The Construction Investment Project Management Board of Binh Duong province said that the 1,500-bed General Hospital project, package No. 1 is the construction, supply and installation of technical systems by Construction Corporation No. 1 - JSC. construction. To date, the volume has reached 92.35% and disbursement reached 79.48%.
There is still the installation of terminal equipment waiting to be connected to the system for operation, so it depends on the implementation progress of the Central Technical Block and Funeral House (FMMO) item, and the General Hospital Equipment item. 1,500 beds.
Package No. 2 is construction and installation of medical gas system equipment and specimen transportation. The construction unit is a joint venture of TNT Trading and Technical Technology Company Limited - HTΜ Medical Equipment Trading and Services Joint Stock Company.
To date, the implementation volume has reached 89%, the disbursement volume has reached 49.56%, including the following tasks: complete construction of copper gas pipelines and specimen transportation pipelines; Terminal equipment, compressors, transport stations, gas cabinets, operating room ceiling arms... have been imported to the project...
The work that needs to be done includes the work of installing a single air outlet, installing the operating room ceiling mount, and installing the sending and receiving station, because we have to wait for the combined operating room work to be installed synchronously.
In addition to the contractual volumes of the two packages mentioned above, there is currently an air conditioning and ventilation system for the project. This is being submitted to the Provincial People's Committee for consideration and approval of the arising policy as a basis for implementation.
The completed project must wait, incurring maintenance costs
For the wastewater treatment station, construction has now been completed and the project's equipment connections have been installed. However, the wastewater source is not yet available and the transformer station has not been accepted to serve the project. This leads to some work items in the contract such as microbiological culture, system stabilization, interlock load testing, and transfer training having to wait until the 1,500-bed General Hospital officially operates.
Currently, the units have asked to temporarily stop construction. We are proposing that the investor consider additional funding for project protection and preservation of installed equipment.
Equipment project must be adjusted
For the 1,500-bed General Hospital equipment item approved since 2019, up to now the hospital's needs have many changes in terms of needs, quantity of equipment, technical features, technology,... Therefore, it is necessary to update and adjust it to suit the current needs of the user unit, the Hospital.
Currently, the project is carrying out the step of reporting and proposing adjusted investment policies. The report document proposing the adjusted investment policy has been appraised by the Department of Planning and Investment and is awaiting approval by the Provincial People's Council to take the next step. The project is expected to be completed in 2025.
1 contractor whose construction was slow had his contract terminated
The Construction Investment Project Management Board of Binh Duong province said it has terminated the construction contract for the Central Technical Block and funeral home items for Nam Thinh Refrigeration Electrical Engineering Joint Stock Company. To date, the implementation volume has reached 32.2%; Unrealized work accounts for 67.8%.