On the construction site of the 692 billion VND road connecting 2 expressways in Phu Tho

Tô Công |

Phu Tho - 3 construction teams are being deployed at the construction site of the Noi Bai - Lao Cai Expressway Construction Investment Project with Tuyen Quang - Phu Tho Expressway.

The Noi Bai - Lao Cai Expressway Connection Investment Project with Tuyen Quang - Phu Tho Expressway was approved in Decision No. 699/QD-BGTVT dated June 4, 2024 of the Ministry of Transport (now the Ministry of Construction).

This project has a total investment of more than 692 billion VND, the Department of Transport of Phu Tho province (now the Department of Construction) is assigned as the project investor. Of which, the value of the construction package is nearly 468 billion VND, the construction unit is Tu Lap Construction Company Limited (from mid-February 2025).

Du an ket noi tu diem cuoi cao toc Tuyen Quang - Phu Tho voi Nut giao IC9 cao toc Noi Bai - Lao Cai. Anh: To Cong.
The project connects from the end point of Tuyen Quang - Phu Tho Expressway to the IC9 Intersection of Noi Bai - Lao Cai Expressway. Photo: To Cong

According to the reporter of Lao Dong Newspaper in early June, along the Ho Chi Minh road section passing through Ha Loc commune, Phu Ho commune of Phu Tho town, many equipment, vehicles, and raw materials have been brought to the construction site of this project.

The underpasses with large volumes of reinforced concrete have been built into shape, the roadbed is being dug, and the precast components have been gathered at the construction site...

Nhieu phuong tien, thiet bi dang thi cong ham chui. Anh: To Cong.
Many vehicles and equipment are constructing the underpass. Photo: To Cong

With the construction of the current Ho Chi Minh road surface with a lot of means of transportation, the construction unit has arranged fences, lights and dense warning signs with 5 workers in charge of ensuring traffic safety.

There have been 3 construction teams deployed: Gate 1: Construction of underpass items, precast structures (1 technical officer, 40 workers); Gate 2: Construction of the DT.115B Intersection Overpass item (1 technical officer, 10 workers); Gate 3: Construction of road items (2 technical officers, 15 workers).

3 mui thi cong duoc trien khai tai cong truong du an. Anh: To Cong.
3 construction teams are deployed at the project site. Photo: To Cong

According to the design, the project to invest in the route connecting Noi Bai - Lao Cai Expressway with Tuyen Quang - Phu Tho Expressway will build a main route connecting the two expressways with a total length of over 2.73 km, including 4 lanes, with the design of the A1 elevated road surface made of asphalt concrete.

Along with that, the project will build a system of service roads and return roads to connect the local traffic system and bridges, underpasses on a number of level crossings, intersections at other intersection levels...

According to the report of the Phu Tho Provincial Construction Investment Project Management Board (project management unit), the construction work to date has reached a value of about VND 27,102/467.731 billion, the completed volume focuses on works such as: excavation, bamboo pile construction, underpass, precast components... basically meeting progress.

Rao chan, den, bien canh bao duoc bo tri day dac ngan cach duong Ho Chi Minh va du an. Anh: To Cong.
Barriers, lights, and warning signs are densely arranged to separate Ho Chi Minh Road and the project. Photo: To Cong.

Regarding disbursement, the project has so far disbursed 137.376/692.565 billion VND (19.84%), of which: Consulting cost 11.33 billion VND; construction cost 126 billion VND; other costs; 0.046 billion VND.

Regarding site clearance, the total recovered land area is 3.31 hectares, the total number of affected households is expected to be 188 households. Up to now, in Ha Loc commune (3.2 ha), land, crops, trees and architectural objects on the land have been inventoried for 149/166 households, in Phu Ho commune (0.11 ha) there are 16/22 households.

When put into use, the project will help reduce the load on the Ho Chi Minh route, reduce traffic accidents, improve exploitation capacity and investment efficiency of the two main expressways, contributing to promoting socio-economic development.

Tô Công
RELATED NEWS

Construction overnight on Quang Ngai - Hoai Nhon Expressway

|

To ensure the Quang Ngai - Hoai Nhon expressway opens to traffic by the end of 2025, contractors are reducing their efforts to work overtime, working day and night.

Speeding up progress, Central Expressway expected to finish on time

|

Binh Dinh - The Permanent Deputy Prime Minister requested investors and contractors to speed up the progress, bringing the national transport project to the finish line on time.

VEC speaks out about the Noi Bai - Lao Cai expressway asphalt paving contractor in the rain

|

Vietnam Expressway Corporation (VEC) said that the contractor will remove the asphalt section of the Noi Bai - Lao Cai Expressway.

Hanoi sinks in air pollution, risk of respiratory diseases increases

|

Hanoi is experiencing serious air pollution, increasing the risk of respiratory diseases, cardiovascular diseases, stroke and comprehensively affecting health.

Artist Thuong Tin passes away at the age of 69

|

Artist Thuong Tin passed away in the early morning of December 9 in Khanh Hoa, at the age of 69.

Bruno Fernandes scored twice, Man United beat Wolves impressively

|

In the early morning of December 9 (Vietnam time), Man United won an impressive 4-1 victory over Wolves in the Premier League.

Conservation of rare Hong Hoang individuals in Phong Nha - Ke Bang

|

Quang Tri - Rare Hong Hoang individuals are being rescued and cared for to continue their journey to return to nature in Phong Nha - Ke Bang.

Gold price update on the morning of December 9: Decreased due to selling pressure

|

Gold price update on the morning of December 9: World gold prices reversed and decreased last night. Domestic gold may decrease accordingly in today's trading session.

Construction overnight on Quang Ngai - Hoai Nhon Expressway

VIÊN NGUYỄN |

To ensure the Quang Ngai - Hoai Nhon expressway opens to traffic by the end of 2025, contractors are reducing their efforts to work overtime, working day and night.

Speeding up progress, Central Expressway expected to finish on time

Hoài Phương |

Binh Dinh - The Permanent Deputy Prime Minister requested investors and contractors to speed up the progress, bringing the national transport project to the finish line on time.

VEC speaks out about the Noi Bai - Lao Cai expressway asphalt paving contractor in the rain

Nhóm PV |

Vietnam Expressway Corporation (VEC) said that the contractor will remove the asphalt section of the Noi Bai - Lao Cai Expressway.