On May 31, Dong Nai City People's Committee just decided to approve the Project on compensation, support, and resettlement to create a clean land fund to organize land use rights auctions for land areas within the 1/2,000 scale zoning plan of Long Thanh Urban - Commercial - Service Area in Binh An commune and Long Thanh ward.
The project has a total recovered land area of about 1,164.5 ha invested by the Dong Nai City Land Fund Development Center, including 4 land plots.
Zone 1 (sub-zone A) area is about 610.5 ha; Zone 2 (sub-zone E) area is about 329 ha; Zone 3 (sub-zone I, sub-zone II belonging to the old Binh Son Resettlement Area) has an area of about 170 ha; Zone 4 has an area of about 55 ha.
The total investment of the project is more than 983 billion VND, with capital advanced from the Dong Nai City Land Development Fund.
Implementation time from 2026-2027. In which, in 2026, procedures will be prepared to submit for appraisal and approval of the project; submit to the Dong Nai City People's Council for approval of the land acquisition list; deploy measurement and inventory work, complete the work of preparing compensation and support plans, and receive land for 4 land plots in August 2026.