How is the progress of the 1,500-bed hospital project after 10 years?

ĐÌNH TRỌNG |

The 1,500-bed General Hospital project in Binh Duong (initial investment capital of 2,300 billion VND) was built in 2014 and is still not completed.

According to the Binh Duong Provincial Construction Investment Project Management Board, the 1,500-bed General Hospital project, package 1, is the construction, supply and installation of technical systems by Construction Corporation No. 1 - JSC. Up to now, the volume has reached 92.35% and the disbursement has reached 79.48%.

Currently, the terminal equipment installation is still waiting for the system connection for operation, so it depends on the implementation progress of the Central Technical Block and Funeral Home (FMMO) project and the 1,500-bed General Hospital Equipment project.

FD
Package No. 1 has reached 92.3%. Photo: Dinh Trong

Package No. 2 is the construction and installation of medical gas system equipment and transportation of specimens. The construction unit is the Joint Venture of TNT Technical Technology and Trading Company Limited - H.T.Μ Medical Equipment Trading and Service Joint Stock Company.

Up to now, the implementation volume has reached 89%, the disbursement volume has reached 49.56%, including the following works: complete construction of copper gas pipelines and sample transportation pipelines; terminal equipment, compressors, transportation stations, air cabinets, operating room ceiling hanging arms... have been imported to the project...

Dang trien khai lap dat thiet bi ky thuat. Anh: Dinh Trong
Technical equipment installation in progress. Photo: Dinh Trong

The work to be done includes the installation of single air outlet, installation of operating room ceiling bracket, installation of sending and receiving stations, because we have to wait for the combined operating room work to install synchronously.

In addition to the contracted volumes of the two packages mentioned above, there are currently air conditioning and ventilation systems for the project. This is being reported to the Provincial People's Committee for consideration and approval of the arising policy as a basis for implementation.

v
The project was extended and additional items were added. Photo: Dinh Trong

Construction completion must wait, maintenance costs arise

Regarding the wastewater treatment plant, the construction has been completed and the equipment for the project has been installed. However, the wastewater source is not yet available, and the transformer station has not been accepted to serve the project. This leads to some work items in the contract such as microbiological culture, system stability, interlocking load testing, and transfer training having to wait until the 1,500-bed General Hospital officially operates.

Currently, the units have requested to temporarily stop construction. They are requesting the investor to consider additional funding for construction protection and maintenance of installed equipment.

Cong trinh thanh phan hoan thanh phai cho cac hang muc khac. Anh: Dinh Trong
Completion of component projects must wait for other items. Photo: Dinh Trong

Must adjust equipment project

For the equipment category of the 1,500-bed General Hospital approved since 2019, up to now, the hospital's needs have changed a lot in terms of demand, number of equipment, technical features, technology, etc., so it is necessary to update and adjust to suit the current needs of the using unit, which is the Hospital.

Currently, the project is in the process of reporting the proposed investment policy adjustment. The report has been appraised by the Department of Planning and Investment and is awaiting approval from the Provincial People's Council to carry out the next step. The project is expected to be completed in 2025.

Ky vong du an hoan thanh trong nam 2025. Anh: Dinh Trong
The project is expected to be completed in 2025. Photo: Dinh Trong

1 contractor was terminated for slow construction.

The Binh Duong Province Construction Investment Project Management Board said it has terminated the contract for the construction of the Central Technical Block and the funeral home with a company. To date, the work has been completed at 32.2%; unfinished work accounts for 67.8%.

ĐÌNH TRỌNG
RELATED NEWS

Minister of Justice clarifies concerns that unemployed public lawyers still receive salaries

|

The Minister of Justice said that there is no rigid regulation on the ratio of time to perform tasks: Public lawyers and the work of civil servants.

Live football U17 Vietnam vs U17 Australia in the semi-finals of U17 Southeast Asia

|

Live match between U17 Vietnam and U17 Australia in the U17 Southeast Asian semi-finals, taking place at 7:30 PM today (April 22).

Fight against false and hostile information with scientific and persuasive arguments

|

Regulation No. 19-QD/TW has stated the proactive struggle against false and hostile information and arguments with scientific and persuasive arguments.

Thousands of tons of eels are in stock, farmers in Can Tho and Ca Mau face the risk of losses

|

Can Tho - Eel prices in Can Tho and Ca Mau have dropped sharply, causing farmers to face the risk of losses.

Veteran and the journey of more than 30 years of "keeping the fire" of national history

|

Instead of choosing a comfortable retirement age, the veteran entered a new "job" - educating national historical traditions.

Iran opens fire on container ship in the Strait of Hormuz

|

Iran fired at a container ship in the Strait of Hormuz on April 22, causing the ship to be damaged.

Long Thanh airport lacks labor

|

Dong Nai - Long Thanh Airport is targeted to be put into commercial operation in the fourth quarter of 2026, but still faces difficulties due to labor shortages.

Britain, France convene multinational military alliance, discuss reopening the Strait of Hormuz

|

According to the British Ministry of Defense, more than 30 countries will attend a conference in London to build a military plan to reopen the Strait of Hormuz after reaching a ceasefire agreement.

"Beheading" the contractor, when will the 2,300 billion VND hospital be finished?

Lê Thanh Phong |

Binh Duong province "fired" the contractor for delaying the construction of a 2,300 billion VND hospital.

Reason for terminating contract of 1 contractor for 2,300 billion VND hospital project

ĐÌNH TRỌNG |

The 1,500-bed hospital project has been delayed, and Binh Duong province has decided to terminate the contract with one contractor.

Làm đường rộng 10 làn xe, nhà xưởng bạt ngàn đón nhà đầu tư

ĐÌNH TRỌNG |

Những nhà máy sản xuất công nghiệp phía Nam tỉnh Bình Dương đang được định hướng dịch chuyển phía Bắc. Nhiều đường lớn, khu nhà xưởng mới đang được xây dựng.