The 3-storey, trillion-dong intersection in the East of Ho Chi Minh City has been under construction for 8 years and is not yet completed

MINH QUÂN |

After 8 years of construction, the My Thuy intersection project - a project expected to "rescue" traffic congestion in the East of Ho Chi Minh City - is only 48% complete, despite an investment of more than 3,600 billion VND.

My Thuy intersection is located on an important route: Dong Van Cong - Vo Chi Cong - Nguyen Thi Dinh (in Thanh My Loi ward, Thu Duc city), is the gateway to Cat Lai port - the largest port in the country in terms of cargo volume.

This is an area that often experiences serious traffic congestion and is one of the 9 black spots for traffic accidents in Ho Chi Minh City.

Un tac tren duong Nguyen Thi Dinh doan gan nut giao My Thuy.  Anh: Minh Quan
Traffic jam on Nguyen Thi Dinh street, near My Thuy intersection. Photo: Minh Quan

The My Thuy intersection project is designed on a 3-storey scale with a total initial investment of about 1,998 billion VND, approved in principle by the Ho Chi Minh City People's Council in 2016 and expected to be completed in 2021.

However, although construction started in 2016, the project has only reached 48% of the total workload.

Some major items have been completed, including: Ky Ha 3 bridge (left branch) 75m long with 4 lanes; left turn tunnel from Ring Road 2 to Cat Lai port 505m long (2 lanes); overpass on Ring Road 2 with 4 lanes; My Thuy 3 bridge with 6 lanes.

Since 2021, the project has been suspended due to problems with site clearance. In August 2022, the Ho Chi Minh City People's Council decided to adjust the total investment of the project to VND 3,622 billion, an increase of more than VND 1,623 billion compared to the original, mainly due to increased site clearance costs.

The site clearance work was then separated into a separate project, invested by Thu Duc City People's Committee.

Du an nut giao My Thuy van dang do sau 8 nam thi cong.  Anh: Minh Quan
The My Thuy intersection project (Thu Duc City, Ho Chi Minh City) remains unfinished after 8 years of construction. Photo: Minh Quan

In April this year, the project was restarted with the construction of Ky Ha 4 Bridge. However, according to the Ho Chi Minh City Traffic Construction Investment Management Board (the investor), the slow site clearance process continues to hinder construction.

Up to now, Thu Duc City People's Committee has only been able to hand over 1 out of 195 cases needing land to the investor, making it almost impossible for the project to progress.

The construction package of Ky Ha 4 bridge and the right turn from Phu My bridge has only reached about 16%.

The construction packages for the road branches and underpasses on the left and right banks of My Thuy canal have reached 15% and 50% respectively, but are currently suspended due to land acquisition problems.

The project was allocated more than 757 billion VND in capital this year, but only more than 9.5 billion VND has been disbursed, reaching a rate of 1.25%.

Un tac tren cau My Thuy 3 gan nut giao My Thuy.  Anh: Minh Quan
Traffic jam on My Thuy 3 bridge near My Thuy intersection. Photo: Minh Quan

In order to avoid further delays in the project, Vice Chairman of the Ho Chi Minh City People's Committee Bui Xuan Cuong has assigned the Thu Duc City People's Committee to urgently complete and finalize procedures related to compensation, support, and resettlement, and hand over the entire cleared site to the investor before December 31.

In the immediate future, the site related to the abutment and piers of Cat Lai overpass and the construction site of abutment M1 of Ky Ha 4 bridge must be handed over before November 15.

As planned, My Thuy intersection will be completed in December 2025, helping to reduce congestion and the risk of accidents in the East of Ho Chi Minh City.

MINH QUÂN
TIN LIÊN QUAN

The Eastern road of Ho Chi Minh City has been waiting for 9 years but still has not been widened

|

HCMC - The project to expand Luong Dinh Cua Street (Thu Duc City) with an investment capital of 826 billion VND has been implemented for 9 years, but the completion date has not yet been determined.

Road and bridge projects delayed, traffic jams surround the East of Ho Chi Minh City

|

Beltway 2, My Thuy intersection, An Phu intersection, Tang Long bridge, and the expansion of National Highway 13 are behind schedule, causing traffic jams to surround Thu Duc City and the eastern part of Ho Chi Minh City.

Clarifying responsibility for issuing wrong red books on prison land

|

Lam Dong - Provincial inspectors determined that 4.29 hectares of land of Dai Binh Prison had been illegally granted red books by local authorities to 7 households.

Inadequate treatment of officials and workers

|

National Assembly delegates said that the treatment of officials and employees working at drug rehabilitation facilities is not commensurate with the requirements and tasks of the job.

Nam Dinh has a new Provincial Party Secretary

|

Nam Dinh - Mr. Dang Khanh Toan was mobilized and appointed by the Politburo to hold the position of Secretary of Nam Dinh Provincial Party Committee.

Go Cong sea dike "fluctuates" before monsoon season

|

Tien Giang - Some sections of the Go Cong sea dike are degraded, local authorities in Go Cong Dong district have proposed investing in wave-reducing dikes.

Sad news

|

Mr. Ignatius Do Van Luan, born in 1956, father of comrade Do Thi Yen Phuong, father-in-law of comrade Nguyen Van Quang - reporter of Lao Dong Newspaper working at the Representative Office in the Mekong Delta, passed away at 2:00 p.m. on November 13, 2024, October 13, Giap Thin year. He was 68 years old.

Proposal to discipline former Minister of Transport Nguyen Van The

|

At the 50th Session, the Central Inspection Committee proposed that competent authorities consider and discipline Mr. Nguyen Van The.

The Eastern road of Ho Chi Minh City has been waiting for 9 years but still has not been widened

MINH QUÂN |

HCMC - The project to expand Luong Dinh Cua Street (Thu Duc City) with an investment capital of 826 billion VND has been implemented for 9 years, but the completion date has not yet been determined.

Road and bridge projects delayed, traffic jams surround the East of Ho Chi Minh City

MINH QUÂN |

Beltway 2, My Thuy intersection, An Phu intersection, Tang Long bridge, and the expansion of National Highway 13 are behind schedule, causing traffic jams to surround Thu Duc City and the eastern part of Ho Chi Minh City.

Cửa ngõ phía Đông TPHCM kẹt xe cả buổi sáng, giao thông hỗn loạn

NHƯ QUỲNH |

TPHCM - Việc cơ quan chức năng đóng cao tốc TPHCM - Long Thành - Dầu Giây để xử lý tại nạn vào sáng sớm khiến đường Võ Chí Công kẹt xe cả buổi sáng. Thêm một vụ va chạm khác giữa xe ôtô và xe đầu kéo tại vòng xoay Phú Hữu khiến giao thông càng hỗn loạn.