Opening a bridge worth over VND741 billion to traffic, eliminating congestion in the East of Ho Chi Minh City

TÚ QUỲNH |

HCMC - After 8 years of construction, Tang Long Bridge (Thu Duc City) has officially opened to traffic to "rescue" traffic congestion on La Xuan Oai Street.

On the morning of February 28, the Tang Long bridge project, spanning Trau Trau canal on La Xuan Oai street, Truong Thanh ward, Thu Duc city, officially opened one branch of the bridge after many years of waiting by the people.

Nguoi dan vui mung di tren cay cau moi. Anh: Tu Quynh
People happily walk on the new bridge. Photo: Nhu Quynh

Ms. Nguyen Thi Quy (residing in Thu Duc City) shared that seeing people struggling to move on the old bridge for many years, she was happy that people now have the opportunity to walk on the new bridge.

"Every day, this road is often congested, people struggle to travel on old, small, narrow bridges, and sometimes the old bridges lose their iron plates, which is extremely dangerous," said Ms. Quy.

Mr. Bui Van Nghia (residing in Thu Duc City) said that this morning he took the opportunity to go around the new bridge twice.

"Since a few days ago, when our people heard about the bridge being prepared to open to traffic, everyone was happy and hoped that this bridge would help people move more conveniently," said Mr. Nghia.

1 nhanh cau Tang Long moi thong xe, thay the cho cau cu da xuong cap, nho, hep. Anh: Tu Quynh
1 new branch of Tang Long Bridge will be opened to traffic, replacing the old, degraded, small, and narrow bridge. Photo: Anh Tu

The Tang Long bridge project across Trau Trau canal is 231m long, including 2 branches, each branch is 11m wide for 2 lanes and sidewalks. The two ends of the bridge are access roads with a total length of 559m, along with lighting, trees, and drainage systems.

The project started construction at the end of 2017, and in September 2019, when it reached more than 30% of the volume, the project had to be temporarily suspended due to land clearance problems.

The project has a total investment of 741.1 billion VND, of which the construction cost is 688 billion VND, the compensation and site clearance cost is 53.1 billion VND.

aaa
The Tang Long Bridge section is 231 m long, including 2 branches, each branch is 11 m wide for 2 lanes and sidewalks. Photo: Photo: Nhu Quynh
Phan duong gom dan sinh phia 2 ben cau dang dan hoan thien cac hang muc cuoi cung. Anh: Tu Quynh
The residential access road on the side of the bridge is gradually completing the final items. Photo: Nhu Quynh

The representative of the Investor - Ho Chi Minh City Traffic Construction Investment Project Management Board (Traffic Board) said that a branch of the newly opened Tang Long bridge project will contribute to reducing the load on the existing La Xuan Oai road, the old Tang Long bridge that has been overloaded for many years.

After the opening, the units will continue to complete the remaining bridge branches and other items according to the plan by the end of 2025.

Nguoi dan ki vong cau Tang Long se gop phan giam un tac khu Dong TPHCM. Anh: Anh Tu
People expect Tang Long Bridge to contribute to reducing traffic congestion in the East of Ho Chi Minh City. Photo: Anh Tu

When completed, Tang Long Bridge will increase the connection of La Xuan Oai Street, an axis route through Tang Nhon Phu A, Long Truong, Truong Thanh wards (Thu Duc city), serving traffic between neighboring urban areas, contributing to economic development and urban embellishment, while helping to reduce congestion in the eastern area of Ho Chi Minh City.

TÚ QUỲNH
TIN LIÊN QUAN

The perennial traffic jam road in Ho Chi Minh City is about to be expanded to 60 m, 10 lanes

|

HCMC - National Highway 13 is a vital route, with a high density of vehicles, and frequent traffic jams. The upcoming route will be expanded to 60 m, 10 lanes.

Tang Long Bridge in Ho Chi Minh City is about to open after many years of "covering the mat"

|

Ho Chi Minh City - Immediately after the Lunar New Year, Tang Long Bridge Project has conducted construction again, speeding up the progress to clear the car at the end of February.

Vital bridge clears traffic congestion in southern HCMC before opening day

|

HCMC - The Phuoc Long bridge project connecting District 7 and Nha Be district, after 4 years of construction, has now completed nearly 100% of the work volume, preparing to open to traffic on December 30.

Appointment of Director of the National Aviation Security Center

|

The Ministry of Public Security announced the Decision to establish and launch the National Aviation Security Center; Decision to appoint Colonel Pham Hoang Diep as Director of the Center.

The Vietnam General Confederation of Labor deploys key tasks of propaganda and women's work

|

On the afternoon of February 28, the Vietnam General Confederation of Labor held a conference to deploy tasks of propaganda work and women's union work in 2025.

The Ministry of Finance has 9 Deputy Ministers and 35 units after the merger

|

According to Decree No. 29/2025/ND-CP, the Ministry of Finance has 35 units and 9 Deputy Ministers after merging with the Ministry of Planning and Investment.

Close-up of cracks and subsidence at the site of the metro tunnel excavation incident

|

Cracks and subsidence appeared at many locations in Lane 7 Giang Van Minh (Hanoi) after the Nhon - Hanoi Railway Station metro tunnel excavation incident.

The truth behind US mineral ambitions

|

Controlling rare mineral resources has become a focus of US foreign policy, especially under President Donald Trump.

The perennial traffic jam road in Ho Chi Minh City is about to be expanded to 60 m, 10 lanes

TÚ QUỲNH |

HCMC - National Highway 13 is a vital route, with a high density of vehicles, and frequent traffic jams. The upcoming route will be expanded to 60 m, 10 lanes.

Tang Long Bridge in Ho Chi Minh City is about to open after many years of "covering the mat"

Tâm Tú |

Ho Chi Minh City - Immediately after the Lunar New Year, Tang Long Bridge Project has conducted construction again, speeding up the progress to clear the car at the end of February.

Vital bridge clears traffic congestion in southern HCMC before opening day

NHƯ QUỲNH - ANH TÚ |

HCMC - The Phuoc Long bridge project connecting District 7 and Nha Be district, after 4 years of construction, has now completed nearly 100% of the work volume, preparing to open to traffic on December 30.