Permanent Deputy Prime Minister Nguyen Hoa Binh inspects the Quy Nhon - Chi Thanh expressway section

Hoài Luân |

Binh Dinh - Deputy Prime Minister Nguyen Hoa Binh inspected the actual progress of the Quy Nhon - Chi Thanh Component Project.

On the afternoon of 6.6, in Binh Dinh province, Member of the Politburo, Standing Deputy Prime Minister Nguyen Hoa Binh checked the actual progress of the component project of Quy Nhon - Chi Thanh. At the same time, listening to the progress of Hoa Lien - Tuy Loan, Quang Ngai - Hoai Nhon - Quy Nhon - Quy Nhon highway project under the North -South Expressway Construction Project in the East period 2021 - 2025.

According to the investor's report, the Quy Nhon - Chi Thanh project is 61.7 km long, passing through Binh Dinh province 19.6 km, Phu Yen province 42.1 km.

The completion progress is according to the contract in December 2025 and it is expected to shorten the basic completion time to September 2025. The parties are striving to complete the entire project before September 30.

Pho Thu tuong Thuong truc Nguyen Hoa Binh tham, tang qua dong vien cong nhan lao dong lam viec tai cong truong Du an thanh phan Quy Nhon - Chi Thanh qua tinh Binh Dinh. Anh: Thanh Thanh
Permanent Deputy Prime Minister Nguyen Hoa Binh visited and presented gifts to encourage workers working at the construction site of the Quy Nhon - Chi Thanh Component Project through Binh Dinh province. Photo: Thanh Thanh

Permanent Deputy Prime Minister Nguyen Hoa Binh inspected the actual construction of Son Trieu tunnel and the section under the Project.

At the construction site, contractors are organizing 78 construction teams, mobilizing 903 vehicles and 237 engineers and 2,320 workers. To date, the accumulated construction output has reached VND 7,739/10,178 billion, equivalent to 76.04% of the contract value.

In particular, the Son Trieu tunnel project has completed the construction of both tunnels, reaching 100%, the units are implementing the completion of equipment, lighting, roadbed and operator.

Current difficulties include 3 construction packages, so far, the construction output has reached 76.04%, about 0.86% behind the basic plan. Currently, the Quang Ngai - Hoai Nhon expressway component project still has some points that have not been handed over the site...

Permanent Deputy Prime Minister Nguyen Hoa Binh requested contractors to strictly control the quality of the project. For difficult terrain locations, we must also try harder and speed up the progress.

"There is a requirement to do it quickly but not ignore any technical process, ensuring quality" - Permanent Deputy Prime Minister Nguyen Hoa Binh emphasized.

Visiting workers directly working at the Quy Nhon - Chi Thanh Expressway construction site, Permanent Deputy Prime Minister Nguyen Hoa Binh requested that construction units pay attention and encourage the brothers according to the Prime Minister's instructions, working day and night, working 3 shifts, 4 teams.

Hoài Luân
TIN LIÊN QUAN

Permanent Deputy Prime Minister receives new duties

|

Deputy Prime Minister Nguyen Hoa Binh is the Head of the Central Steering Committee for national target programs for the period 2021 - 2025.

Expressway is littered with land, Deputy Prime Minister requests to run at full speed to the finish line in 2025

|

Lang Son - Deputy Prime Minister Bui Thanh Son has issued drastic requirements on the progress of key expressway projects in the North.

The Deputy Prime Minister requested an inspection of the selection of bidding packages after the reflection of Son Hai Group

|

Deputy Prime Minister Tran Hong Ha has just requested the establishment of an inter-Ministryal Working Group to conduct an inspection of the selection of contractors for the expressway project package.

Mr. Nguyen Van Tho is assigned to be the Standing Vice Chairman of the Ho Chi Minh City People's Committee

|

HCMC - Mr. Nguyen Van Tho was assigned to hold the position of Permanent Vice Chairman of the HCMC People's Committee.

Benchmark scores for grade 10 admission to 4 specialized schools in Hanoi in 2025

|

The benchmark score for grade 10 of 4 high schools for the 2025-2026 school year has been announced by the Hanoi Department of Education and Training.

Ms. Paetongtarn begins her first day of work in her new position

|

On July 4, Ms. Paetongtarn Shinawatra began her first working day as Minister of Culture after being suspended from the position of Prime Minister of Thailand.

List and codes of 34 provinces and cities, 3,321 new commune-level administrative units

|

The decision stipulates the list and codes of Vietnamese administrative units including 34 provinces and cities used uniformly nationwide from July 1, 2025.

AFC denies Malaysia's investigation into naturalized players

|

The Asian Football Confederation (AFC) has dispelled all speculation about the investigation of Malaysian football, related to the use of naturalized players.

Permanent Deputy Prime Minister receives new duties

ANH HUY |

Deputy Prime Minister Nguyen Hoa Binh is the Head of the Central Steering Committee for national target programs for the period 2021 - 2025.

Expressway is littered with land, Deputy Prime Minister requests to run at full speed to the finish line in 2025

Khánh Linh |

Lang Son - Deputy Prime Minister Bui Thanh Son has issued drastic requirements on the progress of key expressway projects in the North.

The Deputy Prime Minister requested an inspection of the selection of bidding packages after the reflection of Son Hai Group

HƯƠNG NHA |

Deputy Prime Minister Tran Hong Ha has just requested the establishment of an inter-Ministryal Working Group to conduct an inspection of the selection of contractors for the expressway project package.