Tan Son Nhat airport's T3 terminal continues to leak water due to heavy rain

ANH TÚ |

HCMC - Although it has only been inaugurated for more than a month, the T3 terminal of Tan Son Nhat airport continued to leak when it rained at noon on May 24.

During the heavy rain at noon on May 24, many passengers when arriving at the T3 terminal - Tan Son Nhat International Airport were surprised to see rainwater flowing down from the roof, leaking at the terminal to the T3.

According to the clip recorded by local residents, water flowed continuously in the area near the check-in counter and the luggage handling strip, affecting the experience of passengers.

Previously, on May 7, a similar phenomenon had also occurred in the plane waiting area. Although the contractor later confirmed that it had been fixed, the leakage situation when heavy rain occurred continued to recur.

Not only the water leaked, some construction items in the terminal were also reported to be unfinished, especially the stone foundation in the waiting hall. Many locations have peeling facility, uneven tiles or patchwork, causing loss of aesthetics.

Responding to the press, the representative of the T3 station contractor said that due to the urgent progress in order to make the station into operation as planned, some auxiliary items, including the stone foundation, must continue to complete after the station exploited. Up to now, about 50% of the foundation has been constructed. The contractor pledged to complete the entire stone background before June 30, including the plastering, elastic glue pump, grinding and polishing the background.

Because the project has been put into operation, the construction is carried out at night (from 0:00 to 3:00 am) to avoid affecting flight operations. The contractor hopes to receive sharing from passengers and investors.

Tan Son Nhat T3 Terminal has a total investment of more than VND 11,000 billion, started construction at the end of 2022 and inaugurated on April 19, 2025, 2 months ahead of schedule. The terminal has a designed capacity of 20 million passengers/year and is expected to reduce the pressure on Terminal T1, which has been overloaded for many years.

ANH TÚ
TIN LIÊN QUAN

The Civil Aviation Authority directs ACV after reflecting that Terminal T3 has defects

|

Terminal T3, Tan Son Nhat airport continues to be reported to have defects after the roof leaked in early May 2025

The stone foundation of Terminal T3 of Tan Son Nhat airport will be completed before June 30

|

HCMC - Before the reflection of peeling and patching of the stone foundation at Terminal T3, the contractor committed to completing the entire stone foundation before June 30 to ensure aesthetics.

The new 6-lane road cannot save the Northwest gateway of Ho Chi Minh City from traffic jams

|

HCMC - Despite having a 6-lane Tran Quoc Hoan - Cong Hoa connecting road, old roads such as Cong Hoa and Truong Chinh at the Northwest gateway of HCMC are still seriously congested.

MC Hoang Linh fined 107.5 million VND in HIUP milk advertising case

|

MC Hoang Linh was administratively sanctioned, with a total fine of 107.5 million VND for violations in advertising activities.

The longest-serving Ukrainian Prime Minister nominated as Secretary of Defense

|

Ukrainian President Volodymyr Zelensky has appointed the country's longest-serving Prime Minister, Denys Shmyhal, as his next defense minister.

A small alley in Ho Chi Minh City has been haunted all year round by malicious bombs

|

HCMC - A steep alley suddenly became famous in the sales and delivery world... because bad guys used the address to bomb malicious goods for a long time.

Gold bandit camp discovered again in protective forest in Quang Tri

|

Quang Tri - Forest protection forces continue to discover gold bandit camps set up in the middle of old forests to illegally exploit gold.

Experts: Can consider supporting 30 - 50% of the cost of buying electric vehicles for people

|

Experts say that it is necessary to soon have solutions to support people to switch to electric vehicles when banning gasoline motorbikes from entering Hanoi's Ring Road 1.

The Civil Aviation Authority directs ACV after reflecting that Terminal T3 has defects

Xuyên Đông |

Terminal T3, Tan Son Nhat airport continues to be reported to have defects after the roof leaked in early May 2025

The stone foundation of Terminal T3 of Tan Son Nhat airport will be completed before June 30

Anh Tú |

HCMC - Before the reflection of peeling and patching of the stone foundation at Terminal T3, the contractor committed to completing the entire stone foundation before June 30 to ensure aesthetics.

The new 6-lane road cannot save the Northwest gateway of Ho Chi Minh City from traffic jams

MINH QUÂN |

HCMC - Despite having a 6-lane Tran Quoc Hoan - Cong Hoa connecting road, old roads such as Cong Hoa and Truong Chinh at the Northwest gateway of HCMC are still seriously congested.