HCMC risks breaking the schedule for the Metro line worth over 2 billion USD connecting 6 districts

MINH QUÂN |

HCMC - Metro Line 2 (Ben Thanh - Tham Luong) is more than 11km long, passing through 6 districts 1, 3, 10, 12, Tan Binh and Tan Phu, facing the risk of missing the start date at the end of 2025.

According to the plan of the Ho Chi Minh City People's Committee, Metro Line 2 project will be issued an order to start construction at the end of 2025.

However, according to the latest report of the Ho Chi Minh City Urban Railway Management Board (MAUR), up to now, a series of important tasks are behind schedule.

MAUR said that the adjustment of the volume and package prices of some consulting contracts in the project was expected to be completed on March 22, 2025, but by May 30, 2025, it was still not completed - 69 days late compared to the deadline assigned by the Ho Chi Minh City People's Committee.

Similarly, the procedures for approving additional contractor selection plans include: Consulting on the preparation of the adjusted feasibility study report, FEED design and bidding; the bidding package for the consulting on the appraisal of reports; general legal consultation for the project; construction survey supervision consultation is also 61 days behind schedule.

The appraisal of the bidding package's estimate dossier "Consulting on the preparation of the feasibility study report for adjustment, FEED design and bidding" was 51 days behind schedule.

Proposing specific mechanisms, especially according to Resolution No. 188 of the National Assembly, along with detailed implementation progress and orientation for appointing consultants and EPC contractors for Metro Line 2 that were expected to be completed before March 31, 2025, but have not yet been completed.

MAUR said that the above issues have been reported to the Ho Chi Minh City People's Committee and consulted with relevant departments and branches. To speed up the progress, MAUR recommends that the Department of Finance and the Department of Construction promptly give opinions, synthesize and advise the Ho Chi Minh City People's Committee.

hoi canh Metro so 2 doan di ngam qua cong vien Le Thi Rieng (Quan 10, TPHCM). Ảnh: MAUR
Perspective of Metro Line 2 underground section through Le Thi Rieng Park (District 10, Ho Chi Minh City). Photo: MAUR

Another major bottleneck that puts Metro Line 2 at risk of missing the deadline is the failure to complete procedures to stop using ODA capital and foreign preferential loans.

Loans from 3 international partners including the Asian Development Bank (ADB), the German reconstruction Bank (KfW), and the European Investment Bank (EIB) have all expired due to the project's progress being delayed for many years.

Therefore, it is necessary to carry out procedures to stop using ODA capital and foreign preferential loans for the project, and at the same time adjust it to use public investment capital to implement according to Resolution No. 188 of the National Assembly.

According to the roadmap set by the Ho Chi Minh City People's Committee, important milestones for the Metro No. 2 project in 2025 include: completing the survey and completing the overall design (FEED) in June; appraisal of the pre-feasibility study report in August and submitting it to the Ho Chi Minh City People's Committee for approval in September.

The contractor selection work is expected to take place in October to officially start construction in December. However, with the current situation, the risk of progress failure is very clear.

Metro No. 2 is over 11km long, running through 6 districts: 1, 3, 10, 12, Tan Binh, Tan Phu, playing a role in connecting the central area of Ho Chi Minh City with the Northwest direction, contributing to relieving traffic pressure on key axes such as Cach Mang Thang Tam, Truong Chinh, Cong Hoa...

The project was approved in 2010 with an initial total investment of about 1.3 billion USD (equivalent to 26,000 billion VND). By 2019, after adjustment, the total capital increased to more than 2 billion USD (equivalent to 47,900 billion VND).

This is the second metro line of Ho Chi Minh City after Metro Line 1 (Ben Thanh - Suoi Tien) which was put into commercial operation at the end of 2024.

MINH QUÂN
TIN LIÊN QUAN

Ho Chi Minh City Party Committee concludes about Metro Line 2 passing through 6 districts

|

The Ho Chi Minh City Party Committee basically agreed on the policy of using budget capital to implement Metro Line 2 (Ben Thanh - Tham Luong), instead of ODA capital as planned.

Seen from above, Metro No. 2 ground is clear

|

HCMC - The site clearance work for Metro Line 2 has reached nearly 100%. The final items are being urgently completed, ready to start construction at the end of 2025.

Metro No. 2 in Ho Chi Minh City will start construction at the end of 2025 after 15 years of waiting

|

Ho Chi Minh City plans to issue an order to start construction of Metro Line 2 (Ben Thanh - Tham Luong) in December 2025.

Impressed by the performance of real bullet shots, anti-terrorism in Ho Chi Minh City

|

Ho Chi Minh City - The special performances of the People's Public Security force were admired and praised by many people in Ho Chi Minh City.

AEON discovers accounting errors before buying back PTFs, requests to cancel contracts with SeABank

|

AEON Financial Services said that it had discovered fraud in PTF accounting data before the time of signing the contract.

Police "sitting on fire" when universities abandoned admission for grade C00

|

With only 20 days left until the 2025 high school exam officially takes place, many universities have abandoned the C00 admission process, causing students in Hanoi to "not be able to keep up".

Disciplinary action to expel former Vice Chairman of Dong Nai and former Vice Chairman of Hau Giang People's Council from the Party

|

The Secretariat decided to take disciplinary action by expelling from the Party Mr. Tran Ngoc Thuan, Vo Van Chanh, Nguyen Van Tien.

detecting a series of violations in Sacombank Da Nang's credit activities

|

Sacombank Da Nang was discovered to have committed a series of violations in credit activities, using capital for the wrong purpose and not closely monitoring cash flow...

Ho Chi Minh City Party Committee concludes about Metro Line 2 passing through 6 districts

MINH QUÂN |

The Ho Chi Minh City Party Committee basically agreed on the policy of using budget capital to implement Metro Line 2 (Ben Thanh - Tham Luong), instead of ODA capital as planned.

Seen from above, Metro No. 2 ground is clear

Anh Tú |

HCMC - The site clearance work for Metro Line 2 has reached nearly 100%. The final items are being urgently completed, ready to start construction at the end of 2025.

Metro No. 2 in Ho Chi Minh City will start construction at the end of 2025 after 15 years of waiting

MINH QUÂN |

Ho Chi Minh City plans to issue an order to start construction of Metro Line 2 (Ben Thanh - Tham Luong) in December 2025.