Long Thanh Airport: Some bidding packages exceed 90%, new bidding packages reach 36%

HÀ ANH CHIẾN |

Dong Nai - Many main construction packages at Long Thanh airport have reached over 90%, including a package that has been basically completed.

On July 26, according to Vietnam Airports Corporation (ACV), the main construction packages at component project 3 of Long Thanh airport to date have reached more than 57,807 billion VND, equivalent to about 69.69% of the contract value.

Package No. 4-6, construction of runways, taxiways, and aircraft landing pads has a volume value of more than 90%.

Package No. 4. 7, construction and installation of equipment for aircraft apron and passenger terminal, the value of the implemented volume reached nearly 90%.

Package No. 4. 8, construction of inland port traffic and airport technical infrastructure, the value of implemented volume reached nearly 65%.

Package No. 4. 9, construction of aircraft fuel supply system has a volume value of nearly 88%.

Package No. 4. 12, construction of the 2nd runway, taxiway and other synchronous works has a volume value of more than 59%.

Package No. 5-10, passenger terminal construction has a volume value of more than 67%.

Package No. 5. 11, construction of airport management system has a volume value of more than 51%.

Package No. 6. 12, construction of connecting traffic (route No. 1 and route No. 2) has been basically completed.

Package No. 11. 5, parking garage construction has a volume value of nearly 37%. According to the schedule, this package will be completed on October 30, 2026.

Package No. 7-8, construction of cargo terminal No. 1 and auxiliary works has a volume value of about 36%. According to the plan, this package will be completed on October 30, 2026.

Previously, component project 3 of Long Thanh airport also completed 3 bidding packages including: bidding package 2.4 (inner fence 1.810ha), bidding package 3.4 (base leveling and drainage) and bidding package 5.6 (pile construction of passenger terminal).

The entire component project 3 of Long Thanh airport has a total production value of about 77.85%. The total investment of the project is 99. 019 billion VND.

Long Thanh Airport phase 1 builds 2 runways, 1 passenger terminal and synchronous auxiliary items, with a capacity of 25 million passengers/year and 1.2 million tons of cargo/year; completion and commissioning time at the end of 2026.

HÀ ANH CHIẾN
RELATED NEWS

Long Thanh airport reaches nearly 78%, still lacking 2,000 workers

|

Dong Nai - Long Thanh airport construction site is maintaining more than 7,000 direct workers and will increase to 9,000 people to complete the project.

Developing a detailed plan for 5,000ha of Long Thanh airport, preparing for phase 2

|

Dong Nai - Airports Corporation of Vietnam (ACV) is implementing detailed planning for the Long Thanh airport project on a total area of 5,000ha.

Close-up of the lotus-shaped lighting roof system at Long Thanh airport terminal

|

Dong Nai - Long Thanh airport passenger terminal center with a lotus-shaped light-taking roof system is gradually being completed, creating a unique architectural highlight.

Saigon Hot News: Site clearance for drainage project outside Long Thanh airport

|

Saigon Hot News July 16: Site clearance for a 19km long drainage project outside Long Thanh airport; N4 overpass branch at An Phu intersection to be opened to traffic soon;...

Principal reflects disadvantages because teacher gives birth to third child

|

Nghe An - Principal reflects being reduced in ranking because the school has a teacher who gives birth to a third child, affecting the opportunity to be arranged after the merger.

Memories of comrades who lay down on the Quang Tri battlefield

|

Memories of the Quang Tri battlefield are still intact in the minds of female wounded soldiers, from emergency cases amidst bombs and bullets to moments of life and death on the battlefield.

New roofs open a way to settle down for people in flood-affected Muong Than areas

|

Lai Chau - New roofs are being built every day in the resettlement area in Muong Than commune, helping people in flood-affected areas soon stabilize their lives.

The movie scene "Living with Mother-in-law" about gold and diamonds after 9 years is causing a storm again

|

A scene in the movie "Living with Mother-in-law" with characters going to buy precious diamonds suddenly caused a storm on social networks.

Long Thanh airport reaches nearly 78%, still lacking 2,000 workers

HÀ ANH CHIẾN |

Dong Nai - Long Thanh airport construction site is maintaining more than 7,000 direct workers and will increase to 9,000 people to complete the project.

Developing a detailed plan for 5,000ha of Long Thanh airport, preparing for phase 2

HÀ ANH CHIẾN |

Dong Nai - Airports Corporation of Vietnam (ACV) is implementing detailed planning for the Long Thanh airport project on a total area of 5,000ha.

Close-up of the lotus-shaped lighting roof system at Long Thanh airport terminal

HÀ ANH CHIẾN |

Dong Nai - Long Thanh airport passenger terminal center with a lotus-shaped light-taking roof system is gradually being completed, creating a unique architectural highlight.

Saigon Hot News: Site clearance for drainage project outside Long Thanh airport

NHÓM PV |

Saigon Hot News July 16: Site clearance for a 19km long drainage project outside Long Thanh airport; N4 overpass branch at An Phu intersection to be opened to traffic soon;...