Criticizing the investor for building a multi-level boarding school in Cao Bang

Trọng Lộc |

Cao Bang - Chairman of the Provincial People's Committee criticized many related units for allowing delays to occur when building inter-level boarding schools.

Cao Bang is deploying the construction of 11 ethnic minority boarding primary and secondary schools in border communes to meet the learning and living needs of highland students.

As Lao Dong Newspaper has reported, although required to be completed before August 30, 2026, many projects are still behind schedule.

According to PV's investigation, phase 1 has 11 projects implemented, of which 10 projects use state budget capital, and Phuc Hoa Ethnic Minority Boarding Primary and Secondary School is invested from funding from Hanoi City.

Đức Long đang là một trong những dự án chậm tiến độ nhất tại Cao Bằng. Ảnh: Trọng Lộc
Duc Long is one of the slowest projects in Cao Bang. Photo: Trong Loc

Real-world records show that by July 2026, most of the projects have completed ground leveling, foundation construction, or are preparing to build the first floors.

Many projects such as Lung Nam, Quang Han, Duc Long, Truong Ha, Dam Thuy, Dinh Phong and Phuc Hoa... the progress achieved ranges from 25-38%.

The whole province has many projects behind schedule, putting great pressure in the context of the new school year approaching.

On July 6, information from Cao Bang Provincial People's Committee, Chairman of the Provincial People's Committee Le Hai Hoa just inspected the construction progress of inter-level boarding schools in Duc Long, Phuc Hoa, Dam Thuy, Dinh Phong and Quang Trung border communes.

At the scene, the delegation inspected classrooms, administration buildings, dormitories, dining rooms, technical infrastructure; listened to the investor, consulting unit and contractors report on progress, difficulties and solutions to accelerate construction.

Chủ tịch UBND tỉnh Cao Bằng Lê Hải Hòa (áo đen) kiểm tra thực địa tại Trường Nội trú liên cấp Tiểu học và Trung học cơ sở xã Quang Trung. Ảnh: Cổng thông tin tỉnh Cao Bằng
Chairman of Cao Bang Provincial People's Committee Le Hai Hoa (in black shirt) inspects the field at Quang Trung Commune Inter-level Primary and Secondary Boarding School. Photo: Cao Bang Provincial Information Portal

According to the Cao Bang Provincial Investment and Construction Project Management Board, the projects are being accelerated, but some items are still at risk of being delayed due to the impact of prolonged rainy weather and difficult construction conditions.

Through inspection, the Chairman of the Provincial People's Committee recorded positive changes at the Phuc Hoa, Dam Thuy and Quang Trung projects when units proactively mobilized forces, organized more construction teams and had positive progress.

However, the Chairman of the Provincial People's Committee seriously criticized the progress of the 2 projects Duc Long and Dinh Phong; saying that the contractor, construction site commander and the Investment and Construction Project Management Board of Cao Bang province (the investor) have not closely followed the site, have not promptly removed difficulties, and have delayed many key items compared to requirements.

Chairman of the Provincial People's Committee requests replacement of construction site commanders at two projects Duc Long and Dinh Phong.

At the same time, directing contractors to urgently supplement skilled personnel, organize construction simultaneously in many directions, increase shifts, increase crews, review the roadmap and prioritize completing items serving the opening ceremony.

Dự án tại xã Trà Lĩnh một trong 2 công trình có tiến độ tốt nhất tỉnh Cao Bằng, có thể về đích đúng hẹn. Ảnh: Trọng Lộc
The project in Tra Linh commune is one of the two projects with the best progress in Cao Bang province, which can be completed on schedule. Photo: Trong Loc

In case the contractor does not meet the requirements, the investor must transfer the volume or supplement subcontractors according to regulations, and at the same time issue a written warning and handle responsibilities for units that are behind schedule.

Các dự án trường nội trú liên cấp tại Cao Bằng đang nhận sự hỗ trợ từ quân đội. Ảnh: Trọng Lộc
Inter-level boarding school projects in Cao Bang are receiving support from the military. Photo: Trong Loc
Toàn cảnh dự án tại xã Đàm Thủy. Ảnh: Trọng Lộc
Overview of the project in Dam Thuy commune. Photo: Trong Loc

For the Project Management Board, departments, branches and localities, the Chairman of the Provincial People's Committee requested to strengthen close monitoring of each project, control progress daily, and promptly remove obstacles related to human resources, materials, site clearance, payment and procedures.

The Office of the Provincial People's Committee is assigned to continue to organize regular inspections to ensure that projects are completed on schedule and meet the requirements for the opening of the 2026 - 2027 school year.

Trọng Lộc
RELATED NEWS

Lai Chau mobilizes officers and soldiers to support the construction of a multi-level boarding school

|

Lai Chau - "100 days and nights peak campaign" mobilizes officers and soldiers to support the construction of inter-level boarding schools in border communes.

9/11 multi-level boarding schools in Cao Bang are behind schedule

|

Cao Bang - Manpower shortages and unfavorable weather are the reasons hindering construction at boarding schools.

Overview of 11 boarding school projects in Cao Bang ahead of schedule

|

Cao Bang - Assigned to complete before August 30, contractors at the construction site of 11 inter-level boarding schools are accelerating construction.

Deputy Prime Minister Nguyen Van Thang becomes Chairman of the Executive Council of the International Financial Center

|

Deputy Prime Minister Nguyen Van Thang was assigned to be the Chairman of the Executive Council of the International Financial Center in Vietnam.

From July 9-10, Hanoi Police will ban and temporarily suspend vehicles on many roads

|

Hanoi - City police temporarily ban and restrict vehicles on many roads to serve the "Peaceful Fatherland" Gala.

Launching a contest to learn about major resolutions of the Party, Fatherland Front and Trade Union

|

On the afternoon of July 6, the Party Committee of the Vietnam General Confederation of Labour organized the Launching Ceremony of the online contest "Understanding the Resolution of the 14th National Congress of the Party, Resolution of the 1st Congress of the Party Committee of the Vietnam Fatherland Front, Central Agencies, Resolution of the 14th Congress of the Vietnam Trade Union, term 2026-2031".

Lai Chau mobilizes officers and soldiers to support the construction of a multi-level boarding school

THANH BÌNH |

Lai Chau - "100 days and nights peak campaign" mobilizes officers and soldiers to support the construction of inter-level boarding schools in border communes.

9/11 multi-level boarding schools in Cao Bang are behind schedule

Long An |

Cao Bang - Manpower shortages and unfavorable weather are the reasons hindering construction at boarding schools.

Overview of 11 boarding school projects in Cao Bang ahead of schedule

Long An |

Cao Bang - Assigned to complete before August 30, contractors at the construction site of 11 inter-level boarding schools are accelerating construction.