Speed up the site clearance progress of 2 projects on DT 744 road in Ho Chi Minh City

ĐÌNH TRỌNG |

HCMC - Localities are speeding up site clearance to construct the drainage project and upgrade and expand DT 744.

According to the Ho Chi Minh City People's Committee, currently, on DT 744 road, 2 projects are being implemented including the construction of a drainage system and upgrading and expanding DT 744 (from km 12+000 to km 32+000).

In particular, a drainage system will be built on DT 744 passing through Phu An ward and Tay Nam ward. When implementing the project, there were 169 cases affected with a reclaimed area of about 0.97ha.

Up to now, the units have completed the notice of land recovery and measurement. The counting work has been carried out on 161/169 cases, reaching 95%; compensation plans have been approved for 78 cases with an amount of 39.1 billion VND, reaching 46.15%. There have been 52 cases of site handover with a reclaimed area of 0.484 hectares, reaching 49.9%.

Doan dang thuc hien du an
The section is implementing a project to build a drainage system on DT 744. Photo: Dinh Trong

For the project to upgrade and expand DT 744 (from km 12+000 to km 32+000), site clearance will also be carried out in the section passing through Phu An ward and Tay Nam ward. When implementing the project, 848 affected cases had to be compensated about 835 billion VND to reclaim the site.

To date, 530 cases have been measured. The Compensation Council approved a draft compensation and support plan for 309 cases with an amount of 65.3 billion VND.

Phu An ward and Tay Nam ward are focusing on mobilizing people to agree to receive compensation and hand over the site. The leaders of the Ho Chi Minh City People's Committee requested the two wards and related units to complete compensation and site clearance for the project in November 2025.

Tuyen duong bi hu hong gay nguy hiem cho nguoi tham gia giao thong.Anh: Dinh Trong
The road is damaged, causing danger to road users. Photo: Dinh Trong

According to the reporter's records, due to the lack of land, construction projects have been sluggish for the past 2 years. Meanwhile, DT 744 road is degraded, some sections are damaged, and have deep holes, posing a danger to road users.

Tren duong xuat hien cac ho sau. Anh: Dinh Trong
Deep holes appeared on the road. Photo: Dinh Trong
ĐÌNH TRỌNG
RELATED NEWS

HCMC speeds up the progress of land acquisition of 1,553 households to build a belt road

|

HCMC - The competent authorities of the HCMC People's Committee are speeding up the progress of land acquisition for 1,553 households to build the HCMC Ring Road 4.

Approving compensation of VND744 billion for site clearance for the 2.5km road expansion project in Ho Chi Minh City

|

HCMC - The authorities have approved compensation of VND744 billion to reclaim the site for a 2.5-km project in Tan Khanh ward, An Phu ward, HCMC.

Urgently mobilize site clearance for the VND5,892 billion project in Ho Chi Minh City

|

HCMC - Units are urgently mobilizing site clearance to get clean land for units constructing the Suoi Cai reinforced dredging project.

Russian plane carries 29 tons of emergency relief goods for people in flooded areas of Hue

|

On the morning of October 30, at Noi Bai airport (Hanoi), a Russian private plane landed, carrying 29 tons of emergency aid to the people of Hue city

Accelerate waste-to-energy projects to end the situation of waste being left behind

|

Ninh Binh - With a large amount of waste remaining, causing environmental pollution, Ninh Binh province is directing to speed up the progress of waste treatment projects to end the above situation.

Forecast of the risk of 2-3 typhoons near the East Sea in November

|

The low pressure is forecast to strengthen into a storm in early November, and there may be 2-3 storms near the East Sea throughout the month.

Floodwaters have flooded, farmer's tractor has turned into a special rescue vehicle

|

Quang Tri - The whole commune was flooded with immense floodwaters, some families were flooded, some went to the hospital to need support, Mr. Phung was there. The tractor is often a means of livelihood, now becoming a special rescue vehicle when floods come.

Fed cuts interest rates to deal with unstable economy

|

Amid the US government's closure and lack of economic data, the Fed has decided to cut interest rates despite internal division.

HCMC speeds up the progress of land acquisition of 1,553 households to build a belt road

ĐÌNH TRỌNG |

HCMC - The competent authorities of the HCMC People's Committee are speeding up the progress of land acquisition for 1,553 households to build the HCMC Ring Road 4.

Approving compensation of VND744 billion for site clearance for the 2.5km road expansion project in Ho Chi Minh City

ĐÌNH TRỌNG |

HCMC - The authorities have approved compensation of VND744 billion to reclaim the site for a 2.5-km project in Tan Khanh ward, An Phu ward, HCMC.

Urgently mobilize site clearance for the VND5,892 billion project in Ho Chi Minh City

ĐÌNH TRỌNG |

HCMC - Units are urgently mobilizing site clearance to get clean land for units constructing the Suoi Cai reinforced dredging project.