10-lane road in Dong Nai connecting Ho Chi Minh City under construction during the September 2nd holiday

HÀ ANH CHIẾN |

Dong Nai - The project to upgrade and expand road 25B (Ton Duc Thang road) section from the center of Nhon Trach ward to National Highway 51 is under construction throughout the September 2nd holiday.

On August 29th, in an exchange with a reporter from Lao Dong Newspaper, a representative of the Dong Nai City Construction Investment Project Management Board said that they had directed contractors to focus machinery, vehicles and personnel to continue construction throughout the September 2nd holiday to promptly bring the project to upgrade and expand road 25B (Ton Duc Thang road) section from the center of Nhon Trach ward to National Highway 51 to the finish line on schedule.

According to the Dong Nai City Construction Investment Project Management Board, the project has now completed construction and opened to traffic the main left section. Contractors are focusing on constructing the main right section, the parallel road on both sides of the main route, along with bridges, technical culverts, underpasses for people and lighting systems.

Regarding the site clearance work, there is still 2% that has not been handed over, currently the investor is drastically coordinating with local authorities and functional agencies to complete the section that is still entangled in the Hiep Phuoc intersection area (Nhon Trach ward).

Thi công xuyên lễ 2.9 trên công trường dự án nâng cấp mở rộng đường 25B (đường Tôn Đức Thắng) đoạn từ trung tâm Nhơn Trạch ra quốc lộ 51. Ảnh: HAC
Construction throughout the September 2nd holiday at the construction site of the 25B road upgrade and expansion project (Ton Duc Thang road) section from Nhon Trach center to National Highway 51. Photo: HAC

The project to upgrade and expand road 25B section from the center of Nhon Trach ward to National Highway 51 has a length of more than 9.2km, started in December 2024, with a total investment of nearly 1,500 billion VND and is being expanded to 10 lanes.

The 25B road upgrade and expansion project along with the 25C road construction project (from Huong Lo 19 to National Highway 51) are being simultaneously implemented, which are 2 projects implemented by Dong Nai to create 2 traffic axes connecting from Long Thanh airport to Ho Chi Minh City and vice versa.

According to the plan, roads 25B and 25C will connect Long Thanh airport through National Highway 51 to the Ben Luc - Long Thanh expressway, Ring Road 3 of Ho Chi Minh City, reducing the load on the Ho Chi Minh City - Long Thanh - Dau Giay expressway.

Dong Nai City People's Committee has also requested Nhon Trach and Long Thanh wards to accelerate progress and soon hand over the entire site to complete the 25B road project and put it into operation at the end of 2026.

HÀ ANH CHIẾN
RELATED NEWS

Delegate of Dong Nai People's Council proposes to prevent speculation and land exploitation

|

Dong Nai - Delegates of the People's Council of Dai Phuoc commune propose to prevent and stop speculation, price manipulation, and land exploitation.

Dong Nai considers establishing a clean land fund of 358 ha in Nhon Trach ward for auction

|

Dong Nai - The City People's Council is considering and approving a Resolution to create a clean land fund of 358 ha in Nhon Trach ward for auction.

Dong Nai counts the site of the 65.573 billion VND metro project connecting Long Thanh airport

|

Dong Nai - The Ben Thanh - Suoi Tien metro line project to the new administrative center and Long Thanh airport is being measured, marked, and land acquisition maps are being made.

More than 11km of Ring Road 3 of Ho Chi Minh City through Dong Nai to be opened to traffic in October

|

Dong Nai - More than 11km of Ho Chi Minh City Ring Road 3 project completed and opened to traffic in October 2026.

The joyful atmosphere throughout Hanoi streets, towards National Day September 2nd

|

Hanoi - These days, the Capital is wearing a brilliant coat of flags, flowers, posters... towards the 81st anniversary of National Day 2. 9.

Son Tung MTP, Hoa Minzy and how Vietnamese music attracts attention from the world

|

According to Assoc. Prof. Dr. Nguyen Huy Phuong, the success of Son Tung M-TP and Hoa Minzy is thanks to the combination of Vietnamese materials with modern music language.

Opportunity for Vietnam to become a global manufacturing center

|

FDI capital flows along with production and export growth are opening up opportunities for Vietnam to rise to become a global manufacturing center.

Overnight completion of Muong Khuong boarding school before opening

|

Lao Cai - Workers are working overnight, urgently completing the final parts at Muong Khuong boarding school before the opening day.

Delegate of Dong Nai People's Council proposes to prevent speculation and land exploitation

HÀ ANH CHIẾN |

Dong Nai - Delegates of the People's Council of Dai Phuoc commune propose to prevent and stop speculation, price manipulation, and land exploitation.

Dong Nai considers establishing a clean land fund of 358 ha in Nhon Trach ward for auction

HÀ ANH CHIẾN |

Dong Nai - The City People's Council is considering and approving a Resolution to create a clean land fund of 358 ha in Nhon Trach ward for auction.

Dong Nai counts the site of the 65.573 billion VND metro project connecting Long Thanh airport

HÀ ANH CHIẾN |

Dong Nai - The Ben Thanh - Suoi Tien metro line project to the new administrative center and Long Thanh airport is being measured, marked, and land acquisition maps are being made.

More than 11km of Ring Road 3 of Ho Chi Minh City through Dong Nai to be opened to traffic in October

HÀ ANH CHIẾN |

Dong Nai - More than 11km of Ho Chi Minh City Ring Road 3 project completed and opened to traffic in October 2026.