Ho Chi Minh City clears more than 1,000 households to build 6-lane road in Thu Duc

MINH QUÂN |

HCMC - Thu Duc City is urgently completing procedures to spend more than 7,000 billion VND to compensate for two sections of the Ring Road 2 project, affecting more than 1,000 households.

The two sections of Beltway 2 through Thu Duc City have a total length of more than 6km. Section 1 is 3.5km long, starting from Phu Huu Bridge and connecting to Vo Nguyen Giap Avenue, with a total investment of about VND9,328 billion.

Section 2 from Vo Nguyen Giap Avenue to Pham Van Dong Street, has a length of 2.8km with a total capital of about 4,543 billion VND.

Both projects will have their entire land cleared from the beginning, 67m wide, then parallel roads will be built on both sides with 6 lanes (each road is 17m wide, 3 lanes). The vacant land in the middle of the route will be reserved for future road expansion.

Of the total investment cost, the majority of the cost is for site clearance, estimated at more than VND8,600 billion, to reclaim more than 61 hectares of land. This is one of the major challenges of the project, due to the large number of affected households, up to more than 1,000 cases.

Sau khi di qua duong Kha Van Can, doan Vanh dai 2 se den duong Pham Van Dong. Anh: Anh Tu
After passing Kha Van Can Street, the Ring Road 2 section will reach Pham Van Dong Street. Photo: Anh Tu

According to Mr. Hoang Tung - Chairman of Thu Duc City People's Committee, the counting and verification work has been completed on schedule. Currently, the units are urgently completing legal procedures, collecting information and appraising land prices to be able to proceed with compensation for the people.

However, one of the biggest difficulties of the project at present is the resettlement of affected households.

The Belt Road 2 project is expected to require 657 plots of land and 68 apartments to serve resettlement needs. Of which, section 1 requires 555 plots of land and 58 apartments, while section 2 requires 102 plots of land and 10 apartments. However, when the 2024 Land Law comes into effect, the project will face many new legal problems.

Thu Duc City has proposed that the Ho Chi Minh City People's Committee adjust decisions related to compensation and resettlement, and at the same time requested a review of all public land along Ring Road 2 to build the nearest resettlement area for households.

"Currently, Thu Duc City has identified a number of land plots that can be used immediately for the construction of resettlement areas with a total investment not too large," said Mr. Hoang Tung.

TPHCM muon cong tac boi thuong du an Vanh dai 2 la “kieu mau” khi ap dung Luat Dat dai 2024.  Anh: Anh Tu
Ho Chi Minh City wants compensation for the Ring Road 2 project to be a "model" when applying the 2024 Land Law. Photo: Anh Tu

At a recent working session with Thu Duc City, Chairman of the Ho Chi Minh City People's Committee Phan Van Mai emphasized that the two sections of Ring Road 2 through Thu Duc City are "model" projects in implementing the 2024 Land Law.

Mr. Phan Van Mai requested that relevant departments and branches must have high political determination and coordinate closely to effectively implement the project right from the first stage.

To achieve the above goal, Mr. Phan Van Mai noted that relevant departments and branches should focus on implementing the task of adjusting land price lists and related documents, other support policies, and by October 30, must complete project approval and approve resettlement compensation plans.

In addition, Mr. Phan Van Mai also assigned Thu Duc City to complete disbursing at least VND 7,600 billion for the Ring Road 2 project by the end of this year.

According to the plan, these two sections of Ring Road 2 will start construction in the second quarter of 2025 and be completed in 2027, contributing to completing the Eastern traffic network, increasing connections to Cat Lai and Truong Tho ports...

MINH QUÂN
TIN LIÊN QUAN

7 năm chưa làm xong 2,7km đường vành đai ở TPHCM

MINH QUÂN |

TPHCM – Khởi công năm 2017, dự kiến hoàn thành sau 2 năm, nhưng đến nay 2,7km đường Vành đai 2 (từ đường Phạm Văn Đồng đến nút giao Gò Dưa, TP Thủ Đức) mới đạt gần 44% khối lượng và tạm ngưng thi công 4 năm qua.

