Ninh Binh has more than 9,000 households affected by the high-speed railway project

NGUYỄN TRƯỜNG |

Ninh Binh - The total land area for the high-speed railway project section passing through Ninh Binh province is over 1,000ha with more than 9,000 affected households.

The North-South high-speed railway section passing through Ninh Binh province has a total length of about 86km, passing through 23 communes and wards with 3 stations and 3 maintenance stations. In which, the starting point is identified in Dong Van ward and the ending point in Trung Son ward. Currently, localities with projects passing through are focusing on site clearance to serve the Project.

On December 19, in an exchange with a reporter from Lao Dong Newspaper, a representative of the Ninh Binh Provincial Department of Construction said that according to the route of the Project provided by the Railway Project Management Board and the report of the People's Committees of communes and wards where the Project passes through. The total area to be recovered from the Project in Ninh Binh province is over 1,000ha with more than 9,000 households affected. In which, the scope of railway safety corridor boundary is about 631.7ha and the scope of project protection boundary is about 406.78ha.

Lanh dao tinh Ninh Binh kiem tra cong tac GPMB Du an tuyen duong sat toc do cao doan qua dia ban xa My Loc. Anh: Dieu Anh
Leaders of Ninh Binh province inspect site clearance for the high-speed railway project section passing through My Loc commune. Photo: Dieu Anh

It is estimated that the number of affected households under resettlement is about 1,713 households. Currently, localities are continuing to review and standardize accurate data according to the route profile of the Project handed over by the Railway Project Management Board. 21/23 communes and wards have resettlement needs and are expected to arrange 31 resettlement projects for affected households.

Up to now, Ninh Binh Provincial People's Committee has issued a document approving the policy of the resettlement project for 16 communes and wards with 25 resettlement projects. Among them, 6 communes and wards have completed the master plan and are implementing the next steps of the project to submit for appraisal" - a representative of Ninh Binh Provincial Department of Construction said.

Ban do huong tuyen duong sat toc do cao tren truc Bac - Nam, doan qua dia phan tinh Ninh Binh. Anh: Dieu Anh
Map of the direction of the high-speed railway line on the North-South axis, passing through the territory of the old Ninh Binh province. Photo: Dieu Anh

According to representatives of the Ninh Binh Provincial Department of Construction, currently, site clearance work is facing some difficulties and obstacles because the Project passes through a number of religious buildings, historical relics, densely populated residential areas, companies, production plants, and material mining mines...

The Department of Construction has issued a document reporting to the Ministry of Construction for consideration and consultation with competent authorities to supplement the specific mechanism of the Project, allowing construction in advance of cemetery areas to promptly meet the project's progress requirements.

At the same time, direct the Railway Project Management Board, consulting unit and relevant agencies and units to review, research, work directly and agree with Ninh Binh province on the route direction and location of stations, depots, maintenance stations, and project design solutions to ensure suitability, efficiency, and convenience for site clearance work.

NGUYỄN TRƯỜNG
RELATED NEWS

Hung Yen builds 7 resettlement areas to serve the Ninh Binh - Hai Phong expressway

|

Hung Yen - The Ninh Binh - Hai Phong expressway project through the province is on schedule, with a site handover rate of 85%.

Ninh Binh enforces land acquisition to implement Tay Phu Van New Urban Area Project

|

Ninh Binh - On November 19, the authorities conducted enforcement of the counting, clearance, and construction protection for the Tay Phu Van New Urban Area Project.

Speed up the progress of site clearance for Ninh Binh - Hai Phong expressway

|

Ninh Binh - After the merger, Ninh Binh province is focusing on speeding up the site clearance progress of the Ninh Binh - Hai Phong Expressway Project, the section passing through the province.

6 LED screens on Nguyen Hue pedestrian street are ready to fuel U23 Vietnam in the semi-finals

|

Ho Chi Minh City - On the morning of January 20, the installation of 6 large LED screens along Nguyen Hue pedestrian street is completing the final stage to serve U23 Vietnam fans in time.

U23 Vietnam vs U23 China Preview in the U23 Asian Championship semi-finals

|

Football prediction for the match between U23 Vietnam and U23 China in the semi-finals of the 2026 AFC U23 Championship taking place at 10:30 PM tonight (January 20).

International trust placed on the 14th Party Congress

|

The 14th National Party Congress (from January 19-25) will discuss, give opinions and approve many particularly important draft documents, which are of long-term orientation for the country's development. International friends in Vietnam also expressed their belief in the success of the 14th Congress.

Promoting intelligence, solidarity, and innovation - The foundation for the new development phase of Ho Chi Minh City

|

The 14th National Party Congress takes place at a time of special significance: the country celebrates 40 years of persistent renovation, its international position and prestige are constantly being enhanced. At the same time, the world and regional context is volatile, complex, and unpredictable, posing increasingly high requirements for the Party's leadership and governance capacity.

It's a bit of a bit of a bit of a bit of a bit of a bit.

Effectively mobilizing resources, promoting potential and advantages - The driving force for Ca Mau to develop quickly and sustainably in the new era

|

In the atmosphere of excitement and belief of the entire Party, people and army, we are heading towards the 14th National Party Congress - a major political event, a historical milestone opening the era of national development and rise, today (January 20), in Hanoi Capital, the Congress enters the second working day with important agenda items.

Hung Yen builds 7 resettlement areas to serve the Ninh Binh - Hai Phong expressway

Mai Hương |

Hung Yen - The Ninh Binh - Hai Phong expressway project through the province is on schedule, with a site handover rate of 85%.

Ninh Binh enforces land acquisition to implement Tay Phu Van New Urban Area Project

NGUYỄN TRƯỜNG |

Ninh Binh - On November 19, the authorities conducted enforcement of the counting, clearance, and construction protection for the Tay Phu Van New Urban Area Project.

Speed up the progress of site clearance for Ninh Binh - Hai Phong expressway

NGUYỄN TRƯỜNG |

Ninh Binh - After the merger, Ninh Binh province is focusing on speeding up the site clearance progress of the Ninh Binh - Hai Phong Expressway Project, the section passing through the province.