Construction of a series of hundred-billion VND traffic projects in Vinh Phuc area is coming soon

Tô Công |

In the Vinh Phuc area of Phu Tho province, a series of large transport projects with a total investment of hundreds of billions of VND are preparing for construction.

274 billion VND to build road from DT. 310B connecting road D3

Component project 2: Investment in the construction of the road from DT. 310B connecting road D3 area of Thanh Lanh village, Trung My commune, Binh Xuyen district (former Vinh Phuc province) with a total investment of 274 billion VND.

According to the reporter's investigation, on August 19, the Vinh Phuc Regional Project Management Board (the investor) issued a bidding invitation notice for the "Construction and installation + Ensuring traffic safety" package of the project (package price of more than 251 billion VND).

In the near future, the winning bidder will construct a project in the area of Ba Hien and Trung My towns, former Binh Xuyen district, now belonging to Binh Tuyen commune, Phu Tho province.

Regarding the scale of construction investment, the road will have a total length of 6.5km, divided into 2 sections:

Section 1 is 3.25km long, is a section that coincides with the planning of Ring Road 5 - Capital Region, designed with geometric elements to ensure the scale of highways, design speed of 100km/h.

Section 1 has a roadbed width of 32.5m, of which the road surface is 28.5m wide (2 sides, each side 14.25m), the rest is the roadside and the median strip.

Các tuyến đường dưới chân núi Tam Đảo tại khu vực Vĩnh Phúc được đầu tư khang trang, hiện đại. Ảnh: Tô Công
Roads at the foot of Tam Dao mountain in Vinh Phuc area are invested in spaciously and modernly. Photo: To Cong

Section 2 is 3.25km long, designed with a scale of level III plain road, design speed of 80km/h (exempting speed of 60km/h for some locations with difficult terrain).

Section 2 has a roadbed width of 12m, a road surface width of 11m (2 sides, 5.5m each side), and the rest is the roadside.

Along with that, the road section is invested in synchronous construction of items: Foundation, road surface, drainage system, bridges on the route, lighting, traffic safety system and other items.

According to the investor, the project is invested with the goal of gradually completing the traffic infrastructure of Ring Road 5 - Capital Region according to the approved plan; and developing a tourist and service area along the foot of Tam Dao mountain... contributing to socio-economic development.

Many large transportation projects are preparing for construction

From the beginning of August to now, in the Vinh Phuc area, many transportation projects with large total investments have implemented the selection of construction contractors (all projects are invested by the Vinh Phuc Regional Project Management Board).

Most recently, Component Project 2: Investment in Construction, Renovation and Upgrading of DT. 306, section from the intersection with Van Quan - Song Lo road to Vinh Phu bridge (total investment of 190 billion VND).

On August 13, the investor issued a bidding invitation notice for the "Construction + Equipment" package of the project (priced at over 177 billion VND).

The road construction package has a length of about 5.153km, starting point at the intersection with Van Quan - Song Lo road, ending point of the route intersecting with the left dike of the Lo River at Km23+850.

Cầu Vĩnh Phú nối xã Sông Lô với phường Việt Trì. Ảnh: Tô Công
Vinh Phu bridge connects Song Lo commune with Viet Tri ward. Photo: To Cong

Previously, the Ring Road 2 project in the western area of Vinh Phuc urban area, the section from DT. 306 to DT. 307 (total investment of more than 358 billion VND) also started looking for a construction contractor.

On August 6, the investor announced the bidding invitation for the "Construction and installation" package (priced at nearly 225 billion VND) of the project.

The road construction package has a length of 4.521km, starting from the end point of the Vinh Phuc urban area West Ring Road 2 project, phase I (section from DT. 305 to DT. 306) intersecting with DT. 306 in Ban Gian commune (old), ending at the intersection with DT. 307 in Hoa Son town (old).

Tuyến ĐT.307 thuộc địa phận thị trấn Hoa Sơn, huyện Lập Thạch trước đây, nay là xã Liên Hòa, tỉnh Phú Thọ. Ảnh: Bùi Trang
DT. 307 route belongs to Hoa Son town, formerly Lap Thach district, now Lien Hoa commune, Phu Tho province. Photo: To Cong

Similarly, Component Project 2: Investment in construction of the traffic route connecting from the left dyke of the Red River to Van Phuc bridge (total investment of nearly 985 billion VND) also started the selection of construction contractors.

On August 3, the investor announced the bidding invitation for the "Construction + Equipment" package (priced at over 870 billion VND) of the project.

The road being built has a total length of about 2.12km, connecting from the left dyke of the Red River to Van Phuc bridge, located in Lien Chau commune, Phu Tho province.

Tô Công
RELATED NEWS

Phu Cuong Group denies information related to the rape of a Vietnamese-American woman in Phu Tho

|

Phu Cuong Group has just issued a notice rejecting information related to the rape case of a Vietnamese-American woman in Phu Tho.

Hoa Binh Hydropower Plant opens 1 bottom discharge gate, Phu Tho requests to ensure downstream safety

|

Phu Tho - On August 19, Phu Tho Provincial People's Committee requested departments, branches and People's Committees of communes and wards to ensure safety for people when Hoa Binh hydropower reservoir discharges bottomwater.

Da Nang considers coercive measures to remove site obstacles for a series of traffic projects

|

Da Nang - Chairman of Da Nang City People's Committee has just directed to definitively remove site obstacles for key traffic projects.

Proposal to reduce 30% tax for businesses with revenue under 10 billion VND

|

The Government proposes a 30% reduction in personal income tax and corporate income tax for business households and businesses with revenue below 10 billion VND.

Heavy rain and tornadoes caused an ancient tree to fall and hit a truck moving on Deo Chuoi Pass

|

Lam Dong - Heavy rain accompanied by tornadoes caused many forest trees and green trees to be uprooted and fallen on National Highway 20, including an ancient tree falling on a truck on Deo Chuoi Pass.

Inspectors point out a series of violations at the Vietnam Academy of Science and Technology

|

The Government Inspectorate has just pointed out many violations in personnel organization and task performance that occurred at the Vietnam Academy of Science and Technology.

Ho Chi Minh City parents run more than 20 km, go to 5-6 places to find textbooks for their children

|

Approaching the school start day, many parents in Ho Chi Minh City have to run dozens of kilometers, finding 5-6 places to gather enough textbooks for their children.

Gold prices surge, people line up to buy, people hesitate to take profits

|

On August 20, domestic gold prices increased sharply. Recorded in Hanoi, many people took advantage of buying gold when prices went up, while some customers considered selling.

Phu Cuong Group denies information related to the rape of a Vietnamese-American woman in Phu Tho

Xuyên Đông |

Phu Cuong Group has just issued a notice rejecting information related to the rape case of a Vietnamese-American woman in Phu Tho.

Hoa Binh Hydropower Plant opens 1 bottom discharge gate, Phu Tho requests to ensure downstream safety

Xuyên Đông |

Phu Tho - On August 19, Phu Tho Provincial People's Committee requested departments, branches and People's Committees of communes and wards to ensure safety for people when Hoa Binh hydropower reservoir discharges bottomwater.

Da Nang considers coercive measures to remove site obstacles for a series of traffic projects

Nguyễn Linh |

Da Nang - Chairman of Da Nang City People's Committee has just directed to definitively remove site obstacles for key traffic projects.