Bach Mai Hospital facility 2 staff housing project urgently completed

NGUYỄN TRƯỜNG |

Ninh Binh - The investor and construction unit are urgently completing the social housing project for officials and employees of Bach Mai and Viet Duc Hospitals, facility 2.

To create conditions for food and accommodation for officials and employees when returning to work at Bach Mai Hospital and Viet Duc Friendship Hospital facility 2 in Ninh Binh, Ninh Binh province is focusing on accelerating the construction progress of the social housing project for officials and employees of the above 2 hospitals.

Present at the construction site of 2 social housing projects for officials and employees of Bach Mai Hospital and Viet Duc Friendship Hospital facility 2 in Ninh Binh on December 30, according to records of Lao Dong Newspaper reporters, contractors are mobilizing manpower, machinery and equipment to accelerate the project progress.

Don vi thi co da hoan thien Anh: Nguyen Truong
The construction unit has completed the steel reinforcement part, mixing rack and concreted the 7th floor wall of the social housing project for officials and employees of Bach Mai Hospital facility 2 in Ninh Binh. Photo: Nguyen Truong

Mr. Do Huy Tuan - Deputy Director of the Construction Investment Project Management Board (under the Ninh Binh Provincial Department of Construction), the investor of the above 2 projects - said that 2 social housing investment projects for officials and doctors of Bach Mai Hospital and Viet Duc Facility 2 in Ninh Binh were started in August 2025, according to the approved decision, the completion time is in 2028. However, before the actual requirements, the unit is directing contractors to work overtime even at night to shorten the project completion time.

We are striving to complete and put into use in August 2026. Up to now (December 30, 2025 - PV), the construction volume of the above 2 projects has reached about 70% and the entire rough construction will be completed in January 2026, expected to be put into use in August 2026" - Mr. Tuan said.

Cac nha thau huy dong nhan luc lam tang ca ban dem de kip tien do. Anh: Nguyen Truong
Contractors mobilize manpower to work overtime at night to keep up with the schedule. Photo: Nguyen Truong

Also according to Mr. Tuan, the social housing project for officials and employees of Bach Mai Hospital facility 2, is built on an area of about 1.2ha, including 2 10-story social housing buildings on land plots CT01 and CT02, with a maximum construction density of 40%. Scale of 216 apartments/1 building, total number of 432 apartments, construction floor area of about 11,500m2/1 building and construction of auxiliary items to ensure synchronous connection of technical infrastructure according to the approved plan such as internal traffic roads, parking lots, electricity supply system, water supply, rainwater drainage, wastewater drainage, greenery... Total investment is 284.97 billion VND.

Up to now, the capital allocated for the project is 82 billion VND and has been disbursed. The project does not require site clearance and has been allocated land partly by the Provincial People's Committee for implementation. The contractor has constructed the steel reinforcement, mixed-and-breaker and concreted the wall of the 7th floor.

Cong nhan thi cong tai Du an nha o xa hoi danh cho can bo, nhan vien Benh vien Huu nghi Viet Duc co so 2 tai Ninh Binh. Anh: Nguyen Truong
Workers constructing at the social housing project for officials and employees of Viet Duc Friendship Hospital facility 2 in Ninh Binh. Photo: Nguyen Truong

For the project to invest in building social housing for officials and employees of Viet Duc Hospital facility 2 in Ninh Binh, it is built on an area of about 0.59ha, on land plot OCT-01, including 1 10-story social housing building, construction density of about 45%, scale of 216 apartments, construction floor area of about 11,500m2 and construction of auxiliary items to ensure synchronous connection of technical infrastructure according to the approved plan. The total investment is 143.4 billion VND. Up to now, the allocated capital is 41 billion VND and has been disbursed. The construction unit has processed steel reinforcement, mixed-and-breaker and concreted the 5th floor wall of the project.

NGUYỄN TRƯỜNG
RELATED NEWS

SOON complete facility 2 of Bach Mai and Viet Duc Hospitals to serve the people

|

The Ministry of Health needs to continue to focus highly and soon complete the remaining items of facility 2 of Bach Mai and Viet Duc Hospitals.

Inauguration of Bach Mai and Viet Duc Hospitals, Facility 2 in Ninh Binh

|

Ninh Binh - On the morning of December 19, the Ministry of Health held an inauguration ceremony for the second facility of Bach Mai Hospital and Viet Duc Friendship Hospital in Ninh Binh.

Ministry of Health inaugurates Bach Mai Hospital, Viet Duc Facility 2

|

According to Minister of Health Dao Hong Lan, the implementation of the two second facility projects of Bach Mai Hospital and Viet Duc Hospital, the Ministry of Health encountered unprecedented difficulties.

Hanoi urgently clears the construction of Ring Road 1, will build 2 direct overpasses

|

Hanoi - After receiving the clean site, the investor will deploy the construction of road items and 2 overpasses to directly open the Ring Road 1 project, Hoang Cau - Voi Phuc section.

Cold air is about to cause thunderstorms, the North has places below 19 degrees Celsius

|

Forecast of the first cold air wave of the season with weak intensity, the North turns cool at night and in the morning, the Northern mountainous region has places with the lowest temperature below 19 degrees Celsius.

Businesses mobilize bonds with interest rates up to 13%, behind the trillion-VND capital flow

|

The interest rate of corporate bonds in some lots is 13%/year, while the purpose of capital mobilization ranges from project investment to debt restructuring.

Turning on AI music at coffee shops, on passenger cars, why can copyright fees still be charged

|

When AI music appears in cafes, restaurants, and buses, a question arises: Is it necessary to pay copyright fees if you don't turn on the recording of the real singer?

Infrastructure upgrade project messy in the center of Da Nang city

|

Da Nang - The tens of billions of VND infrastructure project in the city center is under construction in a mess, unfinished, disrupting daily life and lurking at the risk of accidents for people.

SOON complete facility 2 of Bach Mai and Viet Duc Hospitals to serve the people

Thùy Linh |

The Ministry of Health needs to continue to focus highly and soon complete the remaining items of facility 2 of Bach Mai and Viet Duc Hospitals.

Inauguration of Bach Mai and Viet Duc Hospitals, Facility 2 in Ninh Binh

NGUYỄN TRƯỜNG |

Ninh Binh - On the morning of December 19, the Ministry of Health held an inauguration ceremony for the second facility of Bach Mai Hospital and Viet Duc Friendship Hospital in Ninh Binh.

Ministry of Health inaugurates Bach Mai Hospital, Viet Duc Facility 2

Thùy Linh |

According to Minister of Health Dao Hong Lan, the implementation of the two second facility projects of Bach Mai Hospital and Viet Duc Hospital, the Ministry of Health encountered unprecedented difficulties.

Hanoi urgently clears the construction of Ring Road 1, will build 2 direct overpasses

SÓNG HỮU |

Hanoi - After receiving the clean site, the investor will deploy the construction of road items and 2 overpasses to directly open the Ring Road 1 project, Hoang Cau - Voi Phuc section.