Many infrastructure projects in Nghe An are behind schedule due to land clearance problems

QUANG ĐẠI |

Nghe An - Slow progress due to land clearance problems, many transport projects in the province are at risk of affecting the public investment disbursement plan.

People do not agree because of low unit prices

On the morning of June 8, speaking with a reporter from Lao Dong Newspaper, Mr. Vuong Hong Thai, Vice Chairman of Nam Dan District People's Committee, said that up to now, the project to upgrade and expand National Highway 46 from Nam Dan to Vinh City has not yet completed site clearance, despite the province's capital allocation and drastic implementation.

This project is over 10km long, with a total investment of about 500 billion VND, and is expected to strengthen the connection between the Kim Lien Special National Monument area and Vinh City.

However, by early June 2025, the project site is stuck in many households that have not yet accepted the compensation plan.

Pho Chu tich UBND tinh Nghe An Hoang Phu Hien kiem tra tinh hinh thuc hien Du an cai tao, mo rong Quoc lo 46 doan Vinh - Nam Dan. Anh: Phan Quynh
Vice Chairman of Nghe An Provincial People's Committee Hoang Phu Hien inspected the implementation of the National Highway 46 renovation and expansion project, Vinh - Nam Dan section. Photo: Phan Quynh

According to Mr. Thai, the biggest problem at present is the compensation price for garden land applied according to the agricultural land framework multiplied by 3 times, only about 100,000150,000 VND/m2, while the market price is many times higher.

"Many households have residential land and garden land attached to houses, but when it is recovered, the compensation price is lower than the price of residential land, so they do not agree," said Mr. Thai.

Nam Dan District People's Committee has established a full-time working group, organized many dialogues with people and proposed that the province adjust unit prices to suit reality. The goal is to complete the site clearance work by June 2025 according to the direction of the Provincial People's Committee.

Meanwhile, at the National Highway 7 upgrade project through Dien Chau district - one of the key traffic projects in the area - site clearance work has reached high progress but has not yet been completely completed.

According to the report of Dien Chau District People's Committee, as of June 8, 2025, the locality has handed over 18.232km/18.608km of land (reaching 98%) to both sides of the route. However, there are still 353m of site clearance that have not been handed over, equivalent to 2% of the total length of the route. The remaining area belongs to 37 households in three localities: Dien Cat commune, Dien Phuc commune and Dien Thanh town.

The main reason is that some households have not agreed on the origin of the land, others request additional compensation for long-term land use but do not have valid documents. The District People's Committee is coordinating with relevant agencies to organize mobilization, dialogue and prepare a plan for enforcement if people do not cooperate.

Removing land bottlenecks, unblocking projects

With the project to upgrade and expand National Highway 1A, the disbursement of capital for site clearance also faces many difficulties. The main reason is that the processing of documents and appraisal of compensation plans is still slow and some localities have not yet completed payment to the people.

Nghe An Provincial People's Committee has issued more than 100 documents directing the removal of difficulties, requiring localities to complete site clearance for key projects in June 2025, to ensure the progress of public investment disbursement and transport infrastructure construction.

Mr. Hoang Phu Hien - Vice Chairman of Nghe An Provincial People's Committee affirmed that the province is reviewing the progress of each project, each section of the route and each household to specifically resolve the issue. For cases of intentional non-cooperation, the grassroots government will resolutely handle them in accordance with legal regulations.

Site clearance is still the biggest "bottleneck" for the progress of public investment projects in Nghe An. Completing site clearance on time is not only a necessary condition for construction but also a test of management capacity, transparency and consensus between the government and the people.

QUANG ĐẠI
TIN LIÊN QUAN

Reasons for not yet completing site clearance for a project worth over VND1,800 billion in Dak Lak

|

Dak Lak - The authorities have not been able to complete the clearance of 113m of the urban bypass project worth more than VND1,800 billion because many households have not agreed to the compensation plan.

Peak of handover of land for rest stops at the beginning of Vinh Hao - Phan Thiet Expressway

|

Binh Thuan - No later than June 15, 2025, the handover of the site to construct the rest stop at the beginning of the Vinh Hao - Phan Thiet expressway must be completed.

Project worth over VND1,800 billion in Dak Lak risks losing central government capital due to slow site clearance

|

Dak Lak - If there are still problems with the site, the Ministry of Construction will zoning the project for more than VND1,800 billion and hand over the unfinished part to the locality for self-management and capital completion.

The Ministry of Home Affairs proposes work on signing labor contracts with leading civil servants

|

The Ministry of Home Affairs proposes that workers sign labor contracts to perform the duties of their positions with civil servants in leadership and management positions.

Hanoi Department of Education and Training talks about the time to announce the 10th grade exam scores in 2025

|

The Department of Education and Training has informed about the time to announce the exam scores and admission scores for grade 10 this year.

Without input invoices, business households may face risks due to inventory

|

From July 1, 2025, business households with a revenue of VND 1 billion/year must use electronic invoices. Inventory without invoices needs to be explained to avoid tax risks.

The burst of the " end" shouts of the candidate when completing the 10th grade entrance exam

|

Candidates commented that the Math exam for grade 10 in Hanoi is just in time, within the content they have studied and reviewed.

Reasons for not yet completing site clearance for a project worth over VND1,800 billion in Dak Lak

THANH QUỲNH |

Dak Lak - The authorities have not been able to complete the clearance of 113m of the urban bypass project worth more than VND1,800 billion because many households have not agreed to the compensation plan.

Peak of handover of land for rest stops at the beginning of Vinh Hao - Phan Thiet Expressway

Duy Tuấn |

Binh Thuan - No later than June 15, 2025, the handover of the site to construct the rest stop at the beginning of the Vinh Hao - Phan Thiet expressway must be completed.

Project worth over VND1,800 billion in Dak Lak risks losing central government capital due to slow site clearance

THANH QUỲNH |

Dak Lak - If there are still problems with the site, the Ministry of Construction will zoning the project for more than VND1,800 billion and hand over the unfinished part to the locality for self-management and capital completion.