Also attending the meeting with Prime Minister Pham Minh Chinh were Deputy Prime Minister Tran Hong Ha, Deputy Prime Minister Ho Duc Phoc and representatives of central ministries and branches.
At the Long Thanh airport project construction site in Long Thanh district, Dong Nai province, Prime Minister Pham Minh Chinh and the Central working delegation inspected the progress of package 6.12 for the construction of two connecting roads to the Long Thanh airport project, the progress of package 5.10 for the construction of the Long Thanh airport passenger terminal, and the progress of package 4.6 for the construction of the Long Thanh airport runway.
Here, Prime Minister Pham Minh Chinh visited, encouraged and presented gifts to officers, engineers and workers working at the Long Thanh airport project site.
According to Vietnam Airports Corporation (ACV), for the main packages being implemented at the construction site, ACV has directed the construction units to speed up the construction progress, the packages organize hundreds of construction teams with nearly 7,000 experts, engineers, workers, laborers and nearly 3,000 construction equipment, the construction site organization method is scientific, professional, orderly, ensuring security and safety during the construction process.
According to ACV, package 5.10, the expected progress is to complete the entire construction before December 2025.
With package 4.6, ACV is determined to direct construction units to complete and technically exploit the runway before April 30, 2025.
Package 6.12 is expected to be completed in December 2025.