How is the progress of the 1,500-bed hospital project after 10 years?

ĐÌNH TRỌNG |

The 1,500-bed General Hospital project in Binh Duong (initial investment capital of 2,300 billion VND) was built in 2014 and is still not completed.

According to the Binh Duong Provincial Construction Investment Project Management Board, the 1,500-bed General Hospital project, package 1, is the construction, supply and installation of technical systems by Construction Corporation No. 1 - JSC. Up to now, the volume has reached 92.35% and the disbursement has reached 79.48%.

Currently, the terminal equipment installation is still waiting for the system connection for operation, so it depends on the implementation progress of the Central Technical Block and Funeral Home (FMMO) project and the 1,500-bed General Hospital Equipment project.

FD
Package No. 1 has reached 92.3%. Photo: Dinh Trong

Package No. 2 is the construction and installation of medical gas system equipment and transportation of specimens. The construction unit is the Joint Venture of TNT Technical Technology and Trading Company Limited - H.T.Μ Medical Equipment Trading and Service Joint Stock Company.

Up to now, the implementation volume has reached 89%, the disbursement volume has reached 49.56%, including the following works: complete construction of copper gas pipelines and sample transportation pipelines; terminal equipment, compressors, transportation stations, air cabinets, operating room ceiling hanging arms... have been imported to the project...

Dang trien khai lap dat thiet bi ky thuat. Anh: Dinh Trong
Technical equipment installation in progress. Photo: Dinh Trong

The work to be done includes the installation of single air outlet, installation of operating room ceiling bracket, installation of sending and receiving stations, because we have to wait for the combined operating room work to install synchronously.

In addition to the contracted volumes of the two packages mentioned above, there are currently air conditioning and ventilation systems for the project. This is being reported to the Provincial People's Committee for consideration and approval of the arising policy as a basis for implementation.

v
The project was extended and additional items were added. Photo: Dinh Trong

Construction completion must wait, maintenance costs arise

Regarding the wastewater treatment plant, the construction has been completed and the equipment for the project has been installed. However, the wastewater source is not yet available, and the transformer station has not been accepted to serve the project. This leads to some work items in the contract such as microbiological culture, system stability, interlocking load testing, and transfer training having to wait until the 1,500-bed General Hospital officially operates.

Currently, the units have requested to temporarily stop construction. They are requesting the investor to consider additional funding for construction protection and maintenance of installed equipment.

Cong trinh thanh phan hoan thanh phai cho cac hang muc khac. Anh: Dinh Trong
Completion of component projects must wait for other items. Photo: Dinh Trong

Must adjust equipment project

For the equipment category of the 1,500-bed General Hospital approved since 2019, up to now, the hospital's needs have changed a lot in terms of demand, number of equipment, technical features, technology, etc., so it is necessary to update and adjust to suit the current needs of the using unit, which is the Hospital.

Currently, the project is in the process of reporting the proposed investment policy adjustment. The report has been appraised by the Department of Planning and Investment and is awaiting approval from the Provincial People's Council to carry out the next step. The project is expected to be completed in 2025.

Ky vong du an hoan thanh trong nam 2025. Anh: Dinh Trong
The project is expected to be completed in 2025. Photo: Dinh Trong

1 contractor was terminated for slow construction.

The Binh Duong Province Construction Investment Project Management Board said it has terminated the contract for the construction of the Central Technical Block and the funeral home with a company. To date, the work has been completed at 32.2%; unfinished work accounts for 67.8%.

ĐÌNH TRỌNG
RELATED NEWS

National Assembly finalizes birth certificates, marriage certificates must be signed by the Chairman of the Commune People's Committee

|

The Law on Civil Status (amended) stipulates that the Chairman of the Commune-level People's Committee must directly sign birth certificates and marriage certificates.

Lao Cai gold - the first gold enterprise to list on the stock exchange fluctuates due to debt

|

Losing the right to exploit Minh Luong gold mine, accumulated losses exceeding charter capital, Lao Cai Gold Company is facing the most difficult period since listing on the stock exchange.

The role of trade unions in protecting workers in the digital transformation era

|

Quang Ninh - On the morning of April 23, in Bai Chay, the Vietnam General Confederation of Labor organized a workshop "Trade Unions innovate and improve the efficiency of occupational safety and health in the digital age".

Whales reappear, opening their mouths to hunt prey in Mui Ne sea

|

Lam Dong - People again see whales heading up to the sea surface and continuously opening their mouths to hunt prey in Mui Ne sea. This is the 2nd time in the past week.

It is necessary to soon have regulations on recalling and recycling used electric vehicle batteries

|

National Assembly deputies proposed to soon issue regulations requiring businesses producing, assembling, and importing electric vehicles to recall and recycle used batteries.

Implementing data protection regulations, creating a safe and transparent digital environment

|

Lao Dong Newspaper organizes a seminar "Implementing data protection regulations, creating a safe and transparent digital environment".

Bad news

|

Ms. Hoang Thi Tia, born in 1936, from Thuong Tin commune, Hanoi city (Mother-in-law of comrade Nguyen Thu Ha - Head of the Social Work Department of Lao Dong Newspaper) passed away at 8:00 PM on April 22, 2026 (March 6, Binh Ngo year).

"Beheading" the contractor, when will the 2,300 billion VND hospital be finished?

Lê Thanh Phong |

Binh Duong province "fired" the contractor for delaying the construction of a 2,300 billion VND hospital.

Reason for terminating contract of 1 contractor for 2,300 billion VND hospital project

ĐÌNH TRỌNG |

The 1,500-bed hospital project has been delayed, and Binh Duong province has decided to terminate the contract with one contractor.

Làm đường rộng 10 làn xe, nhà xưởng bạt ngàn đón nhà đầu tư

ĐÌNH TRỌNG |

Những nhà máy sản xuất công nghiệp phía Nam tỉnh Bình Dương đang được định hướng dịch chuyển phía Bắc. Nhiều đường lớn, khu nhà xưởng mới đang được xây dựng.