Long Thanh airport reaches nearly 78%, still lacking 2,000 workers

HÀ ANH CHIẾN |

Dong Nai - Long Thanh airport construction site is maintaining more than 7,000 direct workers and will increase to 9,000 people to complete the project.

On July 25, according to Vietnam Airports Corporation (ACV), component project 3 of Long Thanh airport has reached about 77.85% of the total value of signed contracts.

For the main construction packages, the accumulated value implemented to date reached 57,807 billion VND, equivalent to about 69.69% of the contract value.

On the construction site, an average of 7,170 workers are directly involved in construction.

Currently, the entire project is short of about 1,500 to 2,000 workers (concentrated in packages 5.10; 4.8; 7.8 and 11.5).

To ensure detailed progress, ACV said it is resolutely requesting contractors to mobilize more human resources, aiming for nearly 9,000 direct workers and an indirect team to accelerate internal work and complete dossiers.

Also according to ACV, the project is entering an important stage, to organize construction to ensure progress and quality of the project during the rainy season, ACV has requested contractors to thoroughly implement construction measures such as: establishing scientific construction progress from the beginning; establishing an effective drainage system at the project; closely monitoring weather developments and flexibly adjusting construction according to actual conditions; having contingency plans for arising situations.

Long Thanh airport project reaches level 4F according to the classification of the International Civil Aviation Organization (ICAO), with an investment scale of 100 million passengers/year and 5 million tons of cargo/year.

In which, phase 1 builds 2 runways, 1 passenger terminal and synchronous auxiliary items, with a capacity of 25 million passengers/year and 1.2 million tons of cargo/year; completion time and commissioning at the end of 2026.

Latest images of Long Thanh airport construction, Dong Nai city:

Gói thầu số 5.10 - Thi công xây dựng và lắp đặt thiết bị công trình nhà ga hành khách sân bay Long Thành đã đạt khối lượng khoảng 67,08% so với giá trị hợp đồng. Ảnh: Tổng Công ty Cảng hàng không Việt Nam
Package No. 5.10 - Construction and installation of equipment for the Long Thanh airport passenger terminal has reached a volume of about 67.08% compared to the contract value. Photo: Airports Corporation of Vietnam
Hệ mái nhà ga hành khách sân bay Long Thành được thiết kế với những đường nét mềm mại, thanh thoát, tái hiện hình ảnh đóa sen đang bung nở. Ảnh: Tổng Công ty Cảng hàng không Việt Nam
The roof of Long Thanh airport passenger terminal is designed with soft, elegant lines, recreating the image of a blooming lotus. Photo: Airports Corporation of Vietnam
Một khu vực nhà ga hành khách sân bay Long Thành đang dần hoàn thiện. Ảnh: Tổng Công ty Cảng hàng không Việt Nam
A passenger terminal area of Long Thanh airport is gradually being completed. Photo: Airports Corporation of Vietnam
Kế hoạch tiến độ gói thầu 5.10 sẽ hoàn thành cơ bản tất cả các hạng mục đưa vào vận hành thử các đợt từ tháng 9.2026 và vận hành khai thác thương mại vào tháng 12.2026. Ảnh: Tổng Công ty Cảng hàng không Việt Nam
ACV aims to increase the total number of personnel directly on the project site to 9,000 to complete the project. Photo: Airports Corporation of Vietnam
ACV đặt mục tiêu nâng tổng số nhân sự trực tiếp trên công trường dự án lên 9.000 người để hoàn thiện dự án.
The progress plan for package 5.10 will basically complete all items to put into trial operation in batches from September 2026 and commercial operation in December 2026. Photo: Airports Corporation of Vietnam
Dự án thành phần 3 thuộc dự án sân bay Long Thành giai đoạn 1 có tổng mức đầu tư: 99.019 tỉ đồng. Ảnh: Tổng Công ty Cảng hàng không Việt Nam
Component project 3 of the Long Thanh airport phase 1 project has a total investment of 99,019 billion VND. Photo: Airports Corporation of Vietnam

HÀ ANH CHIẾN
RELATED NEWS

Close-up of the lotus-shaped lighting roof system at Long Thanh airport terminal

|

Dong Nai - Long Thanh airport passenger terminal center with a lotus-shaped light-taking roof system is gradually being completed, creating a unique architectural highlight.

Saigon Hot News: Site clearance for drainage project outside Long Thanh airport

|

Saigon Hot News July 16: Site clearance for a 19km long drainage project outside Long Thanh airport; N4 overpass branch at An Phu intersection to be opened to traffic soon;...

Ho Chi Minh City accelerates land acquisition to extend Metro Line 1 to Long Thanh airport

|

Ho Chi Minh City urgently recovers land to implement the project to extend Metro Line 1 to Dong Nai City and Long Thanh airport, with a total capital of more than 65,500 billion VND.

Perspective of the road connecting Long Thanh airport passing through 9 communes and wards in Dong Nai

|

Dong Nai - The DT. 770B road construction project, more than 42km long, is a key traffic project of the city, connecting Long Thanh airport.

Beer shop in Thanh Liet ward catches fire, column of smoke rises tens of meters high

|

Hanoi - Beer shop on Vu Duc Uy street catches fire fiercely, accompanied by loud noises. Functional forces are conducting firefighting and rescue.

Landlord collecting electricity bills of 4,000 VND/kWh may be fined from 20 - 30 million VND

|

According to the lawyer, the act of the landlord collecting electricity bills exceeding regulations may be fined from 20 - 30 million VND and forced to return the wrongly collected amount.

Tuyen Quang sends off the remains of martyrs to Vi Xuyen Cemetery

|

Tuyen Quang - In the afternoon of July 25, the Military Command of Tuyen Quang province organized a ceremony to see off the remains of martyrs to be buried at Vi Xuyen National Martyrs' Cemetery.

Metro line No. 5 in Hanoi has more notable movements

|

Hanoi - Metro line No. 5 project continues to expand the construction site with the deployment of S1 Station (Quan Ngua Station).

Close-up of the lotus-shaped lighting roof system at Long Thanh airport terminal

HÀ ANH CHIẾN |

Dong Nai - Long Thanh airport passenger terminal center with a lotus-shaped light-taking roof system is gradually being completed, creating a unique architectural highlight.

Saigon Hot News: Site clearance for drainage project outside Long Thanh airport

NHÓM PV |

Saigon Hot News July 16: Site clearance for a 19km long drainage project outside Long Thanh airport; N4 overpass branch at An Phu intersection to be opened to traffic soon;...

Ho Chi Minh City accelerates land acquisition to extend Metro Line 1 to Long Thanh airport

MINH QUÂN |

Ho Chi Minh City urgently recovers land to implement the project to extend Metro Line 1 to Dong Nai City and Long Thanh airport, with a total capital of more than 65,500 billion VND.

Perspective of the road connecting Long Thanh airport passing through 9 communes and wards in Dong Nai

HÀ ANH CHIẾN |

Dong Nai - The DT. 770B road construction project, more than 42km long, is a key traffic project of the city, connecting Long Thanh airport.