Compensation of VND2,766 billion to clear land for the Ho Chi Minh City expressway connecting Dong Nai

ĐÌNH TRỌNG |

HCMC - The authorities have approved compensation of VND2,766 billion to clear the land for the HCMC - Thu Dau Mot - Chon Thanh expressway.

On October 20, according to the Ho Chi Minh City People's Committee, localities are urgently implementing site clearance to build the Ho Chi Minh City - Thu Dau Mot - Chon Thanh expressway project.

The project has a site clearance length of 45.7 km, the reclaimed land area is 344.1 ha. The project affects 1,609 households, individuals and organizations. It is expected to resettle 252 cases.

Up to now, the units have issued notices of land recovery to related cases. Measurement was conducted on 1,605 cases (reaching 99.7%), drawings were assessed on 1,601 cases (reaching 99.5%), and 1,514 cases were counted (reaching 94%).

Notably, the units have approved compensation, support and resettlement plans for 788 cases with an amount of VND 2,766 billion (49%).

Moc boi thuong giai phong mat bang lam cao toc TPHCM - Thu Dau Mot - Chon Thanh. Anh: Dinh Trong
Currently, compensation of VND 2,766 billion has been approved for 788 cases. Photo: Dinh Trong

Currently, there have been 318 cases of site handover with an area of 136.25 hectares (reaching 40% of the total area expected to be reclaimed).

According to the Ho Chi Minh City People's Committee, in 2025, the capital disbursement plan for the project's compensation and resettlement support is VND 8,000 billion. Up to now, VND2,766 billion in compensation has been disbursed (reaching a rate of 35% compared to the assigned capital plan).

The Ho Chi Minh City People's Committee has directed the Land Fund Development Center and the People's Committees of communes and wards to speed up the progress of site clearance. Complete compensation and site clearance in December 2025.

Co
There are 318 cases of site handover. Photo: Dinh Trong

The project passes through 9 communes and wards of Ho Chi Minh City

The Ho Chi Minh City - Thu Dau Mot - Chon Thanh Expressway project passes through 4 districts of the former Binh Duong province. After merging Binh Duong with Ho Chi Minh City, it was determined that the project will pass through 9 communes including: Tan Khanh, Tan Hiep, Vinh Tan, Binh Duong, Binh Co, Phuoc Hoa, An Long, Chanh Phu Hoa, Bau Bang. The project starts at Tan Khanh ward, the end point is Bau Bang commune connecting to Chon Thanh ward, Dong Nai province (formerly Chon Thanh town, Binh Phuoc province).

ĐÌNH TRỌNG
RELATED NEWS

51 households receive compensation for an industrial park project worth over VND8,000 billion in Hai Phong

|

Hai Phong - An Truong Commune has just paid compensation and site clearance for the Trang Due 3 Industrial Park Project.

finalizing the groundbreaking date for the project to expand the road connecting Ho Chi Minh City - Long Thanh - Dau Giay Expressway

|

HCMC - The project to expand the HCMC - Long Thanh - Dau Giay expressway will officially start construction at the end of October 2025.

Dong Nai will announce land reclamation for the expansion of the Ho Chi Minh City - Long Thanh expressway in October

|

Dong Nai - The Provincial People's Committee requested a meeting of the people, issue a notice of land acquisition and count the Ho Chi Minh City - Long Thanh expressway expansion project to be completed in October 2025.

Workshop "Promoting self-respect and full tax contributions - Building a strong era"

|

Improving tax compliance is not only a technical task, but a step forward in cultural development and trust between the State and citizens.

A good doctor is to consider patients as teachers

|

The Deputy Minister of Health said that good doctors must examine patients, study them, consider patients as teachers, the greatest book of his life.

Quang Tri has heavy rain before the wedding of Miss Do Thi Ha and the young master of Son Hai Group

|

The wedding of Miss Do Thi Ha and the young master of Son Hai Group is taking place in Quang Tri. Heavy rain with winds as storm No. 12 is approaching.

Minister Nguyen Kim Son talks about the roadmap to build a shared textbook set

|

Minister Nguyen Kim Son said that it is expected that in November the Ministry will complete the plan to build a shared textbook set and submit it to the Government for approval.

Thailand investigates new link suspected of involving Cambodian scam leader Chen Zhi

|

Thailand has officially opened an investigation into Prince International - a business suspected of being involved in the network of Cambodian scammer Chen Zhi.

51 households receive compensation for an industrial park project worth over VND8,000 billion in Hai Phong

Hoàng Khôi |

Hai Phong - An Truong Commune has just paid compensation and site clearance for the Trang Due 3 Industrial Park Project.

finalizing the groundbreaking date for the project to expand the road connecting Ho Chi Minh City - Long Thanh - Dau Giay Expressway

Minh Tâm |

HCMC - The project to expand the HCMC - Long Thanh - Dau Giay expressway will officially start construction at the end of October 2025.

Dong Nai will announce land reclamation for the expansion of the Ho Chi Minh City - Long Thanh expressway in October

HÀ ANH CHIẾN |

Dong Nai - The Provincial People's Committee requested a meeting of the people, issue a notice of land acquisition and count the Ho Chi Minh City - Long Thanh expressway expansion project to be completed in October 2025.