Overcoming the sun and rain at key projects

NGUYỄN TRƯỜNG |

Ninh Binh - At key projects, thousands of engineers and workers are determined to "overcome the sun and rain" to complete the project on schedule.

These days, the competitive atmosphere of labor on key projects and constructions in Ninh Binh province is taking place very urgently. Investors, contractors, along with thousands of officers, engineers and workers are focusing on speeding up the progress to complete ahead of schedule.

At the construction site of the Van River overpass and the western approach road to the Van River bridge (Hoa Lu city), the construction unit is urgently completing the final items of the project such as installing the lighting system; architectural railings for the upstream check-in pedestrian section, paving the sidewalk, planting trees, etc.

Cong nhan dang hoi ha thi tuyen duong Dong - Tay doan qua dia ban huyen Nho Quan (Ninh Binh). Anh: Nguyen Truong
Workers are rushing to construct the East-West route through Nho Quan district (Ninh Binh). Photo: Nguyen Truong

"This is one of the key projects and a highlight of Ninh Binh's urban landscape. We are directing contractors to focus on accelerating the progress so that the project can be completed and put into use during the Lunar New Year 2025" - said a representative of the Ninh Binh Provincial Department of Transport.

Regarding the East-West Road Construction Investment Project in Ninh Binh Province (Phase 1), with a total length of nearly 23km, although the construction volume is very large because it passes through high mountainous terrain and low-lying areas, after more than 2 years of implementation, the important inter-regional traffic connection project of Ninh Binh Province has gradually been completed.

These days before the Lunar New Year 2025, the construction unit is mobilizing machinery and hundreds of workers to speed up the project's progress.

Mr. Pham Quoc Chinh - Director of the Ninh Binh Province Traffic Construction Investment Project Management Board (investor) said that the project is being implemented with the spirit of "eating quickly, sleeping urgently", determined and unanimous to complete the project beyond the set plan.

"We are determined to basically complete the main route to serve people's travel needs during the Lunar New Year 2025 and will complete the project to put it into operation in June 2025," said Mr. Chinh.

Anh: Nguyen Truong
With the spirit of “eating quickly and sleeping quickly”, investors, contractors and workers on key projects in Ninh Binh province are determined and united to exceed the set plan. Photo: Nguyen Truong

At many other construction projects in Ninh Binh province, the construction atmosphere is also very bustling and urgent, such as: Hoa Lu University construction investment project; Project to upgrade and expand the main road to the Kenh Ga tourist area and Van Trinh cave; Project to combine Van Hanh canal and road; Project to build a coastal road through Ninh Binh province...

In addition to urgently and accelerating the completion of projects and works in the area, Ninh Binh province is also actively completing procedures to select investors and contractors and start construction of many important projects in the early 2025 such as: Investment project to build the Ninh Binh - Hai Phong expressway, section through Ninh Binh province; Project to build a high-quality medical examination and treatment unit of Ninh Binh General Hospital; Investment project to build and renovate Ninh Binh Traditional Medicine Hospital...

NGUYỄN TRƯỜNG
RELATED NEWS

Energizing a series of key projects in the Southern provinces

|

In the last days of 2024, the southern provinces continuously energized and put into operation 110kV projects.

Dak Lak urgently disburses public investment capital for key projects

|

Currently, the disbursement of public investment capital in some key transport projects in Dak Lak province is still low, not meeting the set requirements.

Racing progress on a series of key projects in Thai Nguyen

|

Thai Nguyen - A series of key projects with a total investment of tens of thousands of billions are racing to meet progress, some projects will be completed in 2024.

Piloting the delegation of power from higher levels to the Party Committee of grassroots Party committees directly under communes and wards

|

Regulation No. 20-QD/TW has supplemented the regulation on piloting the delegation of powers from higher levels to the Party committees of grassroots Party committees directly under the Party committees of communes, wards, and special zones.

Clarify the authority to organize villages and residential groups in the draft revised Capital Law

|

National Assembly Deputy Tran Thi Nhi Ha said that it is necessary to clarify the authority to organize villages and residential groups in Article 7 of the draft Capital Law (amended).

Red River in a 100-year vision: Awakening the urban face of Hanoi in the future

|

In the Hanoi Capital Master Plan with a 100-year vision, the Red River is identified as the central landscape axis and a new symbol of the city's development.

Hungarian Prime Minister Viktor Orban loses election after 16 years in power

|

Hungarian Prime Minister Viktor Orban admitted a heavy defeat in the landmark election on April 12, ending 16 years in power.

Laborers no longer jump jobs based on feelings

|

Job hopping after the Lunar New Year is a common occurrence in the labor market. However, in the new context, many workers no longer jump jobs emotionally.

Energizing a series of key projects in the Southern provinces

Đạt Phan |

In the last days of 2024, the southern provinces continuously energized and put into operation 110kV projects.

Dak Lak urgently disburses public investment capital for key projects

BẢO TRUNG |

Currently, the disbursement of public investment capital in some key transport projects in Dak Lak province is still low, not meeting the set requirements.

Racing progress on a series of key projects in Thai Nguyen

Việt Bắc |

Thai Nguyen - A series of key projects with a total investment of tens of thousands of billions are racing to meet progress, some projects will be completed in 2024.