The Southern Ring Road project of the old Thai Binh City (now Hung Yen Province) with a total investment of more than 1,100 billion VND is urgently completing the final items to soon reach the finish line.
The project scale is more than 8km long, starting point is km59+950 National Highway 10 (in Tan Thuan commune), ending point is Chu Van intersection (in Tran Lam ward). This is a level II road; cross-section is 67m, main roadbed width is 30m; design speed is 80km/h.


Despite the harsh hot weather, the construction atmosphere at the construction site is still bustling. Because of the progress and responsibility for the project, the engineers and workers overcame the sun, worked enthusiastically, racing against time to complete the work, put the project into use soon, meeting the requirements of local economic and social development and the needs of the people.
In September, Lao Dong Newspaper reporters recorded that at the construction site of the old Southern Ring Road project of Thai Binh City, dozens of equipment and machinery were gathered with about 200 workers urgently working to urgently complete traffic safety items, install signs, signals, paint road markings, plant trees and install lighting.


Mr. Nguyen Huy Son - Construction Commander - said that these days, the weather is hot and sunny, and many solutions have been implemented at the construction site to ensure the health of workers and construction teams in the early morning and later in the evening. In addition, provide adequate drinking water, sun protection and sun protection equipment for workers to work safely in sunny weather.
According to the Hung Yen Province No. 2 Investment and Construction Project Management Board, up to now, the project has basically completed the main items such as Kien Giang Bridge, S1 overpass; the roadbed is made of crushed stone and asphalt concrete has been basically completed. The route is expected to be completed this September and put into operation in the near future.
The old Southern Ring Road project of Thai Binh City plays an important role in connecting traffic, reducing the load on National Highway 10 from Tan De Bridge to the southern area of the province and Thai Binh Economic Zone.
In addition, in order to connect with the old inner-city routes of Thai Binh City, contributing to completing the traffic network in the area; ensuring convenient travel for people; reducing the traffic volume of heavy-duty vehicles passing through the center of the old Thai Binh City. Promote economic exchanges and commodity exchanges; exploit the potential and advantages of the Southern region and neighboring areas; contribute to socio-economic development, ensure national defense and security.