Long Thanh airport approaches the milestone of having 2 runways 4km long

HÀ ANH CHIẾN |

Dong Nai - Package 4.12 construction of the 2nd runway of Long Thanh airport is expected to complete all items before September 30, 2026.

On July 26, according to Vietnam Airports Corporation (ACV), package No. 4.12, construction and installation of equipment for the 2nd runway, taxiway and other synchronous works, the value of implemented volume has now reached about 59.38% compared to the contract value.

Regarding the implementation progress, for runways, 100% of the runway structure has been completed, surface drainage ditch cutting has reached 75.5%, and M150/25 roadside cement concrete has reached 62.2%.

For the rolling stock item, 100% of the 150/25 cement concrete structure and the 350/45 cement concrete structure have been completed, reaching 82.6%.

The service road item has also completed 100% of excavation, pavement and foundation filling, and crushed stone base structure construction reaching 72.5%.

According to the current implementation progress, it is expected to complete the cement concrete work before August 15, 2026 and complete all items of the package before September 30, 2026.

Package 4.12 - 2nd runway, taxiway and other synchronous works were started on May 30, 2025, constructed by the ACC - Truong Son - Vinaconex - Vinadic - ACJC647-Khanh Thien-VTG consortium, with a contract value of 2,570 billion VND.

The second runway is 4 km long and 75 m wide.

Previously, at the end of April 2025, the first runway of Long Thanh airport phase 1 had completed construction and technical operation, exceeding the schedule by 3 months.

According to the schedule, the Long Thanh airport project will be put into operation by the end of 2026.

HÀ ANH CHIẾN
RELATED NEWS

Long Thanh airport reaches nearly 78%, still lacking 2,000 workers

|

Dong Nai - Long Thanh airport construction site is maintaining more than 7,000 direct workers and will increase to 9,000 people to complete the project.

Developing a detailed plan for 5,000ha of Long Thanh airport, preparing for phase 2

|

Dong Nai - Airports Corporation of Vietnam (ACV) is implementing detailed planning for the Long Thanh airport project on a total area of 5,000ha.

Close-up of the lotus-shaped lighting roof system at Long Thanh airport terminal

|

Dong Nai - Long Thanh airport passenger terminal center with a lotus-shaped light-taking roof system is gradually being completed, creating a unique architectural highlight.

Saigon Hot News: Site clearance for drainage project outside Long Thanh airport

|

Saigon Hot News July 16: Site clearance for a 19km long drainage project outside Long Thanh airport; N4 overpass branch at An Phu intersection to be opened to traffic soon;...

Principal reflects disadvantages because teacher gives birth to third child

|

Nghe An - Principal reflects being reduced in ranking because the school has a teacher who gives birth to a third child, affecting the opportunity to be arranged after the merger.

Memories of comrades who lay down on the Quang Tri battlefield

|

Memories of the Quang Tri battlefield are still intact in the minds of female wounded soldiers, from emergency cases amidst bombs and bullets to moments of life and death on the battlefield.

New roofs open a way to settle down for people in flood-affected Muong Than areas

|

Lai Chau - New roofs are being built every day in the resettlement area in Muong Than commune, helping people in flood-affected areas soon stabilize their lives.

The movie scene "Living with Mother-in-law" about gold and diamonds after 9 years is causing a storm again

|

A scene in the movie "Living with Mother-in-law" with characters going to buy precious diamonds suddenly caused a storm on social networks.

Long Thanh airport reaches nearly 78%, still lacking 2,000 workers

HÀ ANH CHIẾN |

Dong Nai - Long Thanh airport construction site is maintaining more than 7,000 direct workers and will increase to 9,000 people to complete the project.

Developing a detailed plan for 5,000ha of Long Thanh airport, preparing for phase 2

HÀ ANH CHIẾN |

Dong Nai - Airports Corporation of Vietnam (ACV) is implementing detailed planning for the Long Thanh airport project on a total area of 5,000ha.

Close-up of the lotus-shaped lighting roof system at Long Thanh airport terminal

HÀ ANH CHIẾN |

Dong Nai - Long Thanh airport passenger terminal center with a lotus-shaped light-taking roof system is gradually being completed, creating a unique architectural highlight.

Saigon Hot News: Site clearance for drainage project outside Long Thanh airport

NHÓM PV |

Saigon Hot News July 16: Site clearance for a 19km long drainage project outside Long Thanh airport; N4 overpass branch at An Phu intersection to be opened to traffic soon;...