Construction through the night to upgrade Ke Go lake after prolonged floods

TRẦN TUẤN |

Ha Tinh - After a long period of flooding, the weather is now favorable, contractors are focusing on overtime, increasing shifts, speeding up the construction of upgrading and repairing Ke Go lake.

On November 30, a reporter from Lao Dong Newspaper was present at the construction site for upgrading and repairing Ke Go lake in Cam Due commune, recording that contractors are mobilizing maximum human resources and machinery to focus on the construction of new floodgates, completing the bridge railing, and upgrading the main dam.

May moc, nhan cong dang thi cong tran xa lu ho Ke Go. Anh: Tran Tuan.
Machinery and workers are constructing the spillway of Ke Go Lake. Photo: Tran Tuan.
Nhung cong nhan dang gat phan dat sat lo taluy cua tran xa lu. Anh: Tran Tuan.
Workers are clearing the landslide area of the positive slope of the spillway. Photo: Tran Tuan.

The project to upgrade and repair Ke Go lake with a total investment of more than 350 billion VND is constructed by a joint venture of 47 Joint Stock Company - Lilama 10 Joint Stock Company - 465 Construction Joint Stock Company.

The main items of the project include: repairing and upgrading the main dam; building a new floodgates; building a new operator house; upgrading the mechanical system at Doc Mieu spillway and surrounding dykes.

Mr. Nguyen Minh Hieu - an officer of the Irrigation Investment and Construction Management Board 1 - said that the Ke Go Lake upgrade and repair project started on December 27, 2024, and is scheduled to be completed in June 2026.

However, due to heavy rain in the past, the construction of contractors encountered difficulties, affecting the workload.

"The weather has been sunny and favorable these past few days, so contractors have focused on 3 shifts and 4 teams, speeding up the progress to compensate for the volume, determined to ensure the progress of the project," Mr. Hieu shared.

Currently, there are nearly 100 workers on the construction site every day along with 4 cranes, 8 trucks, 5 excavators, 2 bulldozers, and 2 mangrove machines.

Cong nhan thi cong phan lan can cau bac qua tran xa lu. Anh: Tran Tuan.
Workers constructing the railing of the bridge over the flood discharge. Photo: Tran Tuan.

Up to this point, the project has basically completed the construction of the new flood overflow overpass. The mechanical items on the Doc Mieu spillway have been completed; the mechanical part of the drainage culvert has also been completed.

According to Mr. Hieu, on the night of November 29, the contractor organized the construction until 2:00 a.m. the next morning and poured the first 260m3 of concrete in the upstream left wing foundation of the new flood spillway.

Hien nay thoi tiet thuan loi, nha thau tap trung thi cong ca vao ban dem de day nhanh tien do. Anh: Minh Hieu.
Currently, the weather is favorable, the contractor focuses on construction even at night to speed up the progress. Photo: Minh Hieu.

Currently, the highest concentration is on the concrete pouring and completion of the foundation hole of the flood discharge spillway.

Mr. Hieu also shared that the current concern is that the project is still stuck with 2 electric poles that have not been relocated.

The investor's representative worked with the People's Committee of Cam Due commune, requesting the urgent relocation of these two electric poles to ensure construction, but the relocation time is still unclear.

Du an dang vuong 2 cot dien chua di doi. Anh: Tran Tuan.
The project is stuck with 2 electric poles that have not been relocated. Photo: Tran Tuan.

Ke Go reservoir was built in 1976, with a capacity of 345 million m3, the most important irrigation project in Ha Tinh. Ke Go Lake not only serves the irrigation of tens of thousands of hectares of agricultural land but also has the task of cutting and reducing floods for downstream areas, providing domestic water and maintaining the ecological environment.

TRẦN TUẤN
RELATED NEWS

Construction of technical infrastructure for AEON My Tho Commercial Center, 2 hectares wide in Dong Thap

|

Dong Thap - AEON My Tho Shopping Center promises to become a bustling business location, contributing to creating a civilized living space.

Accelerating the progress of the 500 billion VND road project that has not been completed after 13 years of construction in Lao Cai

|

Lao Cai - The National Highway 32C upgrade project, the section from Hien Luong - Yen Bai City (old) is being accelerated to open the route before December 31, 2025.

Hung Yen speeds up construction of axis routes connecting economic zones

|

Hung Yen - Construction Investment Project Management Board No. 2 is accelerating construction and accelerating disbursement of key projects in 2025.

From morning to night, Hanoi is immersed in heavy pollution, AQI sometimes ranks 2nd in the world

|

The IQ Air application shows that Hanoi suffered from severe air pollution on November 30.

Public service vehicles continue to appear at the old headquarters of Market Management Team No. 4, Lang Son

|

Lang Son - Public vehicles continue to appear at the old headquarters of Market Management Team No. 4 (Huu Lung commune).

Live football U17 Vietnam vs U17 Malaysia in the U17 Asian qualifiers

|

Live football U17 Vietnam and U17 Malaysia in the U17 Asian qualifiers, taking place at 19:00 today (November 30).

The silent wave of anger after the apartment fire in Hong Kong (China)

|

More than 128 people have died, 150 people are missing and Hong Kong (China) is covered in pain after the catastrophic apartment fire.

Penalties for if the wife forces her husband to work too hard

|

How is a wife punished for forcing her husband to work too much? Lawyer Nguyen Van Hau will answer this question.

Construction of technical infrastructure for AEON My Tho Commercial Center, 2 hectares wide in Dong Thap

Hàn Lâm |

Dong Thap - AEON My Tho Shopping Center promises to become a bustling business location, contributing to creating a civilized living space.

Accelerating the progress of the 500 billion VND road project that has not been completed after 13 years of construction in Lao Cai

Văn Đức |

Lao Cai - The National Highway 32C upgrade project, the section from Hien Luong - Yen Bai City (old) is being accelerated to open the route before December 31, 2025.

Hung Yen speeds up construction of axis routes connecting economic zones

Mai Hương |

Hung Yen - Construction Investment Project Management Board No. 2 is accelerating construction and accelerating disbursement of key projects in 2025.