Another important bridge branch at the largest intersection in Ho Chi Minh City is about to open to traffic

BẢO TÚ |

Ho Chi Minh City - The N3 overpass branch at An Phu intersection is being urgently constructed in the final stages, ready to open traffic and reduce traffic pressure in the area.

In order to promptly open the N3 overpass branch of the An Phu intersection project to traffic right on the occasion of April 30th, dozens of officials and workers are sticking to the construction site, constructing despite the scorching hot weather.

Recorded at package XL10 (N3 overpass branch), the construction teams were maximized in terms of both manpower and machinery to aim for the project to be inaugurated on the occasion of the 51st anniversary of the Liberation of the South and National Reunification Day (April 30, 1975 - April 30, 2026).

 Toàn cảnh nhịp độ thi công khẩn trương tại nhánh cầu vượt N3 (nút giao An Phú) trước thềm dịp lễ 30.4. Ảnh: Thái Bảo
Overview of the urgent construction pace at the N3 overpass branch (An Phu intersection) before the 30th holiday. 4. Photo: Thai Bao

The contractor representative informed that the progress of branch N3 has now reached 99%. The remaining workload is not much, mainly focusing on detailed completion stages such as installing railings, cleaning and technical inspection of the bridge deck. "Although it is only the final steps, this stage requires absolute caution and meticulousness to ensure both technical quality and aesthetics. Currently, we are maintaining about 60 engineers and workers working in shifts continuously day and night to ensure the project reaches the finish line on schedule," the contractor representative shared.

  Nhánh cầu vượt N3 (gói thầu XL10) hiện đã đạt 99% khối lượng, sẵn sàng phục vụ hướng lưu thông Mai Chí Thọ - Đồng Văn Cống. Ảnh: Thái Bảo
The N3 overpass branch (package XL10) has now reached 99% of the volume, ready to serve traffic for the Mai Chi Tho - Dong Van Cong direction. Photo: Thai Bao

With a length of about 400m and a width of 9m, the N3 bridge branch plays a vital role in directly relieving traffic pressure for vehicles moving from Mai Chi Tho street through Dong Van Cong to enter Cat Lai port cluster.

Công nhân khẩn trương lắp đặt hệ thống lan can an toàn trên nhánh cầu vượt N3 thuộc nút giao An Phú. Ảnh: Thái Bảo
Workers urgently install safety railing systems on the N3 overpass branch belonging to An Phu intersection. Photo: Thai Bao

Along with that, the N4 bridge branch (taking on the reverse traffic direction from Dong Van Cong to Mai Chi Tho) is also being accelerated by the contractor in the approach span section, expected to be completed by the end of June 2026.

 Nhánh cầu vượt N4 ở chiều ngược lại đang được khẩn trương thi công phần nhịp dẫn, dự kiến hoàn thành vào cuối tháng 6.2026. Ảnh: Thái Bảo
The N4 overpass branch in the opposite direction is being urgently constructed for the approach span, expected to be completed by the end of June 2026. Photo: Thai Bao

According to a representative of the Ho Chi Minh City Traffic Construction Investment Project Management Board (the investor), to date, the 3-story An Phu intersection project has completed more than 70% of the total workload. Many key items have been put into operation before, promoting the efficiency of reducing congestion such as: HC1- and HC1- 02 underpasses, N2 overpasses. Satellite projects such as Ba Dat bridge, Giong Ong To bridge have also been basically completed.

 Nhánh cầu N3 khi đi vào hoạt động sẽ đưa dòng xe tải, container lên cao, tránh giao cắt trực tiếp với trục đường Mai Chí Thọ giảm ùn ứ giao thông,.
When the N3 bridge branch comes into operation, it will raise the flow of trucks and containers high, avoiding direct intersection with Mai Chi Tho road, reducing traffic congestion. Photo: Thai Bao

Although contractors are focusing their efforts on accelerating, the project is still facing a major challenge at bridge branch N1. 2 due to the bottleneck of site clearance across Luong Dinh Cua road. According to the plan, this item can be completed in November 2026 if the local government hands over enough 22,000m2 of clean ground to organize construction soon.

