Risk of delay in progress at the Ke Go lake upgrade and repair project

TRẦN TUẤN |

Ha Tinh - Although it has focused on construction to compensate for volume, the project to upgrade and repair Ke Go Lake is still at risk of delaying progress.

According to the reporter of Lao Dong Newspaper, currently the contractor is a joint venture of Construction Joint Stock Company 47 - Lilama 10 Joint Stock Company - Construction Joint Stock Company 465 is focusing maximum manpower and machinery to construct the Ke Go Lake upgrade and repair project in Cam Due commune.

Workers are divided into many construction teams simultaneously in the items of upgrading the main dam, pouring concrete for the Dốc Miếu flood discharge spillway, and repairing the water intake tower.

Công nhân đang thi công ở hạng mục tràn Dốc Miếu. Ảnh: Trần Tuấn
Workers are constructing the Doc Mieu spillway item. Photo: Tran Tuan

Through observation, the workload is still large, so there is a risk of project delays when there is only one month left to complete and hand over the project.

Mr. Nguyen Ba Quang - technical officer of Construction Joint Stock Company 47 said that currently the weather is hot and sunny, construction at the construction site is very hard. However, under the pressure of progress, the unit has mobilized maximum machinery and manpower to focus on 3 shifts of 4 teams, constructing even at night.

To ensure workers' health, the company has adjusted working hours flexibly according to hot weather. Accordingly, working in the morning from 6am to 10am; in the afternoon from 2:30pm to 6:30pm.

Nắng nóng nên công nhân rất vất vả. Ảnh: Trần Tuấn
Hot weather makes workers very hard. Photo: Tran Tuan

Because it rained too much at the end of 2025, it affected the construction progress. Although construction has been focused on accelerating to compensate for volume, it is likely that the project will still not meet the completion schedule by June 30th. Perhaps it will be a few more months late to complete the entire project," Mr. Nguyen Ba Quang shared.

Mr. Nguyen Minh Hieu - official of the Irrigation Investment and Construction Management Board 1 - said that the project to upgrade and repair Ke Go Lake was started on December 27, 2024, and according to the plan, it will be completed in June 2026. Up to this point, the total construction volume has reached about 80%.

Also according to Mr. Hieu, due to objective reasons, too many rains and floods at the end of 2025 slowed down the construction progress, leading to low volume achievement.

It is expected that the project will not be completed until August 30, so the project may be delayed by several months compared to the contracted schedule," Mr. Hieu shared.

Currently, every day at the construction site, contractors mobilize about 150 workers to focus on construction in many items. To speed up progress, contractors have also constructed at night.

Công nhân thi công ở hạng mục nâng cấp đập chính. Ảnh: Trần Tuấn
Workers constructing at the main dam upgrade item. Photo: Tran Tuan
Sửa chữa tháp lấy nước. Ảnh: Trần Tuấn
Repairing the water tower. Photo: Tran Tuan
Khối lượng công việc còn lại của dự án là khá lớn. Ảnh: Trần Tuấn
The remaining workload of the project is about 20%. Photo: Tran Tuan

The project to upgrade and repair Ke Go Lake has a total investment of 350 billion VND from central capital, invested by the Irrigation Investment and Construction Management Board No. 1.

The project includes items: Repairing and upgrading the main dam, auxiliary dams 1 and 2, Doc Mieu spillway, water intake culvert, Doc Mieu spillway management and operation building and behind the main dam; building a new flood discharge spillway.

Ke Go reservoir was built in 1976, with a capacity of 345 million m3, and is the most important irrigation project in Ha Tinh.

Ke Go Lake not only serves irrigation for tens of thousands of hectares of agricultural land but also has the task of cutting and reducing floods for downstream areas, supplying domestic water and maintaining the ecological environment.

TRẦN TUẤN
RELATED NEWS

Lack of materials, Lien Khuong airport upgrade project at risk of delay

|

Lam Dong - Lack of construction materials causes difficulties for many items under the Lien Khuong airport repair and upgrade project, posing a risk of delay.

Hanoi Ring Road 2.5 is entangled with site clearance, risk of delayed progress

|

Hanoi - Ring Road 2.5 project is facing site clearance obstacles, facing the risk of not being completed in time in 2026.

Dong Ha bypass road at risk of delay due to site clearance problems, calculating coercive measures

|

Quang Tri - The Dong Ha bypass road project is at risk of continuing to be delayed. The locality is looking for solutions and considering coercive measures to clear the site.

Russia launches fierce attack on Kiev

|

Kiev suffered a wave of fierce attacks from Russia, many people are believed to be trapped under the rubble of an apartment building.

Stock market has not shown signs of bottoming out

|

The stock market will continue to adjust to retest support zones if demand does not improve soon in the coming sessions.

Candidates are concerned about the actual type of math in the 10th grade Math exam in Ho Chi Minh City

|

Entering the 120-minute Math exam in the 10th grade entrance exam in Ho Chi Minh City, many candidates said they were most worried about the practical application questions.

Expecting Vietnam Trade Union to have a large-scale program on AI and digital skills universalization

|

That is the expectation of Ms. Tran Thuy Duong - Member of the Executive Committee of FPT Corporation Trade Union, Chairwoman of FPT University Trade Union.

New look of the ring road project worth more than 7,210 billion VND in Hanoi

|

Hanoi - The Ring Road 1 project, Hoang Cau - Voi Phuc section, is being urgently implemented, in which some sections have been asphalted.

Lack of materials, Lien Khuong airport upgrade project at risk of delay

Phúc Khánh |

Lam Dong - Lack of construction materials causes difficulties for many items under the Lien Khuong airport repair and upgrade project, posing a risk of delay.

Hanoi Ring Road 2.5 is entangled with site clearance, risk of delayed progress

Minh Hạnh |

Hanoi - Ring Road 2.5 project is facing site clearance obstacles, facing the risk of not being completed in time in 2026.

Dong Ha bypass road at risk of delay due to site clearance problems, calculating coercive measures

HƯNG THƠ |

Quang Tri - The Dong Ha bypass road project is at risk of continuing to be delayed. The locality is looking for solutions and considering coercive measures to clear the site.