Increasing sand exploitation capacity for Can Tho - Ca Mau highway

Tạ Quang |

Deputy Minister of Transport Nguyen Duy Lam requested contractors to increase maximum exploitation capacity, add more dredgers and barges to transport sea sand for the expressway project.

On October 15, Deputy Minister of Transport Nguyen Duy Lam led a delegation of the ministry to inspect the construction organization and progress of the North-South Eastern Expressway project, phase 2021-2025, Can Tho - Ca Mau section (Can Tho - Ca Mau Expressway) in Hau Giang province.

Thu truong Nguyen Duy Lam kiem tra cao toc Can Tho - Ca Mau. Anh: Ta Quang
Deputy Minister Nguyen Duy Lam inspects the Can Tho - Ca Mau expressway. Photo: Ta Quang

After listening to the reports from the units, Deputy Minister Nguyen Duy Lam said that over the past time, the investor and contractor have implemented many construction measures and made many efforts to solve difficulties, but the project's progress is still not as planned. That is because the contractors have not mobilized the maximum human and material resources, and the construction organization has not met the requirements.

Deputy Minister of Transport requested contractors to be more determined, increase human resources, equipment and add construction teams, and arrange enough finance to speed up project progress.

Deputy Minister of Transport emphasized that the My Thuan Project Management Board, contractors, supervision consultants... must focus on solving difficulties arising during the construction process, ensuring that by the end of 2024, the load-bearing work and all bridges on the route must be completed.

May moc thi cong cao toc Can Tho - Ca Mau. Anh: Ta Quang
Construction machinery for the Can Tho - Ca Mau expressway. Photo: Ta Quang

Regarding the issue of sand material sources, Deputy Minister Nguyen Duy Lam stated that the current advantage is that the exploitation of sea sand has no capacity limit. In fact, currently, contractors only exploit 12,000 - 13,000 m3/day, while they are allowed to exploit about 30,000 m3/day. Deputy Minister Nguyen Duy Lam proposed to increase the capacity of sea sand exploitation for the project.

According to the report of My Thuan Project Management Board (project investor), as of October 2024, the total construction output of the project reached 46/57%, 11% behind schedule. The demand for materials for the project by the end of 2024 is about 15.5 million m3. Currently, about 9.8 million m3 have been brought to the construction site, with a shortage of about 5.67 million m3.

To ensure the completion of the load-bearing embankment in 2024, the My Thuan Project Management Board has proactively worked with the locality to supplement the sand source. To date, the two provinces of An Giang and Vinh Long have completed sand mine procedures to supply the project with an additional 2.2 million m3, while Dong Thap province has increased the capacity of two sand mines. As for the sand mine in Tien Giang province, about 0.6 million m3, and the two mines in Ben Tre, about 2 million m3, the procedures are being completed.

Regarding stone material sources, the plan to mobilize to load the project in 2024 is about 1.6 million m3, but so far only less than 10% has been mobilized. Due to this difficulty, the Prime Minister has directed An Giang to complete the procedures to extend the mine in August 2024, but so far it has not been completed. Contractors have also been proactively mobilizing stone from neighboring provinces, such as Kien Giang, Dong Nai, Binh Duong...

Tạ Quang
RELATED NEWS

AI cameras enter the cycle, Hanoi traffic improves

|

Hanoi - The new AI camera system put into operation has initially given positive results, the awareness of traffic participants has been significantly improved.

Accident occurs, students startled because they do not have health insurance

|

HCMC - Without health insurance (HI), just an accident or unexpected illness can cause students to fall into debt.

Building a solid ideological shield in the entire Party Committee of the Vietnam Fatherland Front and Central organizations

|

Hanoi - On the afternoon of December 17, the Standing Committee of the Vietnam Fatherland Front Party Committee and Central organizations held a ceremony to summarize and award prizes for the first Party ideological foundation protection contest in 2025.

Proposal to select genes from the time of birth to train the elite

|

The leader of the Hanoi Department of Science and Technology said that to train the elite, it is possible to select people right from birth, selecting genes for training.

Mr. Johnathan Hanh Nguyen is proposed to be awarded the title of Labor Hero

|

The Ministry of Home Affairs is seeking opinions on the proposal to confer the title of "Hero of Labor" to Mr. Johnathan Hanh Nguyen.

Can Tho - Ca Mau Expressway, the journey from muddy to the finish line

|

Can Tho - Ca Mau Expressway is a key project connecting the North - South Expressway axis with the southernmost tip of the country, starting on January 1, 2023 and technically opening to traffic on December 19, 2025.

Information appears that France will send soldiers to Ukraine

|

There are reports that France has sent troops to Ukraine for training, in the context of Russia's continuous strong reaction to the military presence of the West.

SEA Games 33 Medal Schedule on December 17

|

Updated total medal table of the 33rd SEA Games on December 17.

Cao tốc Cần Thơ - Cà Mau: Thi công đường đã chậm, đến cầu cũng chậm

Tạ Quang |

Thứ trưởng Bộ Giao thông vận tải (GTVT) Nguyễn Duy Lâm cho rằng, với sự nỗ lực của Chính phủ, Bộ GTVT và các đơn vị liên quan, vấn đề cát cơ bản đã được tháo gỡ tại dự án cao tốc Cần Thơ - Cà Mau. Tuy nhiên, tiến độ thi công đường, cầu vẫn chậm thì rất khó chấp nhận.

Chưa có thông tin lý do lúa chết hàng loạt cạnh cao tốc Cần Thơ - Cà Mau

Tạ Quang |

Hậu Giang – Nhiều hộ dân ở xã Vị Thắng, huyện Vị Thủy canh tác lúa cạnh cao tốc Cần Thơ – Cà Mau bị chết, kém năng suất do nguồn nước bị nhiễm mặn.

Công nhân bịt kín mít thi công cao tốc Cần Thơ - Cà Mau dưới nắng gần 40 độ

TẠ QUANG |

Dưới cái nắng gần 40 độ C, trên công trường cao tốc Cần Thơ – Cà Mau (đoạn Hậu Giang - Cà Mau), hàng trăm kỹ sư, công nhân vẫn tất bật làm việc. Đối với các công nhân, việc thi công cao tốc là khó tránh khỏi những áp lực của thời tiết...