How is the progress of the 1,500-bed hospital project after 10 years?

ĐÌNH TRỌNG |

The 1,500-bed General Hospital project in Binh Duong (initial investment capital of 2,300 billion VND) was built in 2014 and is still not completed.

According to the Binh Duong Provincial Construction Investment Project Management Board, the 1,500-bed General Hospital project, package 1, is the construction, supply and installation of technical systems by Construction Corporation No. 1 - JSC. Up to now, the volume has reached 92.35% and the disbursement has reached 79.48%.

Currently, the terminal equipment installation is still waiting for the system connection for operation, so it depends on the implementation progress of the Central Technical Block and Funeral Home (FMMO) project and the 1,500-bed General Hospital Equipment project.

FD
Package No. 1 has reached 92.3%. Photo: Dinh Trong

Package No. 2 is the construction and installation of medical gas system equipment and transportation of specimens. The construction unit is the Joint Venture of TNT Technical Technology and Trading Company Limited - H.T.Μ Medical Equipment Trading and Service Joint Stock Company.

Up to now, the implementation volume has reached 89%, the disbursement volume has reached 49.56%, including the following works: complete construction of copper gas pipelines and sample transportation pipelines; terminal equipment, compressors, transportation stations, air cabinets, operating room ceiling hanging arms... have been imported to the project...

Dang trien khai lap dat thiet bi ky thuat. Anh: Dinh Trong
Technical equipment installation in progress. Photo: Dinh Trong

The work to be done includes the installation of single air outlet, installation of operating room ceiling bracket, installation of sending and receiving stations, because we have to wait for the combined operating room work to install synchronously.

In addition to the contracted volumes of the two packages mentioned above, there are currently air conditioning and ventilation systems for the project. This is being reported to the Provincial People's Committee for consideration and approval of the arising policy as a basis for implementation.

v
The project was extended and additional items were added. Photo: Dinh Trong

Construction completion must wait, maintenance costs arise

Regarding the wastewater treatment plant, the construction has been completed and the equipment for the project has been installed. However, the wastewater source is not yet available, and the transformer station has not been accepted to serve the project. This leads to some work items in the contract such as microbiological culture, system stability, interlocking load testing, and transfer training having to wait until the 1,500-bed General Hospital officially operates.

Currently, the units have requested to temporarily stop construction. They are requesting the investor to consider additional funding for construction protection and maintenance of installed equipment.

Cong trinh thanh phan hoan thanh phai cho cac hang muc khac. Anh: Dinh Trong
Completion of component projects must wait for other items. Photo: Dinh Trong

Must adjust equipment project

For the equipment category of the 1,500-bed General Hospital approved since 2019, up to now, the hospital's needs have changed a lot in terms of demand, number of equipment, technical features, technology, etc., so it is necessary to update and adjust to suit the current needs of the using unit, which is the Hospital.

Currently, the project is in the process of reporting the proposed investment policy adjustment. The report has been appraised by the Department of Planning and Investment and is awaiting approval from the Provincial People's Council to carry out the next step. The project is expected to be completed in 2025.

Ky vong du an hoan thanh trong nam 2025. Anh: Dinh Trong
The project is expected to be completed in 2025. Photo: Dinh Trong

1 contractor was terminated for slow construction.

The Binh Duong Province Construction Investment Project Management Board said it has terminated the contract for the construction of the Central Technical Block and the funeral home with a company. To date, the work has been completed at 32.2%; unfinished work accounts for 67.8%.

ĐÌNH TRỌNG
RELATED NEWS

Tim Cook will resign as Apple CEO

|

Apple announced on April 20 that Tim Cook will resign as CEO in September and hand over the highest position to veteran personnel John Ternus.

Ho Chi Minh City is about to build 3 large projects to help Can Gio escape the scene of crossing rivers and ferries

|

Ho Chi Minh City builds sea-crossing roads, expressway intersections, and expands Rung Sac road, helping to break the isolation and directly connect Can Gio with the city center and surrounding areas.

Enrollment 2026: List of schools considering exam scores for competency and thinking assessment

|

Many universities have begun to announce their expected enrollment plans for 2026. In which, many schools use competency and thinking assessment exam scores for admission consideration.

Iran reveals nuclear orientation amid international pressure over enriched uranium

|

Iran affirms nuclear development within the framework of the Treaty on the Non-Proliferation of Nuclear Weapons (NPT), and does not give up the right to enrich uranium.

Approving full-time National Assembly deputies of the 16th term of Lam Dong and Thanh Hoa provinces

|

Vice Chairman of the National Assembly Nguyen Thi Thanh signed and issued 2 Resolutions on approving full-time National Assembly deputies of the 16th term in Lam Dong and Thanh Hoa.

Expecting breakthroughs from high-speed railway projects

|

Many high-speed railway projects have been started, bringing expectations of breakthroughs.

Transfer the case file related to the Usilk City Project to the Ministry of Public Security for consideration and investigation

|

The Government Inspectorate transferred the case file related to the Van Khe Expanded Urban Area Project (Usilk City) to the Ministry of Public Security for consideration, investigation and handling.

Supercomputer predicts U17 Vietnam's win rate in Southeast Asian semi-finals

|

Supercomputer (AI system) predicts the winning rate of U17 Vietnam and U17 Australia in the semi-finals of U17 Southeast Asia 2026.

"Beheading" the contractor, when will the 2,300 billion VND hospital be finished?

Lê Thanh Phong |

Binh Duong province "fired" the contractor for delaying the construction of a 2,300 billion VND hospital.

Reason for terminating contract of 1 contractor for 2,300 billion VND hospital project

ĐÌNH TRỌNG |

The 1,500-bed hospital project has been delayed, and Binh Duong province has decided to terminate the contract with one contractor.

Làm đường rộng 10 làn xe, nhà xưởng bạt ngàn đón nhà đầu tư

ĐÌNH TRỌNG |

Những nhà máy sản xuất công nghiệp phía Nam tỉnh Bình Dương đang được định hướng dịch chuyển phía Bắc. Nhiều đường lớn, khu nhà xưởng mới đang được xây dựng.