Proposal to remove obstacles for 1,533 real estate projects

CAO NGUYÊN |

To continue handling 1,533 real estate projects facing difficulties nationwide, according to experts, it is necessary to continue to synchronize and unify legal regulations.

Resolution 170/2024/QH15 of the National Assembly and Decree 76/2025/ND-CP of the Government have removed a series of "shelved" projects. However, in reality, according to data reported by the Ho Chi Minh City Real Estate Association (HoREA), there are currently 1,533 real estate projects facing difficulties nationwide.

Sharing with Lao Dong reporter, Mr. Le Hoang Chau - Chairman of HoREA - said that it is necessary to continue to synchronize and unify legal regulations so that all of these projects are treated equally.

According to Mr. Le Hoang Chau, for the first time the National Assembly has issued "specific mechanisms and policies" to serve as a basis for handling and removing difficulties and obstacles for 64 specific projects in the conclusions of inspections, examinations and judgments in Ho Chi Minh City, Da Nang City and Khanh Hoa Province.

Thereby, creating conditions for the final handling of 49 projects in Da Nang city (accounting for 77% of the total number of projects) and 11 projects in Khanh Hoa province (accounting for 17% of the total number of projects) and 4 projects in Ho Chi Minh City (accounting for 6%).

This has created conditions for restarting 64 projects that have been "shelved" for decades, which will have a positive impact on the socio-economic and investment and business environment of the locality.

This expert added that not only Resolution 170/2024/QH15 but also Decree 76/2025/ND-CP has allowed that after reviewing, meeting the conditions, and fully fulfilling financial obligations to the State, investors can restart these 64 "covered" projects.

At the same time, continue to carry out investment procedures for construction and business, both ensuring the legitimate and legal rights and interests of investors and secondary investors, customers, and home buyers, both overcoming the situation of "waste" of land and ensuring the state budget "collects correctly and fully", not causing loss or loss.

According to Mr. Chau, not only 64 projects in Da Nang, Khanh Hoa, Ho Chi Minh City but also many other localities have similar projects that need to be resolved.

To remove difficulties for 1,533 real estate projects nationwide, Mr. Le Hoang Chau suggested that the Ministry of Agriculture and Environment consider proposing that the Prime Minister submit to the National Assembly to consider expanding the scope of regulation of Resolution No. 170/2024/QH15.

Accordingly, Resolution No. 170/2024/QH15 is allowed to apply similarly to all similar projects in all provinces and centrally run cities to remove difficulties for many projects out of a total of 1,533 projects that are facing difficulties.

Propose that the Ministry of Agriculture and Environment consider proposing to the Prime Minister to abolish the regulation "The State does not refund the difference" in Points b, Clause 6, Article 5, Point b, Clause 4, Article 6, Point b, Clause 3, Article 7 and Point c, Clause 2, Article 8 of Decree No. 76/2025/ND-CP.

Because, according to Mr. Chau, these points may not be consistent with the provisions of Clause 3, Article 51 of the 2013 Constitution, not in accordance with the provisions of Article 163 of the 2015 Civil Code and not in accordance with Resolution No. 170/2024/QH15 of the National Assembly.

At the same time, it is proposed to supplement the mechanism of "The State refunds the difference" to investors at points b, clause 6, Article 5, Point b, Clause 4, Article 6, Point b, Clause 3, Article 7 and Point c, Clause 2, Article 8 of Decree No. 76/2025/ND-CP to ensure the consistency and unity of the legal system and reasonable understanding.

CAO NGUYÊN
RELATED NEWS

A series of abandoned projects cause waste in Bac Ninh

|

Some projects in Bac Ninh such as the Nhan Hoa - Phuong Lieu Industrial Park project and the Science - Education Union Project are behind schedule and have been abandoned for many years, causing waste of resources and public outrage.

Speed up the removal of 2 obstacles at the nearly 1,000-hectare tourism complex project

|

Binh Thuan and departments and branches speed up the removal of 2 remaining problems in the nearly 1,000-hectare tourist area complex project to be able to re-implement in July 2025.

Ha Tinh removes suspended projects to open the way to welcome new investors

|

In recent times, Ha Tinh province has stepped up the urging and handling of slow-progressing projects and suspended projects to improve the effectiveness of attracting investment and creating jobs for workers in economic zones in the area.

Fishing boat sinks after collision with cargo ship, 17 crew members rescued but 1 person dies

|

Lam Dong - A fishing boat carrying 17 crew members sank after colliding with a cargo ship. Fishermen were rescued in time but 1 person died.

Launching a contest to learn about major resolutions of the Party, Fatherland Front and Trade Union

|

On the afternoon of July 6, the Party Committee of the Vietnam General Confederation of Labour organized the Launching Ceremony of the online contest "Understanding the Resolution of the 14th National Congress of the Party, Resolution of the 1st Congress of the Party Committee of the Vietnam Fatherland Front, Central Agencies, Resolution of the 14th Congress of the Vietnam Trade Union, term 2026-2031".

More than 160 children receive free examination and surgery for cleft lip and palate defects

|

More than 160 children were screened and given free surgery for cleft lip and palate defects in a humanitarian program at E Hospital.

Quang Tri directs handling of garbage surrounding many roads in Dong Hoi

|

Quang Tri - After reflecting on the situation of garbage surrounding many central roads in Dong Hoi ward, the People's Committee of Quang Tri province has directed local authorities to inspect and handle it.

Ha Tinh Department of Education and Training speaks out about an exam room with 15 candidates scoring 10 points

|

Ha Tinh - The Department of Education and Training has just released information related to the incident of 15/22 candidates achieving a score of 10 in mathematics in the 2026 high school graduation exam in an exam room.

A series of abandoned projects cause waste in Bac Ninh

Vân Trường |

Some projects in Bac Ninh such as the Nhan Hoa - Phuong Lieu Industrial Park project and the Science - Education Union Project are behind schedule and have been abandoned for many years, causing waste of resources and public outrage.

Speed up the removal of 2 obstacles at the nearly 1,000-hectare tourism complex project

Duy Tuấn |

Binh Thuan and departments and branches speed up the removal of 2 remaining problems in the nearly 1,000-hectare tourist area complex project to be able to re-implement in July 2025.

Ha Tinh removes suspended projects to open the way to welcome new investors

TRẦN TUẤN |

In recent times, Ha Tinh province has stepped up the urging and handling of slow-progressing projects and suspended projects to improve the effectiveness of attracting investment and creating jobs for workers in economic zones in the area.