Two unfinished resort projects have degraded in Lang Co Bay

PHÚC ĐẠT |

Along the coast of Lang Co Bay (Phu Loc District, Hue City), two resort projects worth hundreds of millions of USD were built unfinished and then abandoned, many unused items have degraded.

Many years ago, Chan May - Lang Co Economic Zone had million-dollar projects formed. Large projects and works have been invested in and started construction to serve the sightseeing and resort needs of tourists when coming to Lang Co Bay, one of the most beautiful bays in the world.

However, many large-scale tourism projects in Lang Co - Canh Duong national tourist area (belonging to Lang Co - Chan May Economic Zone) were built unfinished and then temporarily suspended, such as the Minh Vien International Resort project and the Mediterranean Legendary Resort project.

The Minh Vien International Resort project started construction in December 2018 with a scale of up to 102.7 hectares with a total estimated capital of 368 million USD, invested by Minh Vien International Joint Stock Company, including a hotel system, resort, conference center and supporting services that meet 5-star international standards...

And the Mediterranean Legendary Resort project is invested by Vinacoland House Construction and Development Joint Stock Company, implemented on a 6.9ha area started in January 2016 with a total investment of more than VND 600 billion. As planned, this will be a general service center, resort with 52 villas, hotel rooms, halls and 5 -star standard apartments. At the time of commencement, the investor pledged to mobilize all resources to ensure the project completion progress for 24 months, that is, in 2018, it is possible to put into operation. According to the plan, Minh Vien International Resort Resort project will be completed and put into operation in the first quarter of 2024; In particular, phase 1 is completed and put into operation at the end of 2019. In 2018, it can be put into operation and use the legendary resort project of the Mediterranean. However, by May 525, both of these projects were not yet completed, many constructions were still unfinished. Reported by PV Lao Dong Newspaper, over the years, both projects have not been carried out, no workers or any machines work. However, the project was wild, gradually being degraded. In Minh Vien International Resort, many ceiling locations, walls appear cracked and patchy. Although the project has not been put into operation, the fire protection system, terrain cars, some glass panels here are no longer intact. The reason for the two projects to stop construction for many years is thought to be because the investor has difficulty in capital.

Talking to PV Lao Dong newspaper, Mr. Ho Huy Hinh - representative of Hue City Economic and Industrial Zone Management Board - said that the current situation of Minh Vien International Resort projects projects are negotiating and unifying the terms of capital contribution and being promoted to reboot the project. And the Legendary Mediterranean Resort project was the policy for the Bank to organize a auction to find new investors to transfer the project under the collateral.

PHÚC ĐẠT
TIN LIÊN QUAN

1,500 billion VND project to expand the southern gateway of Ho Chi Minh City after more than 2 years of construction

|

HCMC - The project to expand National Highway 50 through Binh Chanh District has reached 67% of the volume, and there are still some site clearance problems affecting the construction progress.

Real estate prices are starting to increase as a 2,100 billion VND road project is restarted

|

Thai Nguyen - The Bac Son extended road project worth VND 2,100 billion is being accelerated, leading to an increase in land prices along both sides of the route.

Hue temporarily suspends district and commune-level projects

|

HUE - Hue City People's Committee requested to temporarily suspend a series of projects using the budget, preparing to rearrange commune-level administrative units according to the 2-level model.

The West's apology to Russia is not a ticket of thong qua

|

Russian President Vladimir Putin outlined conditions for Western companies to return to Russia, saying the apology was not a transit ticket.

Special features at Uncle Ho's stilt House in Dong Thap

|

Dong Thap - A place to preserve the relics of two historical figures: the patriotic grandfather Nguyen Sinh Sac and the great President Ho Chi Minh.

Clarifying and deepening the position and role of the Fatherland Front

|

The delegate emphasized that the draft adds more content that has clarified and deepened the position and role of the Vietnam Fatherland Front.

Disciplining female vice principals in Hue for having unclean relationships

|

HUE - A female vice principal in Hue was dismissed from the position of Deputy Secretary of the Party Cell for violating ethics and maintaining inappropriate relationships with married people.

1,500 billion VND project to expand the southern gateway of Ho Chi Minh City after more than 2 years of construction

Anh Tú |

HCMC - The project to expand National Highway 50 through Binh Chanh District has reached 67% of the volume, and there are still some site clearance problems affecting the construction progress.

Real estate prices are starting to increase as a 2,100 billion VND road project is restarted

Lam Thanh |

Thai Nguyen - The Bac Son extended road project worth VND 2,100 billion is being accelerated, leading to an increase in land prices along both sides of the route.

Hue temporarily suspends district and commune-level projects

PHÚC ĐẠT |

HUE - Hue City People's Committee requested to temporarily suspend a series of projects using the budget, preparing to rearrange commune-level administrative units according to the 2-level model.