Progress of overcoming landslides and anti-landslide embankments in Kien Giang

NGUYÊN ANH |

Kien Giang - The work to repair the embankment landslide has completed items such as piling, construction and installation of formwork reinforcement and pouring concrete for the bottom slab in 3 segments.

On November 1, the People's Committee of Giang Thanh district (Kien Giang) provided information on the progress of overcoming subsidence and landslides of the Ha Giang canal embankment project.

According to the District People's Committee, the embankment project was completed and put into use for a while, but on August 4, 2024, landslides occurred in 3 segments A35, A36, A37.

After the incident occurred, the District People's Committee directed the District Construction Investment Project Management Board, construction units, supervision units, and design consultants to inspect and survey the site. At the same time, the District People's Committee organized meetings to propose solutions to complete the work as soon as possible.

The district also assigned the District Construction Investment Project Management Board to directly monitor the progress of the repair. However, the progress of the repair is still slower than expected and the contractor's commitment due to the weather, construction during the rain and storm, which somewhat affected the progress.

Huyen Giang Thanh cho hay cong tac khac phuc cung gap phan nao kho khan vi thoi tiet mua bao. Anh: Xuan Nhi
Giang Thanh district said the recovery work was also somewhat difficult due to the stormy weather. Photo: Xuan Nhi

Up to now, the troubleshooting of the above 3 segments has completed the following items: piling, construction and installation of formwork reinforcement, pouring concrete for the bottom slab of the 3 segments. The construction unit is preparing for the construction of the remaining items such as pouring concrete for the embankment wall; filling soil behind the embankment; completing sidewalks, trees, internal roads, curbs and railings. The lighting system at these 3 segments is expected to be completed by November 30, 2024.

The contractor is currently constructing the subsidence brick paving on the embankment (natural subsidence), the volume has reached 70%, the rest will be completed as soon as possible.

The District People's Committee also said that it has directed the District Construction Investment Project Management Board to regularly monitor the progress and quality of the project and require supervision consultants to be present regularly at the project during the remediation process, promptly report problems occurring on the project and take responsibility for their duties.

The contractor must speed up the work of fixing the problems in the above 3 segments and the natural subsidence locations, creating a green, clean and flat embankment landscape as soon as possible during the warranty period, but must ensure the quality of the project according to regulations.

As previously reported, the Ha Giang canal embankment is more than 3km long. After the incident, representatives of the investor, construction unit, and supervisory unit recorded the scene, warned of danger, and erected barriers. At the same time, machinery and workers also unloaded soil at 3 sections at risk of landslides to reduce the load, conduct geological surveys, and propose solutions to fix and stabilize the entire embankment.

The embankment project has an investment of 80 billion VND. The embankment project with auxiliary systems such as sidewalks, trees, drainage systems, lighting... will be completed in 18 months and will be accepted and put into use from March 11, 2024.

However, in July 2024, the embankment showed signs of subsidence of pavement tiles. By August 2024, a nearly 70m long embankment section had seriously eroded, causing concern among residents.

NGUYÊN ANH
TIN LIÊN QUAN

President Biden speaks out on 2024 US election results

|

President Joe Biden has spoken out about the results of the 2024 US election, in which Ms. Kamala Harris confirmed her loss to Mr. Donald Trump.

People suffer because roads become dikes to block water

|

Due to the lack of drainage, many roads in Quang Tri province have become dikes every time it rains, causing flooding. Although people have made many complaints since the construction began, the authorities have yet to take a thorough action.

Proposal to terminate FLC's multi-billion high-tech agricultural project

|

The high-tech agricultural project in Thach Van commune (Thach Ha district, Ha Tinh province) failed when the investor asked to return the project.

Typhoon Yinxing's terrifying journey towards Vietnam

|

Typhoon Yinxing (Marce) has been steadily strengthening over the past two days, continuing to threaten parts of the Philippines before heading towards central Vietnam.

Waiting for the mark of the female volleyball team coach

|

Women's content - phase 2 of the 2024 National Volleyball Championship will compete today (November 7). It is easy to see that each teacher is the spiritual leader for his students, so the coach's decisiveness on the field is a decisive factor in the outcome.

Nhan Dan Newspaper won Gold Award, Asian Media Awards, WAN-IFRA

|

The propaganda campaign for the 70th anniversary of Dien Bien Phu Victory of Nhan Dan Newspaper was awarded the Gold Prize in the Best in Newspaper Marketing category within the framework of the 2024 Asian Media Awards organized by WAN-IFRA.

Vụ bờ kè 80 tỉ đồng sạt lở, trước đó đã 2 lần xảy ra sự cố

NGUYÊN ANH |

Ngoài sự cố sạt lở hồi tháng 8.2024 khi đưa vào sử dụng 5 tháng thì trước đó, dự án bờ kè chống sạt lở kênh Hà Giang còn 2 lần bị sự cố lúc thi công.

Dự án bờ kè 80 tỉ đồng sạt lở, Kiên Giang xử lý ra sao

NGUYÊN ANH |

Chủ đầu tư, đơn vị thi công, đơn vị giám sát đã ghi nhận hiện trường bờ kè sạt lở (huyện Giang Thành, Kiên Giang) cảnh báo nguy hiểm, dựng hàng rào chắn.

Sạt lở nghiêm trọng, Kiên Giang chủ động di dời dân khỏi vùng nguy hiểm

NGUYÊN ANH |

Trước diễn biến sạt lở phức tạp, nghiêm trọng hơn khi vào mùa mưa bão, Kiên Giang đã chỉ đạo các ngành chuyên môn, địa phương vùng sạt lở sớm di dời dân trước khi có thiệt hại, nhằm giữ tài sản, an toàn tính mạng người dân.