Construction through ceremony to make up for the slow progress of the expressway project through Dong Nai

HÀ ANH CHIẾN |

Dong Nai - Bien Hoa - Vung Tau Expressway and Ho Chi Minh City Ring Road 3 are under construction during the Hung Vuong Commemoration Ceremony to make up for the delay in progress of these two previous projects.

Construction offset the progress of Bien Hoa - Vung Tau Expressway

In Dong Nai, the Bien Hoa - Vung Tau expressway project is behind schedule, the locality is required to urgently complete the embankment before June 30 and the entire project before December 31, 2025. Therefore, the construction of this project is also being " sprayed" by Dong Nai, organizing construction through the ceremony.

Speaking to Lao Dong newspaper reporters, Mr. Nguyen Linh - Deputy Director of the Dong Nai Province Traffic Construction Investment Project Management Board - said: In 2 national key projects invested by the unit, including Component Project 1 - Bien Hoa - Vung Tau Expressway and Component Project 3 - Ho Chi Minh City Ring Road 3, contractors maintained construction throughout the 3 days of the Hung Kings' Commemoration Day holiday in 2025 with the goal of speeding up progress, compensating for the previously delayed progress of these 2 projects.

Cac du an giao thong trong diem o Dong Nai thi cong xuyen le Gio to Hung Vuong nam 2025. Anh: HAC
Key transport projects in Dong Nai will be constructed during the Hung Vuong Commemoration Ceremony in 2025. Photo: HAC

Component project 1 - Bien Hoa - Vung Tau Expressway has 2 main construction packages. Contractors are deploying 34 construction teams, with about 250 motorbikes and equipment, 100 engineers and more than 400 workers participating in the construction site.

Meanwhile, Component Project 3 - Ho Chi Minh City Ring Road 3 has 3 main construction packages. In this project, contractors are arranging about 23 construction teams with more than 160 locomotives and equipment of all kinds mobilized to the construction site to serve the construction.

Mr. Nguyen Dinh Kien - a worker working at package 18 of the Bien Hoa - Vung Tau expressway, from Nghe An province - shared that to ensure the project progress is very urgent, he tries to strive for the tasks assigned by superiors.

Many projects to open to traffic, technical traffic opening on April 30

At the Component 1A project of Ho Chi Minh City Ring Road 3, the Nhon Trach bridge project across Dong Nai River, connecting Thu Duc City (HCMC) with Nhon Trach District (Dong Nai Province) is also planned to be technically opened to traffic before the April 30 holiday. Therefore, the investor and contractor also mobilized construction forces throughout the Hung Vuong Ancestor's death anniversary to race for progress, completing the bridge deck to soon open the technical traffic.

Component project 1A of Ho Chi Minh City Ring Road 3 has a total length of 8.22 km, passes through Dong Nai 6.3 km and passes through Ho Chi Minh City 1.92 km. Of which, Nhon Trach Bridge is 2.6 km long, the scale of phase 1 includes 4 lanes for motor vehicles and 2 lanes for mixed vehicles. This is a key project, playing a role in connecting the region, shortening travel time from Ho Chi Minh City to Dong Nai and neighboring localities.

When the entire component project 1A of Ho Chi Minh City Ring Road 3 is put into operation, it will connect with component project 3 of Ho Chi Minh City Ring Road 3 (Dong Nai province section), leading to Ben Luc - Long Thanh Expressway, divided into the Ho Chi Minh City - Long Thanh - Dau Giay Expressway and National Highway 51.

Thi cong goi thau 5.10 nha ga hanh khach san bay Long Thanh. Anh: HAC
Construction of package 5.10 of Long Thanh airport passenger terminal. Photo: HAC

In addition to the projects of Ring Road and Expressway, at the ceremony, at Long Thanh Airport Project (Dong Nai), the main bidding packages were also constructed through the ceremony. Vietnam Airport Corporation (ACV) - Investor of component project 3 of Long Thanh Airport - said, on the construction site, construction units have mobilized hundreds of construction stitches with nearly 10,000 experts, engineers, workers, workers and nearly 3,000 construction equipment to accelerate construction progress.

In particular, package 5 - construction of Long Thanh airport passenger terminal, has more than 5,000 experts, engineers, workers and laborers being mobilized for urgent construction throughout the holiday. Similarly, package 4.6 - construction of the Long Thanh airport runway is also under construction through the ceremony in time for the technical exploitation of the runway and taxiway before April 30.

HÀ ANH CHIẾN
TIN LIÊN QUAN

Garment company in Dong Nai rewards 2,300 workers for Hung Vuong's Commemoration Day holiday

|

Dong Nai - Dong Phu Cuong Joint Stock Company's Trade Union awarded 2,300 workers on the occasion of Hung Vuong's Commemoration Day with a total amount of 440.5 million VND.

About to open 33km of expressway connecting Long An - Ho Chi Minh City - Dong Nai

|

HCMC - On the occasion of April 30, an additional 33km of the Ben Luc - Long Thanh expressway was put into operation, helping to increase connectivity between HCMC, Long An, Dong Nai, and shorten travel time.

The road project connecting Dong Nai with the expressway to Ho Chi Minh City is stuck in land clearance

|

Dong Nai - The Huong Lo 2 - Section 1 project, nearly 2km long, to connect the Ho Chi Minh City - Long Thanh - Dau Giay expressway, is stuck with 250m of site clearance.

Vietnam Airlines plane has just had to make emergency landing in India to rescue passengers

|

Informing Lao Dong Newspaper on the evening of July 7, a representative of Vietnam Airlines said that the airline had just had to make an emergency landing in India to rescue passengers.

Plan to help people save costs when metro tickets increase from 1.8

|

Hanoi - Tickets for the two metro lines will increase from August 1, 2025, the highest at 40%.

Dragon fruit garden owner in Lam Dong hires technology bodyguards to steal

|

Lam Dong - Many dragon fruit gardens have hired a 24/7 garden surveillance camera service to promptly prevent theft of electric wires and light bulbs.

Motorbikes still overflow into the car lane on Pham Van Dong Street, traffic police on duty to remind

|

Hanoi - The situation of motorbikes entering the lane reserved for cars on Pham Van Dong Street is still happening.

President granted amnesty to those sentenced to prison and life imprisonment on the occasion of National Day, September 2

|

A person sentenced to life in prison who has been reduced to prison for a period of 18 consecutive quarters of good or more can be considered and granted amnesty.

Garment company in Dong Nai rewards 2,300 workers for Hung Vuong's Commemoration Day holiday

HÀ ANH CHIẾN |

Dong Nai - Dong Phu Cuong Joint Stock Company's Trade Union awarded 2,300 workers on the occasion of Hung Vuong's Commemoration Day with a total amount of 440.5 million VND.

About to open 33km of expressway connecting Long An - Ho Chi Minh City - Dong Nai

MINH QUÂN |

HCMC - On the occasion of April 30, an additional 33km of the Ben Luc - Long Thanh expressway was put into operation, helping to increase connectivity between HCMC, Long An, Dong Nai, and shorten travel time.

The road project connecting Dong Nai with the expressway to Ho Chi Minh City is stuck in land clearance

HÀ ANH CHIẾN |

Dong Nai - The Huong Lo 2 - Section 1 project, nearly 2km long, to connect the Ho Chi Minh City - Long Thanh - Dau Giay expressway, is stuck with 250m of site clearance.