On July 18, according to the Dong Nai City Construction Investment Project Management Board, the Cai Riverside road project (section from Ha Huy Giap road to Tran Quoc Toan road), construction package No. 10 - construction of 5 bridges on the route including: Ba Bot, Chim Tau, Rach Gio, Suoi Linh, Tan Mai, reached nearly 140 billion VND, equivalent to 87% of the contract value.
In the coming time, with construction package No. 10, the contractor will continue to complete the blocking walls of the remaining sections, Rach Gio bridgehead road; complete the girder installation, construct the span structure, bridge deck and Ba Bot bridgehead road; complete the blocking wall, Chim Tau bridgehead road; construct the bridge deck, Tan Mai bridgehead road and complete the road surface, Suoi Linh bridge traffic safety system.
Also at the Cai Riverside Road Project, construction package No. 20 - relocation of high-voltage, medium, low-voltage power lines, transformer stations and lighting under the project, reached more than 14 billion VND, equivalent to 88% of the contract value; construction package No. 27, reached nearly 19 billion VND, equivalent to 12% of the contract value; construction package No. 28, reached more than 21 billion VND, equivalent to 13% of the contract value.
The Cai River Road project has a route length of nearly 4.6km, with a total investment of nearly 574 billion VND. The project will invest in building a 32m wide road, 5 bridges on the route and technical infrastructure, green trees, and traffic safety signs.
To implement the Cai riverside road project, the total land area to be recovered is nearly 15ha in Tran Bien and Tam Hiep ward.
The investor and contractor are striving to carry out rolling construction, completing the project before December 31, 2027.