Dự án nút giao 3 tầng An Phú đã hoàn thành hơn 70% tổng khối lượng công việc. Ảnh: Thái Bảo
The 3-story An Phu intersection project has completed more than 70% of the total workload. Photo: Thai Bao

Started in 2021 with a total investment of 3,400 billion VND, An Phu intersection is expected to be the "key" to eliminate traffic jam black spots at the eastern gateway of Ho Chi Minh City. When completed and fully put into operation, this large-scale project will not only clear traffic flow into and out of Cat Lai port but also create a seamless connection between the vital traffic axes of the Southern Key Economic Region.

BẢO TÚ
RELATED NEWS

Accelerate the construction of the final intersection on the 34 trillion VND expressway

|

Despite the lack of materials, construction units are still making efforts to accelerate the progress of the Tri Binh - Dung Quat intersection, the last intersection on the Da Nang - Quang Ngai expressway.

Urgently construct Ring Road 3 HCMC and National Highway 13 intersections

|

HCMC - The Ring Road 3 HCMC intersection project with National Highway 13 is being urgently constructed, many items are gradually being completed. Expected to be put into operation in 2026.

Ho Chi Minh City's largest intersection accelerates towards the finish line, Eastern gateway is about to end traffic jams

|

Ho Chi Minh City is accelerating the construction of An Phu intersection worth more than 3,400 billion VND, expected to be basically completed on June 30, 2026, contributing to eliminating traffic jams at the eastern gateway.

Da Nang speaks out about discriminatory information against Indian tourists

|

Da Nang - The city affirmed that no signs of discrimination against Indian tourists have been detected, and at the same time requested verification and correction of inaccurate information.

VTV announces ownership of World Cup 2026 television rights

|

VTV has officially announced the ownership of the FIFA World Cup 2026 copyright in Vietnam.

Senior Lieutenant General Le Duc Thai becomes Secretary of Thanh Hoa Provincial Party Committee

|

Thanh Hoa - Senior Lieutenant General Le Duc Thai, Deputy Minister of National Defense, was transferred by the Politburo to hold the position of Secretary of Thanh Hoa Provincial Party Committee.

Mr. Nguyen Manh Quyen elected Chairman of Hung Yen Provincial People's Committee

|

Hung Yen - The first session of the 18th Hung Yen Provincial People's Council elected the Chairman of the People's Council, the Chairman of the Provincial People's Committee and consolidated the leadership apparatus for the 2026-2031 term.

Ms. Bui Thi Minh Hoai re-elected as Secretary of the Party Committee of the Fatherland Front and Central Agencies

|

Politburo Member, Secretary of the Party Central Committee, Chairman of the Central Committee of the Vietnam Fatherland Front Bui Thi Minh Hoai was re-elected as Secretary of the Party Committee of the Vietnam Fatherland Front and central mass organizations.

Accelerate the construction of the final intersection on the 34 trillion VND expressway

ĐÔNG GIANG |

Despite the lack of materials, construction units are still making efforts to accelerate the progress of the Tri Binh - Dung Quat intersection, the last intersection on the Da Nang - Quang Ngai expressway.

Urgently construct Ring Road 3 HCMC and National Highway 13 intersections

TRỌNG QUỲNH |

HCMC - The Ring Road 3 HCMC intersection project with National Highway 13 is being urgently constructed, many items are gradually being completed. Expected to be put into operation in 2026.

Ho Chi Minh City's largest intersection accelerates towards the finish line, Eastern gateway is about to end traffic jams

MINH QUÂN |

Ho Chi Minh City is accelerating the construction of An Phu intersection worth more than 3,400 billion VND, expected to be basically completed on June 30, 2026, contributing to eliminating traffic jams at the eastern gateway.