Dự án Vành đai 2 TPHCM lận đận 16 năm vẫn chưa khép kín

MINH QUÂN |

TPHCM - Dự án đường Vành đai 2 TPHCM được quy hoạch từ năm 2007 với tổng chiều dài 64km có vai trò quan trọng giúp phân luồng, giảm áp lực giao thông nội đô. Tuy nhiên, cho đến nay, đường Vành đai 2 hiện vẫn còn 14 km (chia làm 4 đoạn) chưa được khép kín.

Hơn 2 km thuộc vành đai 2 hoen gỉ, hoang tàn sau 6 năm dang dở

Phương Ngân - Anh Tú |

TP Hồ Chí Minh - Một đoạn Vành đai 2 dài 2,7 km từ đường Phạm Văn Đồng đến nút giao thông Gò Dưa đã triển khai từ 6 năm trước nhưng đến nay vẫn nằm dang dở, nhiều vật liệu tại công trình hoen gỉ.

Gần 200 người tìm kiếm 2 nạn nhân bị cuốn trôi ở Sơn La

Minh Chuyên |

Sơn La - Các lực lượng chức năng đang tích cực tìm kiếm 2 nạn nhân bị nước cuốn trôi khi đi qua ngầm tràn ở xã Đông Sang, huyện Mộc Châu.

Xác nhận mới về vị trí MH370 mất tích

Thanh Hà |

Tin MH370 mới nhất một lần nữa xác nhận nghiên cứu của kỹ sư hàng không vũ trụ Anh Richard Godfrey về việc xác định địa điểm máy bay MH370 rơi.

Tìm thấy thi thể bé trai 1 tuổi trong vụ lũ quét ở Làng Nủ

Đinh Đại |

Lào Cai - Sáng 22.9, lực lượng chức năng đã tìm thấy thêm thi thể nạn nhân trong vụ lũ quét kinh hoàng ở Làng Nủ (Phúc Khánh, Bảo Yên).

Hóa chất Đức Giang Lào Cai thua trận ra quân Giải bóng chuyền các câu lạc bộ châu Á

MINH PHONG |

Hóa chất Đức Giang Lào Cai thua 0-3 trước Kuanysh VC trận ra quân Giải bóng chuyền vô địch các câu lạc bộ châu Á 2024 vào sáng 22.9.

Hezbollah tấn công căn cứ quân sự Israel

Thanh Hà |

Lực lượng Hezbollah ở Lebanon tuyên bố đã bắn một loạt tên lửa vào một căn cứ quân sự sâu bên trong Israel vào sáng sớm 22.9.

7 năm chưa làm xong 2,7km đường vành đai ở TPHCM

MINH QUÂN |

TPHCM – Khởi công năm 2017, dự kiến hoàn thành sau 2 năm, nhưng đến nay 2,7km đường Vành đai 2 (từ đường Phạm Văn Đồng đến nút giao Gò Dưa, TP Thủ Đức) mới đạt gần 44% khối lượng và tạm ngưng thi công 4 năm qua.

Dự án Vành đai 2 TPHCM lận đận 16 năm vẫn chưa khép kín

MINH QUÂN |

TPHCM - Dự án đường Vành đai 2 TPHCM được quy hoạch từ năm 2007 với tổng chiều dài 64km có vai trò quan trọng giúp phân luồng, giảm áp lực giao thông nội đô. Tuy nhiên, cho đến nay, đường Vành đai 2 hiện vẫn còn 14 km (chia làm 4 đoạn) chưa được khép kín.

Hơn 2 km thuộc vành đai 2 hoen gỉ, hoang tàn sau 6 năm dang dở

Phương Ngân - Anh Tú |

TP Hồ Chí Minh - Một đoạn Vành đai 2 dài 2,7 km từ đường Phạm Văn Đồng đến nút giao thông Gò Dưa đã triển khai từ 6 năm trước nhưng đến nay vẫn nằm dang dở, nhiều vật liệu tại công trình hoen gỉ.