Ninh Binh province spends 2,000 billion VND to build highways

NGUYỄN TRƯỜNG |

Ninh Binh - Ninh Binh - Hai Phong Expressway, the section passing through Ninh Binh province, has a total investment of over 6.8 trillion VND, of which the provincial budget is 2,000 billion VND.

On November 13, speaking with Lao Dong Newspaper, Mr. Nguyen Cao Son - Vice Chairman of Ninh Binh Provincial People's Committee said that the Ninh Binh - Hai Phong Expressway Project is 117km long, passing through Ninh Binh province about 26km, Nam Dinh and Thai Binh about 62km, Hai Phong 29km. The section from Nam Dinh province to Thai Binh is implemented under the PPP method, while the section through Ninh Binh province is invested with budget capital.

According to Mr. Son, according to the traffic network planning, the Ninh Binh - Hai Phong expressway (the whole route is coded as CT.08) is approved for investment in the form of PPP.

However, after more than a year of implementing the preparation steps, the investment procedures under the PPP form have some difficulties. The total length of the route is up to 117km, so if investing under the PPP form, the capital recovery time is too long, so investors cannot do it and it is not feasible.

Therefore, it is necessary to submit to the National Assembly to change the investment form, dividing the project into 3 sections. Of which, the section through Ninh Binh and Hai Phong provinces is invested by the central and local budgets. The section through Thai Binh and Nam Dinh provinces is invested by the PPP form.

"According to regulations for central projects, the central budget is used for investment. However, in the medium-term public investment of the central government and the Ministry of Transport, there are not enough resources, so it is necessary to submit to the National Assembly to issue a resolution to pilot a number of specific policies in the implementation of the Ninh Binh - Hai Phong expressway project, the section through Ninh Binh. Accordingly, Ninh Binh province is allowed to participate in contributing capital to the implementation of the central project" - Mr. Son said.

According to Mr. Son, after the National Assembly issued a Resolution on piloting a number of specific policies, the Prime Minister delegated authority to the People's Committee of Ninh Binh province to be the competent authority to invest in the Ninh Binh - Hai Phong expressway project, the section passing through Ninh Binh province. The People's Committee of Ninh Binh province submitted to the Provincial People's Council and issued a Resolution on the investment policy for the construction of the Ninh Binh - Hai Phong expressway, the section passing through Ninh Binh province with a total investment of over 6.8 trillion VND from the central and local budgets. Of which, the local budget is 2,000 billion VND.

"The completion of the Ninh Binh - Hai Phong expressway, the section through Ninh Binh, in addition to ensuring synchronous connection of the entire expressway from Ninh Binh to Hai Phong, also creates momentum for socio-economic development of the area south of Hanoi, the Red River Delta and the North Central region," Mr. Son shared.

NGUYỄN TRƯỜNG
RELATED NEWS

Ninh Binh - Hai Phong Expressway will start construction in December 2024

|

Ninh Binh - As planned, the Ninh Binh - Hai Phong expressway project, the section passing through Ninh Binh province, will start construction in December 2024.

Stocks maintain recovery momentum

|

The focus of this week's stock market will be the mid-term assessment of market upgrades by FTSE Russell, a catalyst that opens up new waves of increase.

Stone mine "suspended" for 9 months, Gia Lai warns to replace commune leaders

|

Gia Lai - Although licensed, a quarry is still "suspended" for 9 months due to land lease procedures at the commune level.

Hanoi Industrial Meal Company won 148/148 bidding packages, with a total value of 505.8 billion VND

|

Hanoi Industrial Meal Service Joint Stock Company participated and won all 148 bidding packages to supply meals at schools in Hanoi and some northern provinces.

Teachers of Song Hong school nearly 20 months without salary, Phu Tho Department of Home Affairs speaks out

|

Phu Tho - Regarding the case of teachers of Song Hong Intermediate School who have not received salary for nearly 20 months, the Phu Tho Department of Home Affairs has spoken out.

400 billion VND for reconstruction, emergency traffic projects in Da Nang are still messy

|

Da Nang - After more than 4 years of construction, the nearly 400 billion VND emergency traffic project in the mountainous disaster area is still unfinished, bumpy as if it has never been rebuilt.

Day and night construction at the construction site of the widest cable-stayed bridge project in Hai Phong

|

Hai Phong - To date, the construction of the nearly 1,500m long cable-stayed main bridge under the Nguyen Trai bridge project has reached about 32% of the progress, striving to reach the finish line in September 2027.

Today the National Assembly considers and decides on personnel and organizational structure

|

According to the Session program, today April 6, the First Session of the 16th National Assembly officially opens.

Ninh Binh - Hai Phong Expressway will start construction in December 2024

NGUYỄN TRƯỜNG |

Ninh Binh - As planned, the Ninh Binh - Hai Phong expressway project, the section passing through Ninh Binh province, will start construction in December 2024.

Sẽ đầu tư 6 km còn lại dự án cao tốc Ninh Bình - Hải Phòng

Xuyên Đông |

Tuyến cao tốc Ninh Bình - Hải Phòng dài 109 km, cơ quan chức năng đã đầu tư và triển khai gần xong, chỉ còn đúng 6 km qua Hải Phòng.

Cao tốc Ninh Bình - Hải Phòng kết nối hành lang kinh tế

NGUYỄN TRƯỜNG |

Cao tốc Ninh Bình - Hải Phòng, đoạn qua địa bàn tỉnh Ninh Bình hoàn thành sẽ tạo thành hành lang phát triển kinh tế trọng điểm phía Bắc của tỉnh Ninh Bình.