Agree to close Lien Khuong airport from March 4 for repair

Phúc Khánh |

Lam Dong - Local authorities and relevant agencies have agreed to close Lien Khuong airport from March 4, 2026 for repairs.

On January 9th, leaders of Lam Dong province had a working session with Vietnam Airports Corporation (ACV) on the implementation of the project to repair runways at Lien Khuong International Airport.

Dong chi Nguyen Hong Hai, Pho Chu tich UBND tinh Lam Dong yeu cau don vi thi cong day nhanh tien do thuc hien du an, phan dau hoan thanh trong giua thang 8.2026. Anh: Hoang Sa
Mr. Nguyen Hong Hai, Vice Chairman of Lam Dong Provincial People's Committee, requested the construction unit to accelerate the project implementation progress, striving to complete it in mid-August 2026. Photo: Hoang Sa

At the working session, representatives of agencies and units reported and presented plans to organize the project construction. Accordingly, the parties agreed on the closing time of Lien Khuong International Airport from March 4 to serve construction.

Representatives of the contractor said that in the process of project implementation, the unit hopes to continue to receive the attention and close direction of local authorities and timely coordination of relevant departments and branches to remove difficulties and obstacles arising, ensuring progress according to the investor's plan.

Dai dien lanh dao Tong Cong ty Hang khong Viet Nam phat bieu tai buoi lam viec. Anh: Than Hy
Representatives of the leaders of Vietnam Airlines Corporation speak at the working session. Photo: Than Hy

The contractor is committed to strictly implementing technical measures, fully complying with the requirements of the investor, ensuring the quality of the project and completing it on schedule.

Speaking at the conclusion of the working session, Mr. Nguyen Hong Hai, Vice Chairman of Lam Dong Provincial People's Committee emphasized the importance of the project for transport infrastructure, socio-economic development and tourism of the locality; and at the same time requested the contractor to maximize resources, accelerate progress, and ensure project quality in accordance with technical standards.

Dai dien don vi nha thau thi cong trinh bay phuong an thuc hien du an. Anh: Hoang Sa
Representatives of the construction contractor unit present the project implementation plan. Photo: Hoang Sa

Vice Chairman of Lam Dong Provincial People's Committee assigned relevant departments and agencies to closely coordinate with investors and contractors, promptly resolve procedures and arising problems; ensure material gathering, proactively source supply from sand, stone, and terraced land mines and sites to serve construction.

In addition, units need to pay special attention to labor safety, develop reasonable traffic regulation plans in the construction area, and ensure safety for people and vehicles.

According to the plan, Lien Khuong airport will stop operating for 6 months, from March 4 to August 25, 2026, to upgrade runways, rolling stock and technical infrastructure systems.

Phúc Khánh
RELATED NEWS

Lien Khuong airport in Lam Dong is expected to be closed for 6 months to repair

|

Lam Dong - The leaders of the Provincial People's Committee requested the investor to speed up the repair of Lien Khuong airport and reopen it before the National Day holiday on September 2, 2026.

Delaying the closure of Lien Khuong airport in Lam Dong for repairs and upgrades

|

Lam Dong proposed to postpone the closure of Lien Khuong airport to 2026 to reduce the impact on the local economy and society.

Rare cold weather in Ho Chi Minh City, young people are excited

|

On the evening of January 9, the temperature in Ho Chi Minh City continued to drop deeply, making many people clearly feel the rare cold.

Reasons why fraud boss Chen Zhi was extradited by Cambodia to China

|

Chen Zhi, who is accused of operating online fraud activities from Cambodia, has been extradited to China.

Live football U23 Vietnam vs U23 Kyrgyzstan at the AFC U23 Championship

|

Live broadcast of the match between U23 Vietnam and U23 Kyrgyzstan at the 2026 AFC U23 Championship, taking place at 9:00 PM today (January 9).

Trade union activities need to be upgraded and more effective in 2026

|

Ho Chi Minh City - The streamlined trade union organization model requires management, administration and operational efficiency to be raised to a new level in 2026.

Merging two central hospitals into Hanoi Medical University

|

Central Hospital 71 and the Central Nursing and Rehabilitation Hospital will merge into Hanoi Medical University, according to the policy of the Ministry of Health.

Mr. Truong Quoc Huy talks about the reason for resigning from the position of Secretary of Phu Tho Provincial Party Committee

|

Mr. Truong Quoc Huy stopped participating in the Executive Committee, the Standing Committee and stopped holding the position of Secretary of Phu Tho Provincial Party Committee, and was given a leave of absence according to his personal wishes.

Lien Khuong airport in Lam Dong is expected to be closed for 6 months to repair

Phúc Khánh |

Lam Dong - The leaders of the Provincial People's Committee requested the investor to speed up the repair of Lien Khuong airport and reopen it before the National Day holiday on September 2, 2026.

Xử lý 4 trường hợp ở Lâm Đồng đăng tải thông tin sai sự thật tại sân bay Liên Khương

Phúc Khánh |

Lâm Đồng - Cơ quan điều tra Công an tỉnh đã triệu tập, xử lý 4 trường hợp đăng tải thông tin sai sự thật tại sân bay Liên Khương.

Delaying the closure of Lien Khuong airport in Lam Dong for repairs and upgrades

Duy Tuấn |

Lam Dong proposed to postpone the closure of Lien Khuong airport to 2026 to reduce the impact on the local economy and society.