The billion-dollar hydropower plant has been unfinished for more than 10 years and is at risk of continuing to miss deadlines

Việt Bắc |

Tuyen Quang - After more than 10 years of unfinished operation, the Yen Son Hydropower Project, despite many adjustments and prolonged implementation time, still risks not reaching the finish line on time.

The Yen Son Hydropower Project was granted an initial Investment Certificate by the People's Committee of Tuyen Quang province on September 25, 2011, the project started construction at the end of December 2013, with an initial design capacity of 70 MW, including 2 generators, with a total investment of more than VND 2,600 billion.

The investor is Binh Minh Construction and Tourism Group Joint Stock Company. The project is expected to be completed and both generators will be connected to electricity by the end of 2016. However, the project has not been completed on time and has been unfinished for more than 10 years.

From 2011 to 2024, this project has been adjusted and extended 4 times, but the investor still cannot complete it.

At the beginning of April 2025, after more than 1 year of restart, some new items of the Yen Son Hydropower project have been built. In the area where the machines and dam shoulders are installed, there are construction activities.

Mot so hang muc nha may Thuy dien Yen Son dang duoc xay dung, tuy nhien tien do kha i ach. Anh: Viet Bac.
Some items of Yen Son Hydropower Plant are under construction, but the progress is quite sluggish. Photo: Viet Bac.

However, compared to the scale of a hydropower project of nearly 4,000 billion VND and the completion time in 2025, the construction seems to be taking place very slowly, making it difficult to keep up with the special progress when there are only a few months left until the flood season.

Speaking to reporters, a representative of the Department of Industry and Trade of Tuyen Quang province said that recently, a working group of the province came to inspect the progress of the Yen Son Hydropower project. Construction activities are still taking place.

"It is almost impossible to complete and put the project into operation in 2025. With the current progress, as quickly as possible, the project can be completed by the second quarter of 2026," said a representative of the Department of Industry and Trade of Tuyen Quang province.

Chu dau tu da tu y thi cong 3 to may truoc nhieu nam khi duoc UBND tinh Tuyen Quang dieu chinh chu truong dau tu, dieu chinh thiet ke. Anh: Viet Bac.
The investor arbitrarily constructed 3 blocks many years in advance when the People's Committee of Tuyen Quang province adjusted the investment policy and the design (photo taken in January 2024). Photo: Viet Bac.

Previously, in 2022, the Yen Son Hydropower Plant Project was a case of behind schedule according to the inspection results of the People's Committee of Tuyen Quang province for non-budgetary investment projects with slow progress or not implemented in the area.

As to save this billion-dollar hydropower fate, in February 2024, the People's Committee of Tuyen Quang province decided to adjust the investment policy for the project. The total investment capital of Yen Son Hydropower Plant was increased to VND3,918 billion, increasing the capacity to 90MW. The construction and completion progress of the project is extended to 2025.

Việt Bắc
TIN LIÊN QUAN

Hundreds of bridges relieve worries about the flood season in Tuyen Quang

|

Tuyen Quang - The bridges for people not only change the appearance of new rural areas but also help eliminate traffic disruption every time the rainy season comes.

Big fire at night in Ba Vi National Park

|

Hanoi - A large fire suddenly broke out in the Chang Re mountain area - Ba Vi National Park.

Binh Thuan celebrates 50 years of construction, innovation and development

|

Binh Thuan - On the evening of April 19, in Phan Thiet city, Binh Thuan province held a ceremony to celebrate the 50th anniversary of the Liberation of the province.

For the first time, Con Dao has a sea turtle conservation tour worth more than 20 million VND

|

Ba Ria - Vung Tau - Tourists will experience eating, staying and doing work related to sea turtle rescue with the forest rangers in Con Dao.

Nghe An has 3,530 surplus cadres after administrative unit arrangement

|

Nghe An - The whole province will have a surplus of about 3,530 cadres and civil servants after the arrangement of commune-level administrative units.

Reasons for choosing Bac Giang City as the administrative center of Bac Ninh province after the merger

|

Bac Ninh - The project to reorganize Bac Ninh and Bac Giang provinces clearly states the reasons for choosing Bac Giang city as the administrative center after the merger.

List of 65 expected commune-level administrative units in Thai Binh after the reorganization

|

Thai Binh - According to the draft project, after the arrangement, the whole Thai Binh province will now decrease from 242 to 65 commune-level administrative units.

Dong Anh District requires officials not to go sightseeing or relaxation when reorganizing the apparatus

|

Hanoi - Dong Anh District People's Committee requires cadres, civil servants, and public employees not to go sightseeing or vacations until the restructuring of the apparatus is completed.

Hundreds of bridges relieve worries about the flood season in Tuyen Quang

Việt Bắc |

Tuyen Quang - The bridges for people not only change the appearance of new rural areas but also help eliminate traffic disruption every time the rainy season comes.

Chủ đầu tư thủy điện nghìn tỉ muốn chuyển nhượng dự án sau 10 năm đắp chiếu

Nguyễn Tùng |

Tuyên Quang - Sau hơn 10 năm không thể hoàn thành công trình Thủy điện Yên Sơn dù nhiều lần được gia hạn, điều chỉnh tiến độ, chủ đầu tư sốt sắng muốn chuyển nhượng lại dự án.

Cận cảnh thủy điện nghìn tỉ tái khởi động sau nhiều năm đắp chiếu

Nguyễn Tùng |

Sau 10 năm thi công dang dở và rơi vào tình trạng đắp chiếu, dự án Thuỷ điện Yên Sơn với tổng mức đầu tư hơn 2.600 tỉ đồng đã bắt đầu được tái khởi động trở lại mang theo những kỳ vọng của tỉnh miền núi Tuyên Quang.