Accelerate the implementation of a project worth over 170 billion VND connecting infrastructure in Lao Cai

Đinh Đại |

Lao Cai - The construction site of the extended Tran Hung Dao Avenue is entering the acceleration phase, completing asphalt paving for many sections.

On April 20, recorded at the extended Tran Hung Dao Avenue construction site, the construction atmosphere was urgent throughout the route. Many construction fronts were deployed simultaneously, machinery operated continuously, creating a rapid pace in the sprint phase.

Along the route from the end point of the existing Tran Hung Dao road to the Ngoi Bo stream area, Gia Phu commune, vehicles transporting materials are bustling in and out. The roadbed positions are being compressed, each layer of soil is compacted according to technical standards.

Máy móc thi công tại dự án. Ảnh: Đinh Đại
Machinery accelerates construction at the project. Photo: Dinh Dai

In drainage sections, precast sewer and ditch systems have been completed and are being installed synchronously.

According to Mr. Le Thai Toan - Head of ODA Project Management Department, Lao Cai Provincial Traffic Construction Investment Project Management Board, the investor is closely monitoring the progress and closely coordinating with the contractor to organize scientific construction.

We regularly inspect the site, promptly remove obstacles, especially in terms of site clearance, to ensure progress according to the set plan," Mr. Toan said.

Đoạn đường đã hoàn thành thảm nhựa. Ảnh: Đinh Đại
The road section has completed asphalt paving. Photo: Dinh Dai

Regarding progress, package No. 18 (roadbed construction and drainage system) has completed all precast components, and the roadbed is currently being deployed at about 2.3/2.67km.

The value of the implemented volume reached approximately 85/120.55 billion VND, equivalent to 70%. It is expected that this package will be completed on July 30, 2026, earlier than the contract term at the end of the year.

Site clearance work basically meets construction requirements. To date, 161/164 households have been paid compensation and handed over land, with a total area of about 30.9ha. Some remaining cases are continuing to complete procedures for handover in the near future.

Người dân đi lại thuận tiện trên đoạn đã thảm nhựa. Ảnh: Đinh Đại
People travel conveniently on the asphalted section. Photo: Dinh Dai

Mr. Bui Dai Loi - construction site commander informed that the unit is maintaining personnel and equipment to ensure progress.

Currently, we have paved about 450m of road surface, and about 300m is completing the K98 foundation. It is expected that the remaining foundation will be completed in about 20 days to move to the next construction steps," Mr. Loi said.

Meanwhile, package No. 28 (brick foundation construction, road surface and traffic safety system) is worth 55 billion VND, currently about 9.2 billion VND has been implemented, equivalent to 17% of the volume. The contractor is continuing to increase machinery and personnel to accelerate the progress of the remaining items.

The extended Tran Hung Dao Avenue project has a total length of about 2.5km, with a total investment of more than 170 billion VND.

Khi đi vào hoạt động sẽ thúc đẩy giao thương cho khu vực. Ảnh: Đinh Đại
When put into operation, it will promote trade for the region. Photo: Dinh Dai

This is an important traffic route, contributing to completing urban infrastructure, expanding development space towards Gia Phu commune and increasing connectivity with the main traffic axes of the old Lao Cai city.

At the construction site, each section of the route gradually takes shape, and many items are moved to the completion phase.

When the road is put into operation, it will create motivation for socio-economic development for the locality.

Đinh Đại
RELATED NEWS

Lao Cai removes 146 hectares of land from mineral activity prohibition area

|

Lao Cai - No longer entangled in national defense planning, protection forests, many land areas have been removed from prohibited and temporarily prohibited mineral activities by the province.

Donating land to open roads, bringing highland villages in Lao Cai to transform

|

Lao Cai - People voluntarily donate land to build roads, in return for more spacious infrastructure, helping the highland economy gradually transform.

Lao Cai reviews projects, accelerates disbursement of public investment

|

Lao Cai - The province requests to review projects, stop ineffective works, and accelerate construction, ensuring the effective use of public investment capital in 2026.

Stocks recover thanks to Bluechip but lack liquidity

|

The stock market regained its upward momentum thanks to bluechip stocks showing signs of recovery, but liquidity decreased sharply.

Ministry of Education and Training requests review and identification of violations in the case of high school learning without graduating from secondary school in Quang Tri

|

Quang Tri - Regarding Mr. Vo Danh Thuan's high school education before graduating from secondary school, the Ministry of Education and Training affirmed that according to regulations, he must have a secondary school diploma when entering 10th grade.

7.5 magnitude earthquake off the coast of Japan, tsunami warning up to 3m high

|

A magnitude 7.5 earthquake occurred off the northeastern coast of Japan, leading to a tsunami warning of up to 3m, according to the Japan Meteorological Agency.

Nearly 130,000 students register for the 10th grade entrance exam in Hanoi

|

Nearly 130,000 Hanoi students registered to participate in the 10th grade high school (THPT) entrance exam for the 2026-2027 school year.

Rocky mine landslide at night in Thai Nguyen, burying many machines

|

Thai Nguyen - The landslide caused a large amount of soil and rocks to bury many machines, with no casualties.

Lao Cai removes 146 hectares of land from mineral activity prohibition area

Đinh Đại |

Lao Cai - No longer entangled in national defense planning, protection forests, many land areas have been removed from prohibited and temporarily prohibited mineral activities by the province.

Donating land to open roads, bringing highland villages in Lao Cai to transform

Đinh Đại |

Lao Cai - People voluntarily donate land to build roads, in return for more spacious infrastructure, helping the highland economy gradually transform.

Lao Cai reviews projects, accelerates disbursement of public investment

Đinh Đại |

Lao Cai - The province requests to review projects, stop ineffective works, and accelerate construction, ensuring the effective use of public investment capital in 2026.