85km of foundation and 20km of asphalt paving will be opened on the Dong Dang - Tra Linh Expressway

Duy Dũng |

Cao Bang - At the Dong Dang - Tra Linh expressway construction site, workers are working overtime day and night to open the technical route in time.

The Dong Dang - Tra Linh Expressway project has a total length of 121km, invested in two phases with a total investment of nearly VND23,000 billion. The route passes through the two provinces of Lang Son and Cao Bang, of which phase 1 is over 93km long, and is considered one of the expressway projects with the most difficult construction conditions today.

According to records, the entire phase 1 route has up to 64 overpasses, spanning the Ky Cung River, Bang Giang River and many streams and provincial roads. The harsh terrain, the Karst geological foundation (complex Caster cave limestone) and the prolonged flood situation, unusual developments have created many challenges for the construction process.

Cac cong nhan dang thi cong trai tham nhua mat duong, hoan thien vo ham va dao dap nen duong. Anh: Tan Van
Workers are paving the road surface, completing the tunnel lining and digging the roadbed. Photo: Tan Van

On December 17, at the construction site, more than 3,000 officers, engineers and workers were working busily, they spread out hundreds of construction teams, drilled mountains, opened roads, and accelerated the project's progress.

Phase 1 of the expressway has two tunnel crossings, That Khe tunnel and Dong Khe tunnel, named after locations associated with the Border Campaign of 22.

In the Dong Khe tunnel area (nearly 500m long), construction teams are focusing on completing the retaining wall, drainage system, mechanical roof, square area and road connecting the two tunnel gates. Many items such as the outer pressing rack of the tunnel shell and tunnel cleaning are also being implemented simultaneously.

De kip tien do, ba dem tren cong truong van sang den lam viec. Anh: Tan Van
To keep up with the progress, at night the construction site is still lit up with working lights. Photo: Tan Van

At Km58, Dong Khe commune, the asphalt paving line is maintained continuously day and night, with an output of about 2,000 tons per day.

During the "sprint" period, construction units worked all night, without days off to speed up and make up for the progress affected by the weather.

Talking to reporters, Mr. Hoang Duc Tho - Director of the Cao Bang Provincial Traffic Project Management Board said that the construction unit is striving to asphalt 20km of the road on the project by December 19.

"Currently, the units are reinforcing the carpets day and night. The rain for 2 days has affected the paving progress, and the brothers are working overtime at night," said Mr. Tho.

Tuyen cao toc co nhieu cau vuot song, suoi va ham xuyen nui. Anh: Tan Van
The expressway has many bridges across rivers, streams and tunnels across mountains. Photo: Tan Van

According to the plan, before December 19, phase 1 of the project strives to complete the entire roadbed and road surface on the main route of about 85/9km, except for some locations affected by floods and additional bridges. Along with that is 20km of paved road.

This is considered an important milestone, creating a premise for the Dong Dang - Tra Linh expressway to soon promote effective connectivity, promoting the socio-economic development of the Northeast region.

Duy Dũng
RELATED NEWS

Solving the problem of capital shortage at the key Dong Dang - Tra Linh expressway project

|

Cao Bang - The locality is arranging resources to soon achieve the goal of completing phase 1 of the Dong Dang - Tra Linh expressway.

Dong Dang - Tra Linh Expressway will pave the way for Cao Bang to develop

|

Cao Bang - The Dong Dang - Tra Linh Expressway has been started in both phases, expanding 4 lanes.

Starting construction of phase 2 of the Dong Dang - Tra Linh key expressway

|

On the morning of August 19, Cao Bang province coordinated with relevant parties to organize the groundbreaking ceremony for phase 2 of the Dong Dang - Tra Linh Expressway construction project.

boldly handing over to the private sector, forming an autonomous railway industry

|

Many units proactively adjust railway technology and equipment to suit Vietnam's conditions and needs with a transparent mechanism for railway businesses.

Coach Kim Sang-sik: U22 Vietnam will win the championship at Rajamangala

|

Coach Kim Sang-sik is confident that U22 Vietnam will win the 33rd SEA Games gold medal against host Thailand U22.

Gold prices surge, people buy and sell enthusiastically

|

Gold prices recovered after a decline, people with a busy demand for buying. Number of sellers continue to receive coupons waiting for transactions.

The psychology of dealing with AI cameras and the price of covering license plates

|

Hanoi - AI cameras are put into operation, many drivers cover their license plates to avoid fines but are quickly detected and strictly handled.

Proposal to remove difficulties for Nha Rong - Khanh Hoi Complex project

|

HCMC - The investor of the Nha Rong - Khanh Hoi Complex project committed to being ready to adjust the project planning according to the new policy of the city.

Solving the problem of capital shortage at the key Dong Dang - Tra Linh expressway project

Tân Văn |

Cao Bang - The locality is arranging resources to soon achieve the goal of completing phase 1 of the Dong Dang - Tra Linh expressway.

Dong Dang - Tra Linh Expressway will pave the way for Cao Bang to develop

Tân Văn |

Cao Bang - The Dong Dang - Tra Linh Expressway has been started in both phases, expanding 4 lanes.

Starting construction of phase 2 of the Dong Dang - Tra Linh key expressway

Tân Văn |

On the morning of August 19, Cao Bang province coordinated with relevant parties to organize the groundbreaking ceremony for phase 2 of the Dong Dang - Tra Linh Expressway construction project.