Tan Son Nhat airport's T3 terminal continues to leak water due to heavy rain

ANH TÚ |

HCMC - Although it has only been inaugurated for more than a month, the T3 terminal of Tan Son Nhat airport continued to leak when it rained at noon on May 24.

During the heavy rain at noon on May 24, many passengers when arriving at the T3 terminal - Tan Son Nhat International Airport were surprised to see rainwater flowing down from the roof, leaking at the terminal to the T3.

According to the clip recorded by local residents, water flowed continuously in the area near the check-in counter and the luggage handling strip, affecting the experience of passengers.

Previously, on May 7, a similar phenomenon had also occurred in the plane waiting area. Although the contractor later confirmed that it had been fixed, the leakage situation when heavy rain occurred continued to recur.

Not only the water leaked, some construction items in the terminal were also reported to be unfinished, especially the stone foundation in the waiting hall. Many locations have peeling facility, uneven tiles or patchwork, causing loss of aesthetics.

Responding to the press, the representative of the T3 station contractor said that due to the urgent progress in order to make the station into operation as planned, some auxiliary items, including the stone foundation, must continue to complete after the station exploited. Up to now, about 50% of the foundation has been constructed. The contractor pledged to complete the entire stone background before June 30, including the plastering, elastic glue pump, grinding and polishing the background.

Because the project has been put into operation, the construction is carried out at night (from 0:00 to 3:00 am) to avoid affecting flight operations. The contractor hopes to receive sharing from passengers and investors.

Tan Son Nhat T3 Terminal has a total investment of more than VND 11,000 billion, started construction at the end of 2022 and inaugurated on April 19, 2025, 2 months ahead of schedule. The terminal has a designed capacity of 20 million passengers/year and is expected to reduce the pressure on Terminal T1, which has been overloaded for many years.

ANH TÚ
RELATED NEWS

The Civil Aviation Authority directs ACV after reflecting that Terminal T3 has defects

|

Terminal T3, Tan Son Nhat airport continues to be reported to have defects after the roof leaked in early May 2025

The stone foundation of Terminal T3 of Tan Son Nhat airport will be completed before June 30

|

HCMC - Before the reflection of peeling and patching of the stone foundation at Terminal T3, the contractor committed to completing the entire stone foundation before June 30 to ensure aesthetics.

The new 6-lane road cannot save the Northwest gateway of Ho Chi Minh City from traffic jams

|

HCMC - Despite having a 6-lane Tran Quoc Hoan - Cong Hoa connecting road, old roads such as Cong Hoa and Truong Chinh at the Northwest gateway of HCMC are still seriously congested.

Hanoi is seriously polluted this morning, AQI is simultaneously at the purple threshold

|

Hanoi - This morning (December 10), air quality in Hanoi is at the purple threshold - very poor. AQI at 7:30 is 225.

Assets increase sharply, billionaire Pham Nhat Vuong firmly holds the second richest position in Southeast Asia

|

With assets increasing by 2.8 billion USD, Mr. Pham Nhat Vuong, Chairman of Vingroup Corporation, rose to 2nd place in the list of the richest people in Southeast Asia.

Young people in the cancer spinout

|

Increasingly young cancer causes many young people to face the same worries about illness, treatment costs and disruptions in studying, work, and the future.

Three scenarios that can change world gold prices in 2026

|

Gold prices still have room to increase next year, according to many experts.

357 households that have not yet handed over the land to build Ring Road 1 will be forced to work overnight

|

To ensure the progress of site clearance for Ring Road 1, Lang Ward proposed that the Hanoi People's Committee carry out a shortened process.

The Civil Aviation Authority directs ACV after reflecting that Terminal T3 has defects

Xuyên Đông |

Terminal T3, Tan Son Nhat airport continues to be reported to have defects after the roof leaked in early May 2025

The stone foundation of Terminal T3 of Tan Son Nhat airport will be completed before June 30

Anh Tú |

HCMC - Before the reflection of peeling and patching of the stone foundation at Terminal T3, the contractor committed to completing the entire stone foundation before June 30 to ensure aesthetics.

The new 6-lane road cannot save the Northwest gateway of Ho Chi Minh City from traffic jams

MINH QUÂN |

HCMC - Despite having a 6-lane Tran Quoc Hoan - Cong Hoa connecting road, old roads such as Cong Hoa and Truong Chinh at the Northwest gateway of HCMC are still seriously congested.