Many construction sites are bustling again after floods

TRẦN TUẤN |

Ha Tinh - After a period of rain lasting more than a month, the warm sun is returning, so many construction sites and projects in Ha Tinh have been enthusiastically constructing to speed up the progress.

On November 25, present at the VSIP Ha Tinh Industrial Park project, a reporter from Lao Dong Newspaper recorded that contractors are focusing on machinery and workers to construct filling items, asphalt pavement, and drainage culverts.

According to the contractor's representative, the prolonged rain has affected the construction of the unit, with low volumes. Now the weather is warm and sunny, the unit is focusing on maximum human resources, vehicles, and construction machinery to compensate for the volume to ensure the set progress.

According to Vietnam Singapore Urban and Industrial Park Development Joint Stock Company, to date, the VSIP Ha Tinh Industrial Park project has completed about 20% of the leveling volume with 26 hectares; completed 15.62% of the sewer and ditch system; excavated and sealed the ground to 190 hectares...

In June 2024, the VSIP Ha Tinh Industrial Park Project was started (phase 1) with a scale of 190.41 hectares, with a total investment of more than 1,555 billion VND.

Du an Khu Cong nghiep VSIP Ha Tinh giai doan 1 co quy mo 190 ha. Anh: Tran Tuan.
The VSIP Ha Tinh Industrial Park Project Phase 1 has a scale of 190 hectares. Photo: Tran Tuan.

VSIP Ha Tinh is expected to attract domestic and foreign investors in fields such as: Electricity and electronics, semiconductors, precision mechanics, energy, electric vehicle batteries, metals, auto parts, food processing, logistics services, factories for rent...

The project is also expected to create more than 30,000 jobs, creating momentum for the development and economic restructuring of Ha Tinh province.

At the Nam Cau Phu Urban, Commercial and Service Area and Ecological Villa project in Cam Binh commune, the contractor is also focusing on pouring land for leveling. Many trucks continuously poured soil along with leveling sanders to create a flat surface.

This project is invested by T&T Group, and has started construction on October 10, 2025.

The urban area, commercial services, and ecological villas of Nam Cau Phu have an area of nearly 50 hectares, with diverse products, including: commercial shophouses, townhouses, riverside villas, commercial centers - entertainment services - hotels and social housing.

The investor said that the urban area will be arranged with nearly 17,000 m2 of green trees and water surface, creating a cool, comfortable, experiential and sustainable green living space for residents.

Nha thau tap trung san lap mat bang tai Du an Khu do thi, thuong mai dich vu, biet thu sinh thai Nam Cau Phu. Anh: Tran Tuan.
Contractors focus on leveling the ground at the Nam Cau Phu Urban Area, Trade and Service Project, and Ecological villa. Photo: Tran Tuan.
Tranh thu thoi tiet nang am, tren nhieu cong truong o Ha Tinh da soi dong thi cong day nhanh tien do. Anh: Tran Tuan.
Taking advantage of the warm and sunny weather, many construction sites in Ha Tinh have been bustling with construction to speed up progress. Photo: Tran Tuan.

At the Ngo Quyen Street Expansion, Upgrade and Renovation Project (from National Highway 1 to Quang Trung Street) after many days of no machinery or workers due to rain.

Currently, contractors are also focusing on resuming construction by continuing to install drainage systems, build culverts...

This is a project invested by the Ha Tinh Traffic Construction and Urban Development Investment Project Management Board with a capital of 140 billion VND.

The consortium of 471 Joint Stock Company, Dai Hiep Company Limited, and Vinh Phu Construction Company Limited is in charge of the construction. The subcontractors include: Hoang Anh Joint Stock Company, Tan Hai Son Construction Joint Stock Company; the supervising unit is the Tecco 6 - PMC consortium (Consulting Joint Stock Company).

The project started on March 28, 2025, and is scheduled to be completed on December 28, 2025.

Mr. Nguyen Danh Phong - Deputy Director of the Ha Tinh Traffic Construction and Urban Development Investment Project Management Board - said that the project to expand, upgrade, and renovate Ngo Quyen Street from National Highway 1A to Quang Trung Street is due to weather disadvantages, so the progress is slow. The project has been extended to October 2026.

TRẦN TUẤN
RELATED NEWS

Accelerate the construction of Ring Road 3 through Tay Ninh to be technically open to traffic on December 19

|

Tay Ninh - Deputy Prime Minister Mai Van Chinh directly inspected the construction progress of the Ho Chi Minh City Ring Road 3 project through Tay Ninh province.

Hanoi Ring Road 2.5 enters the final stage, contractors mobilize maximum human resources for construction

|

Hanoi - The contractor has completed the C15 asphalt paving item at the beginning of the route of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, with a total capital of more than 1,300 billion VND.

Throughout the night of constructing a billion-dollar road in Hanoi, the finishing time is very close

|

Hanoi - The contractor mobilized many machines and workers overnight to construct the Ring Road 2.5 project, ensuring the quality and progress set out.

Prime Minister Pham Minh Chinh: Solidarity, one heart towards the Central region

|

On the evening of November 24, at the Vietnam Ethnic Culture - Tourism Village (Dong Mo, Hanoi), the opening program of the Great Unity Week of Ethnic Groups - Vietnam Cultural Heritage in 2025 took place with the theme "Solidarity of One Heart - Towards the Central region". Prime Minister Pham Minh Chinh attended the program.

The revised Press Law is expected to create a clear legal framework

|

The amendment of the Press Law and the Intellectual Property Law is expected to create a clearer legal corridor, helping press agencies protect content and develop sustainably.

Urgently pay insurance to people and businesses affected by floods

|

The Prime Minister requested urgent resolution of policies and insurance payments for people and businesses affected by floods.

Banning gasoline motorbikes in Ring Road 1: "We will support people to convert to the highest possible level"

|

Regarding the policy of banning gasoline motorbikes in Ring Road 1, a representative of the Department of Environmental Management said that they will support people to the highest possible level.

WHO recommends Vietnam to absolutely ban e-cigarette and heated tobacco trading

|

WHO representative recommended that Vietnam include the trading of e-cigarettes and heated tobacco products in the list of prohibited industries of the amended Investment Law.

Accelerate the construction of Ring Road 3 through Tay Ninh to be technically open to traffic on December 19

Thanh Vũ |

Tay Ninh - Deputy Prime Minister Mai Van Chinh directly inspected the construction progress of the Ho Chi Minh City Ring Road 3 project through Tay Ninh province.

Hanoi Ring Road 2.5 enters the final stage, contractors mobilize maximum human resources for construction

SÓNG HỮU |

Hanoi - The contractor has completed the C15 asphalt paving item at the beginning of the route of the Ring Road 2.5 project, Dam Hong - National Highway 1A section, with a total capital of more than 1,300 billion VND.

Throughout the night of constructing a billion-dollar road in Hanoi, the finishing time is very close

SÓNG HỮU |

Hanoi - The contractor mobilized many machines and workers overnight to construct the Ring Road 2.5 project, ensuring the quality and progress set out.