Tan Son Nhat airport's T3 terminal continues to leak water due to heavy rain

ANH TÚ |

HCMC - Although it has only been inaugurated for more than a month, the T3 terminal of Tan Son Nhat airport continued to leak when it rained at noon on May 24.

During the heavy rain at noon on May 24, many passengers when arriving at the T3 terminal - Tan Son Nhat International Airport were surprised to see rainwater flowing down from the roof, leaking at the terminal to the T3.

According to the clip recorded by local residents, water flowed continuously in the area near the check-in counter and the luggage handling strip, affecting the experience of passengers.

Previously, on May 7, a similar phenomenon had also occurred in the plane waiting area. Although the contractor later confirmed that it had been fixed, the leakage situation when heavy rain occurred continued to recur.

Not only the water leaked, some construction items in the terminal were also reported to be unfinished, especially the stone foundation in the waiting hall. Many locations have peeling facility, uneven tiles or patchwork, causing loss of aesthetics.

Responding to the press, the representative of the T3 station contractor said that due to the urgent progress in order to make the station into operation as planned, some auxiliary items, including the stone foundation, must continue to complete after the station exploited. Up to now, about 50% of the foundation has been constructed. The contractor pledged to complete the entire stone background before June 30, including the plastering, elastic glue pump, grinding and polishing the background.

Because the project has been put into operation, the construction is carried out at night (from 0:00 to 3:00 am) to avoid affecting flight operations. The contractor hopes to receive sharing from passengers and investors.

Tan Son Nhat T3 Terminal has a total investment of more than VND 11,000 billion, started construction at the end of 2022 and inaugurated on April 19, 2025, 2 months ahead of schedule. The terminal has a designed capacity of 20 million passengers/year and is expected to reduce the pressure on Terminal T1, which has been overloaded for many years.

ANH TÚ
RELATED NEWS

The Civil Aviation Authority directs ACV after reflecting that Terminal T3 has defects

|

Terminal T3, Tan Son Nhat airport continues to be reported to have defects after the roof leaked in early May 2025

The stone foundation of Terminal T3 of Tan Son Nhat airport will be completed before June 30

|

HCMC - Before the reflection of peeling and patching of the stone foundation at Terminal T3, the contractor committed to completing the entire stone foundation before June 30 to ensure aesthetics.

The new 6-lane road cannot save the Northwest gateway of Ho Chi Minh City from traffic jams

|

HCMC - Despite having a 6-lane Tran Quoc Hoan - Cong Hoa connecting road, old roads such as Cong Hoa and Truong Chinh at the Northwest gateway of HCMC are still seriously congested.

Chairman of the Vietnam General Confederation of Labor presents Tet gifts to workers at Ninh Binh Fertilizer Company

|

Ninh Binh - Chairman of the Vietnam General Confederation of Labor Nguyen Dinh Khang visited and presented 84 gifts to workers at Ninh Binh Fertilizer One Member Limited Liability Company.

Near Tet, Hanoi streets are still crowded with vehicles at midnight

|

Hanoi - 10 pm on February 12, many streets in the Capital are still crowded with vehicles passing by because of the flow of people going out to play and shop for Tet.

Erecting the Neu tree to welcome Tet, many people in Nghe An are electrocuted

|

Nghe An - In just a short time before Tet, electric shock incidents occurred continuously when erecting the Neu tree in Nghe An, causing many people to be severely burned.

Ho Chi Minh City Spring Flower Festival opens brilliantly at Tao Dan Park

|

Ho Chi Minh City - The 46th City Spring Flower Festival opened on the evening of February 12th at Tao Dan Park, attracting a large number of people to visit and check-in to welcome Binh Ngo Tet 2026.

Warm spring comes to pediatric patients at the National Institute of Hematology and Blood Transfusion

|

Approaching Tet, many pediatric patients at the National Institute of Hematology and Blood Transfusion are still staying for treatment. On February 12, the Golden Heart Charity Social Fund presented 120 gifts, bringing the warmth of early spring to children and families.

The Civil Aviation Authority directs ACV after reflecting that Terminal T3 has defects

Xuyên Đông |

Terminal T3, Tan Son Nhat airport continues to be reported to have defects after the roof leaked in early May 2025

The stone foundation of Terminal T3 of Tan Son Nhat airport will be completed before June 30

Anh Tú |

HCMC - Before the reflection of peeling and patching of the stone foundation at Terminal T3, the contractor committed to completing the entire stone foundation before June 30 to ensure aesthetics.

The new 6-lane road cannot save the Northwest gateway of Ho Chi Minh City from traffic jams

MINH QUÂN |

HCMC - Despite having a 6-lane Tran Quoc Hoan - Cong Hoa connecting road, old roads such as Cong Hoa and Truong Chinh at the Northwest gateway of HCMC are still seriously congested.