On August 2nd, according to information from the People's Committee of Tran Bien ward, Dong Nai city, the Cai riverside road project section passing through the ward affects 430 households and 4 organizations; of which 324 households are subject to complete clearance and must be resettled. Up to now, households and organizations have handed over land, reaching 100% of the entire project.
The Cai River riverside road project has a route length of nearly 4.6km, with a total investment of nearly 574 billion VND passing through Tran Bien and Tam Hiep wards, with a total land area to be recovered of nearly 15ha.
For Tam Hiep ward, it affects 292 households, individuals and 1 organization. All residents agreed to hand over the site for project construction.
The Cai River riverside road project will invest in building a 32m wide road, 5 bridges on the route and technical infrastructure, green trees, and traffic safety signs.
To date, the progress of the Cai riverside road project has 2 construction packages reaching nearly 90% (construction package No. 10 and construction package No. 20).
With the remaining 2 bidding packages, construction package No. 27 reached about 12%; construction package No. 28 reached about 13%.
The investor and contractor are striving to carry out rolling construction, completing the project before December 31, 2027.