Consider adjusting the progress for the slow-progressing wind power project in Quang Tri

HƯNG THƠ |

Quang Tri - Huong Linh 5 Wind Power Plant project is behind schedule but the investor has paid a deposit to ensure the project, so the locality is considering adjusting the project implementation schedule.

On October 27, a source from Lao Dong Newspaper said that the authorities of Quang Tri province are considering adjusting the implementation progress of the slow-progressing project, Huong Linh 5 Wind Power Plant.

Accordingly, on September 24, 2025, the investor of the Huong Linh 5 Wind Power Plant project paid a deposit of more than 13.2 billion VND to ensure the project's implementation. After depositing, the project investor submitted a dossier to adjust the project's investment policy.

Currently, Quang Tri province is considering adjusting the investment policy of the above project.

In addition to the Huong Linh 5 wind power project being behind schedule, the Huong Hiep 2 and Huong Hiep 3 wind power plant projects (both owners are BB Group Joint Stock Company) are also behind schedule and have not yet made an investment guarantee deposit.

Most recently, on October 2, 2025, the Department of Finance of Quang Tri province sent a document to the investors of the two wind power projects above regarding the deposit to ensure project implementation. After that, BB Group Joint Stock Company committed to making a deposit to ensure the implementation of the Huong Hiep 2 and Huong Hiep 3 Wind Power projects in the fourth quarter of 2025.

Previously, the People's Committee of Quang Tri province held a meeting to resolve the proposals of investors related to 3 wind power projects: Huong Linh 5, Huong Hiep 2 and Huong Hiep 3. The People's Committee of Quang Tri province determined that the above 3 wind power projects were slow to implement, violating the obligation to pay deposits to ensure investment and progress. The investor has not yet completed the dossier, not implemented it on site and has not fulfilled its financial obligations as committed.

Faced with that situation, the Provincial People's Committee agreed to consider extending the progress for investors only if they meet 3 mandatory conditions: to fully deposit the investment guarantee; have a clear commitment on the implementation progress; ensure the legality of legal status, work with localities to update land use needs in the planning.

Previously, the Department of Planning and Investment of Quang Tri province (now the Department of Finance of the province) also drew up a record of violations and imposed administrative penalties on projects that were behind schedule and had violations. The projects that have complied with the fines with a total amount of 180 million VND are Huong Linh 5, Huong Hiep 2 and Huong Hiep 3 projects.

HƯNG THƠ
RELATED NEWS

The Ministry of Agriculture and Environment responds to regulations on reclaiming residential land and agricultural land for wind power

|

The Ministry of Agriculture and Environment has just responded to citizens, the regulation on reclaiming residential land and agricultural land for wind power must change the purpose of land use?

Deadline for slow-progressing wind power projects in Quang Tri province

|

Quang Tri - The Provincial People's Committee requires wind power projects with delayed progress to pay investment deposits before July 31, 2025 if they want to be considered for an extension.

Wind power project behind schedule, no investment guarantee deposit

|

Quang Tri - Of the 8 wind power projects under investment, 4 projects are behind schedule, and one project has not yet deposited an investment guarantee.

D'ran Pass connecting Da Lat with Phan Rang is seriously eroded and cracked

|

Lam Dong - Prolonged heavy rain caused landslides from the positive slope down to D'ran Pass, causing cracks in the roadbed, obstructing traffic.

The Vietnam General Confederation of Labor works with the German Social Democratic Party Delegation

|

Hanoi - On the afternoon of October 28, the Vietnam General Confederation of Labor worked with the German Social Democratic Party Delegation. The issue of concern to both sides is dialogue and negotiation.

Phu Tho has a new Chairman of the Provincial People's Council

|

Phu Tho - Mr. Bui Duc Hinh has just been elected to hold the position of Chairman of the People's Council of Phu Tho province, term XIX, 2021 - 2026.

Gold prices plummet, reaching a three-week low

|

Gold prices fell to a three-week low as expectations of a US-China trade deal reduced safe-haven demand.

Floodwaters surround Hue City, tourists get on boats to flee the flood

|

HUE - Many tourists coming to Hue during the historic flood had to rent boats, carry their luggage and seek shelter.

The Ministry of Agriculture and Environment responds to regulations on reclaiming residential land and agricultural land for wind power

Xuyên Đông |

The Ministry of Agriculture and Environment has just responded to citizens, the regulation on reclaiming residential land and agricultural land for wind power must change the purpose of land use?

Deadline for slow-progressing wind power projects in Quang Tri province

HƯNG THƠ |

Quang Tri - The Provincial People's Committee requires wind power projects with delayed progress to pay investment deposits before July 31, 2025 if they want to be considered for an extension.

Wind power project behind schedule, no investment guarantee deposit

HƯNG THƠ |

Quang Tri - Of the 8 wind power projects under investment, 4 projects are behind schedule, and one project has not yet deposited an investment guarantee.