Criticizing the investor for building a multi-level boarding school in Cao Bang

Trọng Lộc |

Cao Bang - Chairman of the Provincial People's Committee criticized many related units for allowing delays to occur when building inter-level boarding schools.

Cao Bang is deploying the construction of 11 ethnic minority boarding primary and secondary schools in border communes to meet the learning and living needs of highland students.

As Lao Dong Newspaper has reported, although required to be completed before August 30, 2026, many projects are still behind schedule.

According to PV's investigation, phase 1 has 11 projects implemented, of which 10 projects use state budget capital, and Phuc Hoa Ethnic Minority Boarding Primary and Secondary School is invested from funding from Hanoi City.

Đức Long đang là một trong những dự án chậm tiến độ nhất tại Cao Bằng. Ảnh: Trọng Lộc
Duc Long is one of the slowest projects in Cao Bang. Photo: Trong Loc

Real-world records show that by July 2026, most of the projects have completed ground leveling, foundation construction, or are preparing to build the first floors.

Many projects such as Lung Nam, Quang Han, Duc Long, Truong Ha, Dam Thuy, Dinh Phong and Phuc Hoa... the progress achieved ranges from 25-38%.

The whole province has many projects behind schedule, putting great pressure in the context of the new school year approaching.

On July 6, information from Cao Bang Provincial People's Committee, Chairman of the Provincial People's Committee Le Hai Hoa just inspected the construction progress of inter-level boarding schools in Duc Long, Phuc Hoa, Dam Thuy, Dinh Phong and Quang Trung border communes.

At the scene, the delegation inspected classrooms, administration buildings, dormitories, dining rooms, technical infrastructure; listened to the investor, consulting unit and contractors report on progress, difficulties and solutions to accelerate construction.

Chủ tịch UBND tỉnh Cao Bằng Lê Hải Hòa (áo đen) kiểm tra thực địa tại Trường Nội trú liên cấp Tiểu học và Trung học cơ sở xã Quang Trung. Ảnh: Cổng thông tin tỉnh Cao Bằng
Chairman of Cao Bang Provincial People's Committee Le Hai Hoa (in black shirt) inspects the field at Quang Trung Commune Inter-level Primary and Secondary Boarding School. Photo: Cao Bang Provincial Information Portal

According to the Cao Bang Provincial Investment and Construction Project Management Board, the projects are being accelerated, but some items are still at risk of being delayed due to the impact of prolonged rainy weather and difficult construction conditions.

Through inspection, the Chairman of the Provincial People's Committee recorded positive changes at the Phuc Hoa, Dam Thuy and Quang Trung projects when units proactively mobilized forces, organized more construction teams and had positive progress.

However, the Chairman of the Provincial People's Committee seriously criticized the progress of the 2 projects Duc Long and Dinh Phong; saying that the contractor, construction site commander and the Investment and Construction Project Management Board of Cao Bang province (the investor) have not closely followed the site, have not promptly removed difficulties, and have delayed many key items compared to requirements.

Chairman of the Provincial People's Committee requests replacement of construction site commanders at two projects Duc Long and Dinh Phong.

At the same time, directing contractors to urgently supplement skilled personnel, organize construction simultaneously in many directions, increase shifts, increase crews, review the roadmap and prioritize completing items serving the opening ceremony.

Dự án tại xã Trà Lĩnh một trong 2 công trình có tiến độ tốt nhất tỉnh Cao Bằng, có thể về đích đúng hẹn. Ảnh: Trọng Lộc
The project in Tra Linh commune is one of the two projects with the best progress in Cao Bang province, which can be completed on schedule. Photo: Trong Loc

In case the contractor does not meet the requirements, the investor must transfer the volume or supplement subcontractors according to regulations, and at the same time issue a written warning and handle responsibilities for units that are behind schedule.

Các dự án trường nội trú liên cấp tại Cao Bằng đang nhận sự hỗ trợ từ quân đội. Ảnh: Trọng Lộc
Inter-level boarding school projects in Cao Bang are receiving support from the military. Photo: Trong Loc
Toàn cảnh dự án tại xã Đàm Thủy. Ảnh: Trọng Lộc
Overview of the project in Dam Thuy commune. Photo: Trong Loc

For the Project Management Board, departments, branches and localities, the Chairman of the Provincial People's Committee requested to strengthen close monitoring of each project, control progress daily, and promptly remove obstacles related to human resources, materials, site clearance, payment and procedures.

The Office of the Provincial People's Committee is assigned to continue to organize regular inspections to ensure that projects are completed on schedule and meet the requirements for the opening of the 2026 - 2027 school year.

Trọng Lộc
RELATED NEWS

Lai Chau mobilizes officers and soldiers to support the construction of a multi-level boarding school

|

Lai Chau - "100 days and nights peak campaign" mobilizes officers and soldiers to support the construction of inter-level boarding schools in border communes.

9/11 multi-level boarding schools in Cao Bang are behind schedule

|

Cao Bang - Manpower shortages and unfavorable weather are the reasons hindering construction at boarding schools.

Overview of 11 boarding school projects in Cao Bang ahead of schedule

|

Cao Bang - Assigned to complete before August 30, contractors at the construction site of 11 inter-level boarding schools are accelerating construction.

Central Committee of the Vietnam Youth Federation has a new Chairman

|

Hanoi - Mr. Nguyen Kim Quy was consulted to hold the position of Chairman of the 9th Central Committee of the Vietnam Youth Federation, term 2024-2029.

The last smiles of fishermen staying at sea

|

Gia Lai - After 4 days drifting at sea, 32 fishermen were rescued, but the smiles of fellow shipmen before letting go still remain in the memories of returnees.

The underpass in front of the new Mien Dong Bus Station in Ho Chi Minh City is deeply flooded again after heavy rain

|

Ho Chi Minh City - After a heavy rain on the afternoon of September 15, the new Mien Dong Bus Station underpass was flooded, causing many vehicles to stall, and people had to turn around and drive in the opposite direction.

Van Hau banned for 4 matches after a rough foul on Doan Ngoc Tan

|

The Disciplinary Committee of the Vietnam Football Federation has issued additional penalties for Doan Van Hau and Da Silva after rough fouls in round 2 of the V.League.

Number of patients hospitalized suspected of poisoning after eating bread in Quang Tri continues to increase

|

Quang Tri - The number of people hospitalized suspected of poisoning after eating bread has increased to 46 cases.

Lai Chau mobilizes officers and soldiers to support the construction of a multi-level boarding school

THANH BÌNH |

Lai Chau - "100 days and nights peak campaign" mobilizes officers and soldiers to support the construction of inter-level boarding schools in border communes.

9/11 multi-level boarding schools in Cao Bang are behind schedule

Long An |

Cao Bang - Manpower shortages and unfavorable weather are the reasons hindering construction at boarding schools.

Overview of 11 boarding school projects in Cao Bang ahead of schedule

Long An |

Cao Bang - Assigned to complete before August 30, contractors at the construction site of 11 inter-level boarding schools are accelerating construction.