Overview of Huu Nghi - Chi Lang Expressway before the route opens

Khánh Linh |

Lang Son - In less than 24 hours, the Huu Nghi - Chi Lang border gate expressway will officially open.

In mid-December, at the Huu Nghi - Chi Lang border gate expressway construction site, the urgent working atmosphere blended with the joy that was evident on every face of the local workers and people.

After more than 1 year and 8 months of continuous construction, the 43km long expressway is entering the final final drainage stage, ready for the opening ceremony scheduled to take place on the morning of December 19.

According to Lao Dong Newspaper reporters at Km44+700, in Nhan Ly commune, where the route opening ceremony was planned to be held, flags, billboards, and banners have been fully installed.

a
At the Huu Nghi - Chi Lang Expressway construction site. Photo: Vu Linh

The roads leading to the event area are cleaned, creating a solemn and exciting atmosphere. Not only at the construction site, joy also spreads in the lives of people living along the expressway.

Mr. Hoang Van Loi (62 years old, Nhan Ly commune) shared: "We look forward to this route every day. Previously, travel was difficult, now seeing the expressway about to open, everyone is happy. With a new road, travel and business are certainly more convenient."

The construction atmosphere is still maintained urgently along the entire route. More than 19km of the expressway has been paved; construction units are continuing to complete the embankment system to prevent landslides on positive slopes, drainage ditches and auxiliary items.

a
The construction atmosphere is still maintained urgently along the entire route. Photo: Vu Linh

The Huu Nghi - Chi Lang border gate expressway has a total of 38 bridges; of which, the Km18 overpass has been basically completed, the bridge surface is being completed according to plan.

The Huu Nghi - Chi Lang border gate expressway project started construction at the end of April 2024, with a total investment of more than VND 11,000 billion, implemented under the form of public-private partnership (PPP), BOT contract.

The construction process mobilized 2,821 engineers, workers, 1,237 equipment, organized 141 simultaneous construction teams, ensuring progress and quality of the project.

On December 18, speaking with a reporter from Lao Dong Newspaper, Mr. Hoang Dinh Tue - Deputy Director of the Lang Son Provincial Construction Investment Project Management Board said that according to the plan, the project enterprise and contractors set a goal of completing about 30km of asphalt concrete, connecting the section from Yen Trach intersection to the end point of the route at Chi Lang before Tet.

Ky su kiem tra chat luong cong trinh. Anh: Vu Linh
Engineer checks the quality of the project. Photo: Vu Linh

This is a key task in the next phase. Contractors are required to mobilize maximum human resources, equipment, organize continuous construction, and take advantage of favorable weather to ensure the completion of the asphalt paving volume according to the committed schedule, Mr. Tue emphasized.

Along with that, site clearance continues to be identified as a key stage.

The Project Management Board is closely coordinating with departments, branches, and local authorities to focus on removing obstacles, striving to promptly hand over clean land to the construction unit.

Pho Chu tich UBND tinh Lang Son Doan Thanh Son kiem tra, chi dao cong tac chuan bi le thong tuyen. Anh: Tri Dung
Vice Chairman of Lang Son Provincial People's Committee Doan Thanh Son inspected and directed the preparation for the route opening ceremony. Photo: Tri Dung

According to Mr. Tue, for areas that are still facing difficulties, especially hot spots such as Dong Kinh ward, all levels and sectors will take drastic action, fully and in accordance with regulations, implement compensation and support policies, ensure the harmony of interests of the State, businesses and people, not to affect the overall progress of the project.

The opening ceremony of the Huu Nghi - Chi Lang expressway project is one of 234 projects nationwide that simultaneously started construction, inaugurated, opened to technical traffic, and opened the route on the morning of December 19, welcoming the 11th National Patriotic Emulation Congress and the 14th National Party Congress.

Tuyen duong duoc ky vong se giam tai ap luc giao thong tren Quoc lo 1A. Anh: Vu Linh
The route is expected to reduce traffic pressure on National Highway 1A. Photo: Vu Linh

The ceremony was held at 79 locations nationwide, in the form of direct combination online, connecting via television.

When the whistle blew, the Huu Nghi - Chi Lang expressway will shorten the distance, expanding development space for the border area.

On the completed roadbed, there is the sweat and efforts of thousands of engineers and workers, the belief and expectation of the people of the border area for a smooth future of trade and a better life.

Khánh Linh
RELATED NEWS

The first 20km of the Khanh Hoa - Buon Ma Thuot expressway is ready for technical traffic

|

Khanh Hoa - The first 20km of the Khanh Hoa - Buon Ma Thuot expressway project has been basically completed, qualified for technical traffic opening on December 19.

Dong Dang - Tra Linh Expressway is as beautiful as a painting before the "opening" date

|

In just 2 days, the Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway will officially open the route, opening up opportunities for the Northeastern provinces.

85km of foundation and 20km of asphalt paving will be opened on the Dong Dang - Tra Linh Expressway

|

Cao Bang - At the Dong Dang - Tra Linh expressway construction site, workers are working overtime day and night to open the technical route in time.

Stock market liquidity continues to decrease sharply

|

The cautious mentality on the derivatives expiry date has caused the stock market to have a rather boring trading session with deeply decreased liquidity.

After reporting that boarding meals were too few, parents went directly to the school to check

|

HCMC - After comments on social networks about boarding meals, many parents went directly to school to check.

Cho Ray Hospital informs about the history of the ambulance that collided, killing 3 people

|

HCMC - Regarding the ambulance collision that killed 3 people, Cho Ray Hospital said the driver and the vehicle were not part of the hospital's personnel.

Hospital with 2 helicopter Landing lots in Ho Chi Minh City has been under construction for 11 years but is still not finished

|

HCMC - The 1,500-bed hospital with 2 helicopter landing areas in the North of HCMC has been under construction for 11 years but has not yet been completed.

Live Vietnam vs Indonesia men's volleyball in the 33rd SEA Games semi-finals

|

Live match between the Vietnamese men's volleyball team and Indonesia in the semi-finals of the 33rd SEA Games, taking place at 3:00 p.m. today (December 18).

The first 20km of the Khanh Hoa - Buon Ma Thuot expressway is ready for technical traffic

Hữu Long |

Khanh Hoa - The first 20km of the Khanh Hoa - Buon Ma Thuot expressway project has been basically completed, qualified for technical traffic opening on December 19.

Dong Dang - Tra Linh Expressway is as beautiful as a painting before the "opening" date

Khánh Linh |

In just 2 days, the Dong Dang (Lang Son) - Tra Linh (Cao Bang) expressway will officially open the route, opening up opportunities for the Northeastern provinces.

85km of foundation and 20km of asphalt paving will be opened on the Dong Dang - Tra Linh Expressway

Duy Dũng |

Cao Bang - At the Dong Dang - Tra Linh expressway construction site, workers are working overtime day and night to open the technical route in time.