Decree 217/2026/ND-CP specifically stipulates the dossier for applying for a construction permit for individual houses.

The Government has issued Decree 217/2026/ND-CP (effective July 1, 2026) detailing a number of articles of the 2025 Construction Law on construction activity management. In which, Article 60 of this Decree stipulates the dossier for applying for a construction permit for individual houses. Specifically:

Article 60. Dossier requesting a construction permit for individual houses

1. Application for a construction permit according to the provisions of Form No. 01 Appendix II issued together with this Decree.

2. One of the legal land documents for issuing a construction permit as prescribed in Article 55 of this Decree; written opinion of a provincial-level cultural specialized agency (if required by law on cultural heritage).

3. Construction design documents:

a) For individual houses of households and individuals: accompanying set of construction design drawings; results of administrative procedures according to the provisions of law on fire prevention and fighting and rescue (if required); Report on the results of construction design appraisal in cases where construction law requires, including: drawings of the construction site on the land plot accompanied by a project location diagram; drawings of the floors, vertical faces and main sections of the project; drawings of the foundation surface and foundation sections accompanied by a connection diagram of the technical infrastructure system outside the project including water supply, drainage, electricity supply; commitment to ensure safety for adjacent projects;

b) For individual housing projects of organizations: set of construction design drawings in construction design dossiers deployed after the project is approved or construction drawing design for projects only requiring the preparation of an approved economic - technical report according to the provisions of law on construction accompanied by the results of administrative procedures according to the provisions of law on fire prevention and fighting and rescue (if required); Report on the results of construction design appraisal in cases where construction law requires, including: drawing of the construction site on the land plot accompanied by a project location diagram; drawing of the floors, vertical surfaces and main sections of the project; drawing of the foundation surface and foundation sections accompanied by a diagram of connection to the technical infrastructure system outside the project including water supply, drainage, electricity supply; commitment to ensure safety for adjacent projects.

Như Hạ
RELATED NEWS

Application dossier for new construction permit from July 1, 2026

|

From July 1, 2026, Decree 217/2026/ND-CP details the dossier for applying for a construction permit.

Ministry of Construction clarifies cases where construction permits are not exempted

|

The Ministry of Construction said that individual houses in construction areas identified in the commune's general plan are not eligible for exemption from construction permits.

Ministry of Construction answers about issuing new construction permits for individual houses

|

The Ministry of Construction's agency has just resolved citizens' questions related to the issuance of new construction permits for individual houses.

Ho Chi Minh City seeks opinions on naming lines and metro stations to avoid confusion

|

Ho Chi Minh City is seeking public opinions on the naming of metro lines and stations to build a system of easy-to-remember and easy-to-recognize names, limiting inadequacies.

Ministry of Industry and Trade informs about goods not yet reduced according to gasoline prices

|

Representatives of the Ministry of Industry and Trade said that not all points of sale fully supply all types of gasoline and the price of each type of gasoline may be different.

Da Nang will organize a forum to gather opinions and rebuttals before choosing a logo

|

Da Nang - The city is listening to the contributions and criticisms of the people, and will carefully choose the symbol of the new city.

Ministry of Industry and Trade has not finalized peak hour electricity prices for households

|

The Ministry of Industry and Trade said that it has only proposed to study applying electricity prices during peak hours to households, and has not applied them immediately.

Government Inspectorate clearly states a series of violations of the Vietnam Maritime and Waterway Administration

|

The Government Inspectorate pointed out violations in the maintenance of maritime works at the Vietnam Maritime and Waterway Administration.

Application dossier for new construction permit from July 1, 2026

Như Hạ |

From July 1, 2026, Decree 217/2026/ND-CP details the dossier for applying for a construction permit.

Ministry of Construction clarifies cases where construction permits are not exempted

Như Hạ |

The Ministry of Construction said that individual houses in construction areas identified in the commune's general plan are not eligible for exemption from construction permits.

Ministry of Construction answers about issuing new construction permits for individual houses

Như Hạ |

The Ministry of Construction's agency has just resolved citizens' questions related to the issuance of new construction permits for individual houses.