Phu Tho - Many years ago, when Viet Tri ward invested in renovating it, Hung Vuong square was once constructed by Hau "firecrackers" and was involved in no small amount of noise.

New project 85 billion VND

Located in Viet Tri ward, Phu Tho province, Hung Vuong Square is both a symbolic location and a place to organize major events such as the opening of the Hung Temple Festival, art programs, Tet markets, cultural and sports events...

The project "Ilumination, decoration, fountain system in Hung Vuong Square area, Viet Tri ward, Phu Tho province" was approved according to Decision No. 1225/QD-UBND dated December 22, 2025 of Viet Tri Ward People's Committee.

This project has a total investment of 85 billion VND invested by the Viet Tri Ward Construction Investment Project Management Board (under the People's Committee of Viet Tri Ward).

As Lao Dong Newspaper has reported, on May 22, the project investor issued a bidding invitation notice for "Package No. 03: Construction and installation of works".

Đang có sự kiện được tổ chức trong quảng trường. Ảnh: PV
An event is being held in the square. Photo: To Cong

The above-mentioned construction package was widely bid through the network, with a price of 80 billion VND from the Phu Tho provincial budget, Viet Tri ward budget and mobilizing other legal capital sources.

In the near future, after completing the contractor selection for package No. 03, the winning bidder will deploy the construction of lighting, decoration, and fountain systems in the Hung Vuong square area.

According to the project dossier, the construction investment scale of the bidding package includes:

The floor sound water music system is built on the square campus with a total construction area of about 3,400m2 with a system including: About 1,000 shaped nozzles, about 1,000 submerged pumps, more than 1,000 LED lights and controlled electrical cabinet systems, electrical cables, computers, sound...

Một số vòi phun nước và đèn LED sẽ được bố trí trong quảng trường. Ảnh: Bản vẽ
Some water fountains and LED lights will be arranged in the square. Photo: Draft

The elliptical fountain system (including 2 fountains) symmetry on both sides of the square has a total construction scale of about 1,500m2 combined with systems including: Sculpture nozzles; 3-phase and submerged pumps; LED lights and control cabinets, industrial computers, electrical cables...

The contractor will construct, renovate, plant, and arrange green trees to create harmony for the overall architectural structure of the project area; install public utilities, transformer stations serving the project and some other auxiliary items.

Old project noisy due to Hau "firecracker"

Looking back at the history of this square, it is necessary to recall the milestone of August 25, 2009, the time when Phu Tho Provincial People's Committee approved the Hung Vuong Square and resettlement areas project.

After that, this project was appraised by the Ministry of Planning and Investment and the Ministry of Finance; implementation time until December 31, 2015.

Một góc với nhiều cây xanh trong quảng trường. Ảnh: PV
A corner with many green trees in the square. Photo: To Cong

The project was started on May 14, 2011, by Asia Dong Construction and Trading Investment Joint Stock Company - a subsidiary of Phuc Son Group (commonly referred to as Hau "firecracker") with a total investment of more than 771 billion VND.

In which, construction costs are more than 222 billion VND, compensation costs for site clearance and resettlement are more than 48.6 billion VND; Viet Tri City Infrastructure Construction Project Management Board (old) is the representative of the investor.

Một số vị trí bị bong tróc nặng. Ảnh: PV
The square yard has a heavily peeling location. Photo: To Cong

Records of Lao Dong Newspaper reporters in the last days of May 2026 show that after more than a decade of operation, the items of the old Hung Vuong Square project have deteriorated.

Các vết sụt lún ở sân quảng trường. Ảnh: PV
Subsidence marks in the square yard. Photo: To Cong

The most obvious thing is that the floor tiles at many locations have appeared cracked, broken, and peeling; many locations of the foundation are subsided and deformed.

According to Lao Dong's private source, although the project was completed and put into use in 2015, many years later, the procedures for finalizing public investment capital according to regulations have not been completed.

Khu vực này mặt sân đã hư hỏng nhiều. Ảnh: PV
The yard surface in this area has been heavily damaged. Photo: To Cong

Therefore, in 2023, Phu Tho Provincial People's Committee issued a document to strengthen and definitively handle the finalization of public investment capital for completed projects in the area, including the Hung Vuong Square project constructed by Phuc Son's subsidiary.

The above project, along with projects such as: Renovation and upgrading at the Hung Temple relic site; the project to invest in building works to renovate, reinforce and upgrade Au Co road - is one of the projects with a large total investment that Phuc Son Group has implemented in the old Phu Tho province.

Long Nguyễn
RELATED NEWS

Auction of more than 3,000m2 of land in Phu Tho, total starting price of more than 17 billion VND

|

Phu Tho - 19 residential land plots in Hoang Cuong commune are about to be auctioned, with a total starting price of over 17 billion VND.

Viet Tri Ward implements an 85 billion VND project to "change clothes" for Hung Vuong square

|

Phu Tho - Hung Vuong Square in Viet Tri ward will be invested in lighting systems, decorations, and fountains, promising to create highlights for the area.

Phu Tho plans to provide free health check-ups throughout the province

|

Phu Tho - The plan for periodic health check-ups or free screening will be implemented throughout the province, applied to all people.

Ngoc Son is not afraid of affecting his reputation when publicly revealing that he once got into trouble with the law

|

After the drug testing move, Ngoc Son revealed the reason why he remained silent for 34 years without explaining his previous legal troubles.

Hung Vuong Square is about to "change clothes" after a series of scandals

|

Phu Tho - Many years ago, when Viet Tri ward invested in renovating it, Hung Vuong square was once constructed by Hau "firecrackers" and was involved in no small amount of noise.

Outdoor workers struggle to make a living in the scorching heat in Hanoi

|

The intense heat in Hanoi makes outdoor workers tired, easily exhausted and forced to change working hours to ensure health when making a living.

Auction of more than 3,000m2 of land in Phu Tho, total starting price of more than 17 billion VND

Tân Văn |

Phu Tho - 19 residential land plots in Hoang Cuong commune are about to be auctioned, with a total starting price of over 17 billion VND.

Viet Tri Ward implements an 85 billion VND project to "change clothes" for Hung Vuong square

Tô Công |

Phu Tho - Hung Vuong Square in Viet Tri ward will be invested in lighting systems, decorations, and fountains, promising to create highlights for the area.

Phu Tho plans to provide free health check-ups throughout the province

Tô Công |

Phu Tho - The plan for periodic health check-ups or free screening will be implemented throughout the province, applied to all people.