeared warning of an error at Cat Linh station.

Immediately, this unit activated the operating and technical work plan according to the correct procedure. The 2A Enterprise Operations dieu hanh center has notified relevant units to coordinate in handling the situation.

At that time, 4 stations in Area A from Cat Linh Station to Lang Station were turned off to ensure safety for the technical team to approach the scene and handle the situation. At the same time, a small intersection is being run to serve passengers from Thuong Dinh station to Yen Nghia station and vice versa.

The problem was fixed in 25 minutes. This error warning phenomenon is included in the response scenario of Hanoi Metro.

Tô Thế
TIN LIÊN QUAN

Cat Linh - Ha Dong electric train had an accident, took nearly half an hour to fix

|

Hanoi - 4 stations in Area A from Cat Linh Station to Lang Station (Cat Linh - Ha Dong power train line) were cut off for nearly 30 minutes to fix the warning of errors.

Hanoi proposes to repair Cat Linh - Ha Dong railway station

|

Hanoi The Hanoi Department of Construction has just issued a document recommending repairs at a number of stations on the urban railway line (DDT) No. 2A Cat Linh - Ha Dong.

Hanoi Metro admits the mistake of passengers having to cover themselves when taking the Cat Linh - Ha Dong train

|

Hanoi - Cat Linh - Ha Dong electric train experienced a phenomenon of water flowing to regulate the air on the passenger car.

Cambodia, Thailand schedule border negotiations

|

Cambodia and Thailand are expected to negotiate the border next week.

The Ministry of Public Security launched a peak period of counterfeit goods scanning for 3 months

|

The police force has prosecuted 36 cases and 119 defendants related to the crimes of smuggling, trade fraud, production and trading of counterfeit goods.

Accident on Nha Trang - Cam Lam Expressway, 3 victims trapped in car

|

Khanh Hoa - The authorities are trying to rescue the victims trapped inside a 4-seat car after a traffic accident on the Nha Trang - Cam Lam Expressway.

Some businesses in Ho Chi Minh City refuse to accept bank transfers

|

HCMC - Some small stores and restaurants in HCMC refuse to accept transfers or request not to record payment content.

Mr. Trump complains about the difficulty in reaching an agreement with Mr. Xi Jinping

|

US President Donald Trump said that General Secretary and President of China Xi Jinping is a "very tough" person and "extremely difficult to reach an agreement".

Cat Linh - Ha Dong electric train had an accident, took nearly half an hour to fix

HỮU CHÁNH |

Hanoi - 4 stations in Area A from Cat Linh Station to Lang Station (Cat Linh - Ha Dong power train line) were cut off for nearly 30 minutes to fix the warning of errors.

Hanoi proposes to repair Cat Linh - Ha Dong railway station

Minh Hạnh |

Hanoi The Hanoi Department of Construction has just issued a document recommending repairs at a number of stations on the urban railway line (DDT) No. 2A Cat Linh - Ha Dong.

Hanoi Metro admits the mistake of passengers having to cover themselves when taking the Cat Linh - Ha Dong train

Tô Thế - Đặng Tiến |

Hanoi - Cat Linh - Ha Dong electric train experienced a phenomenon of water flowing to regulate the air on the passenger car.