Racing progress on a series of key projects in Thai Nguyen

Việt Bắc |

Thai Nguyen - A series of key projects with a total investment of tens of thousands of billions are racing to meet progress, some projects will be completed in 2024.

Race for progress, finish in 2024

The Ring Road V project is 6.68km long, with a total investment of 699.3 billion VND. Construction started in 2021.

According to the Thai Nguyen Province Traffic Construction Investment Project Management Board (investor), the project has cleared 97.3% of the main route. Contractors are currently constructing the roadbed, foundation, and asphalt concrete pavement. Construction of the Main Canal Bridge and Troi Canal Bridge has reached 99% of the volume.

Hinh hai du an duong vanh dai V qua dia phan tinh Thai Nguyen sau 3 nam trien khai.
The shape of the Ring Road V project through Thai Nguyen province after 3 years of implementation.

Other items such as trees, sidewalks, lighting systems... account for 11% of the volume.

The expected disbursement in October is 70 billion VND and the disbursement of the capital plan in 2024 is 32.4%. The investor and contractors committed to completing the project before December 31.

The Thai Nguyen Provincial Stadium Construction Project started in October 2022, with a scale of 15.47 hectares. The project has a total investment of nearly 536 billion VND, investing in the construction of a new 22,000-seat stadium, roof, and 1 international standard football field.

San van dong tinh Thai Nguyen co suc chua 22.000 cho ngoi du kien hoan thanh nam 2024. Anh: Viet Bac
Thai Nguyen Provincial Stadium project with a capacity of 22,000 seats is expected to be completed in 2024. Photo: Viet Bac

Currently, the contractor has completed the structure of stands A, B, C, D and is building walls and plastering inside stands A and B. The lighting project has reached 75% of the volume. The construction unit is installing fire prevention and fighting equipment.

Removing difficulties

The project of the connecting road connecting Thai Nguyen - Bac Giang - Vinh Phuc provinces has a length of 42.55km, with a total investment of 4,204 billion VND.

According to the Thai Nguyen Province Traffic Construction Investment Project Management Board, the compensation and site clearance work has reached 99.68% and is expected to be completed in October. Currently, contractors are focusing on completing the roadbed, road foundation, and asphalt concrete surface. Construction of 3 large bridges has reached 52.8% of the volume, while the drainage system and other items have reached 85% of the volume.

Regarding the disbursement of the capital plan in 2024, it reached over 33%, equivalent to nearly 387.3 billion VND. The expected disbursement in October is 200 billion VND.

Du an xay dung Tru so lam viec Khoi cac co quan tinh Thai Nguyen toa lac tai phuong Trung Vuong. Anh: Viet Bac
Project to build the Headquarters of the Thai Nguyen Provincial Agencies Block located in Trung Vuong Ward. Photo: Viet Bac

The project to build the Thai Nguyen Provincial Office Headquarters has a scale of 12 floors, with a total investment of 405 billion VND. The project started in June 2023 in Trung Vuong ward on an area of ​​15,000m2, with a total floor area of ​​nearly 29,000m2.

According to the investor's report, the project's rough construction is 96% complete. Contractors are speeding up the completion of the surrounding walls and floor partitions, interior and exterior plastering. Construction of power supply, fire protection, and transformer stations.

Recently, when checking the progress of key projects and works in the locality, Mr. Trinh Viet Hung - Secretary of Thai Nguyen Provincial Party Committee requested departments, branches and localities to coordinate with investors to promptly remove difficulties, ensuring the progress and quality of the works.

The Ring Road V project must be urgently completed before December 31. The Thai Nguyen Provincial Stadium construction project will be completed in 2024.

Việt Bắc
RELATED NEWS

The final stretch on the billion-dollar route through Thai Nguyen

|

The 6.68km-long Ring Road V project in Phu Binh district, Thai Nguyen province, after 3 years of construction, is now in the final stage.

The shape of the bridge connecting Thai Nguyen - Hanoi after 2 years of construction

|

After more than 2 years of implementation, the new Da Phuc bridge project, the bridge connecting Thai Nguyen with Hanoi, has been basically completed and is expected to be completed in 2024.

After the case of a teacher punishing a student with a syringe, the Principal requested a job transfer

|

Ho Chi Minh City - After the incident of a teacher punishing a student for self-injecting a needle into his hand, the Principal self-criticized in front of the School Council and requested a job transfer.

Gas stations in Ho Chi Minh City are ready to sell E10 gasoline

|

From May 15, gas stations in Ho Chi Minh City began switching from RON 95-V gasoline to E10 gasoline.

Instructions on switching from old gasoline cars to electric cars at Green Transit Day 2026

|

On Green Transformation Day 2026, people can bring old gasoline cars to participate in the "gasoline to electricity exchange" program and directly experience new electric vehicle lines.

Draft Report of the Executive Committee of the Vietnam General Confederation of Labor (XIII term) at the XIV Congress of the Vietnam Trade Union, term 2026 - 2031

|

Building a comprehensively strong Vietnam Trade Union; focusing on representing, caring for, and protecting union members and workers; promoting the pioneering role, spirit of innovation and creativity, contributing to realizing the aspiration to build a rich, prosperous, civilized, and happy country.

The final stretch on the billion-dollar route through Thai Nguyen

Nguyễn Hoàn |

The 6.68km-long Ring Road V project in Phu Binh district, Thai Nguyen province, after 3 years of construction, is now in the final stage.

The shape of the bridge connecting Thai Nguyen - Hanoi after 2 years of construction

Nguyễn Hoàn |

After more than 2 years of implementation, the new Da Phuc bridge project, the bridge connecting Thai Nguyen with Hanoi, has been basically completed and is expected to be completed in 2024.

Loạt công trình trọng điểm tại Thái Nguyên về đích năm 2024

Việt Bắc |

Loạt công trình trọng điểm tại Thái Nguyên với tổng mức đầu tư hàng nghìn tỉ đồng đang được đẩy nhanh tiến độ để kịp về đích cuối năm 2024.